| Course | QSO 340 Project Management |
|---|---|
| Module | Module 6 |
| Paper type | Earned value analysis assignment |
| Length | About 1,010 words, 6 pages |
| Format | APA 7 student paper |
| School | Southern New Hampshire University |
| Program | BS Business Administration |
| Updated | October 2026 |
Free sample paper for QSO 340 Module 6
Week 20 by the Numbers: An Earned Value Analysis of a Food Bank's Warehouse System Project
[Student Name]
Southern New Hampshire University
QSO 340: Project Management
Module Six Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Week 20 by the Numbers: An Earned Value Analysis of a Food Bank's Warehouse System Project
The Baseline
The composite food bank's warehouse management system project has a budget at completion of 580,000 dollars for planned work, plus a 60,000 dollar contingency reserve held by the sponsor. The schedule baseline, adjusted after the fast-tracking decision in Module 4, plans cutover in week 36. This review uses data at the end of week 20, when requirements and design should be complete, configuration should be about three-quarters done and hardware installation should be finished. Earned value management rests on three numbers (Fleming & Koppelman, 2010). Planned value is the budget attached to the work the schedule says should be finished by now. Earned value is the budget attached to the work that is in fact finished. Actual cost is the money really spent to finish it.
Status by Work Package
Table 1 shows the three measures for each work package under way or finished by week 20.
Table 1
Earned Value by Work Package, End of Week 20
| Work package | Planned value | Earned value | Actual cost | Percent complete |
|---|---|---|---|---|
| Project management | $30,000 | $30,000 | $32,000 | On plan |
| Requirements and design | $60,000 | $60,000 | $58,000 | 100% |
| System configuration (budget $128,000) | $96,000 | $70,400 | $98,000 | 55% |
| Hardware (budget $58,000) | $58,000 | $58,000 | $66,000 | 100% |
| Data cleanup (budget $22,000) | $18,000 | $17,600 | $17,000 | 80% |
| Total | $262,000 | $236,000 | $271,000 |
Note. Composite figures. Earned value equals each work package's budget multiplied by its percent complete.
Variances and Indices
Cost variance is earned value minus actual cost: 236,000 minus 271,000 dollars, or negative 35,000 dollars. The project has spent 35,000 dollars more than the budgeted value of the work it has completed. Schedule variance is earned value minus planned value: 236,000 minus 262,000 dollars, or negative 26,000 dollars, meaning the project has completed 26,000 dollars less work than planned by this date.
Dividing earned value by actual cost gives a cost performance index of about 0.87: each dollar spent has produced about 87 cents of planned work. Dividing earned value by planned value gives a schedule performance index of about 0.90: the project is progressing at about 90 percent of the planned rate. Both indices are below 1.0, and together they describe a project that is behind schedule and over budget at the same time, which rules out the comforting explanation that it is simply spending ahead of plan.
Forecasting the Final Cost
If the project continues at its current cost efficiency, the estimate at completion is the budget divided by the cost performance index: 580,000 divided by 0.871, or about 666,000 dollars. That is about 86,000 dollars over budget, more than the entire 60,000 dollar contingency reserve. If the overrun so far proves to be a one-time problem and the remaining work is done at the budgeted rate, the estimate at completion is the actual cost plus the remaining budgeted work: 271,000 plus 344,000 dollars, or 615,000 dollars, which the contingency could absorb. The to-complete performance index, the cost efficiency needed on remaining work to finish within the 580,000 dollar budget, is about 1.11. Practitioners of earned value have long observed that a project's cost performance index tends to settle early and seldom recovers much afterward (Fleming & Koppelman, 2010), so the more pessimistic forecast deserves serious attention.
Where the Variance Comes From
Two work packages explain almost all of the problem. System configuration accounts for 25,600 dollars of the schedule variance and 27,600 dollars of the cost variance: it is only 55 percent complete, not 75, and has already cost 98,000 dollars. The cause is scope growth. Warehouse staff requested custom fields for tracking donor sources and the funder's reporting categories, each approved informally by the vendor without going through change control. Hardware finished on time but cost 8,000 dollars more than budgeted, because extending wireless coverage into the freezer required more access points than the site survey estimated. The other work packages are close to plan.
Corrective Actions
Four actions are recommended. First, stop informal changes: every configuration request must now go through the written change control process in the project plan, with its cost and schedule effect estimated before approval. Second, review the custom fields already added and defer any that are not needed for go-live to a second phase after the holiday season. Third, release 24,000 dollars of contingency for the second configuration consultant considered in Module 4, which would recover about two weeks and protect the week 36 cutover, and ask the sponsor to approve it now rather than after the schedule slips further. Fourth, re-baseline the remaining configuration work with the vendor so that future earned value reports measure progress against a realistic plan (Project Management Institute [PMI], 2021; Kerzner, 2022). If these actions work, the project should finish near the 615,000 dollar forecast, within the contingency; if the cost performance index remains near 0.87, the sponsor will need to seek additional funding or reduce scope.
Reporting the Findings to the Sponsor
The analysis must reach the sponsor in a form that supports a decision rather than as a table of indices. The status report for week 20 will therefore open with one sentence: the project is about 10 percent behind schedule and 13 percent over budget on the work completed, and at current performance it would need about 26,000 dollars more than its contingency. It will then state the cause, informal configuration changes and higher freezer wireless costs, and the decision required, approval to use 24,000 dollars of contingency for a second consultant and a freeze on informal changes. The indices themselves will appear in an attachment for the board treasurer, who is familiar with them. Presenting the problem this way matters because a sponsor who sees only a cost performance index of 0.87 may not grasp that the holiday deadline is at stake, while a sponsor who hears only that the project is behind may not see that the fix costs money. Earned value earns its place in project management precisely because it connects schedule and cost in one measurement, and the report should preserve that connection in plain language. The next review, at week 24, will show whether the corrective actions have moved the indices toward 1.0.
References
Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.
Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). Wiley.
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.
What the QSO 340 Module 6 instructions ask for
The Module 6 assignment in QSO 340 usually asks for an earned value analysis of a project at a point in time. Prompts commonly provide planned value, earned value and actual cost, or the data to calculate them, and ask for variances, indices, a forecast and an interpretation with recommendations. Some sections use the course project. The paper is short, with tables and formulas, cited in APA 7. Interpret each number in words. Break the analysis down by work package if the data allow, since totals can hide where the problem is. State the reporting date and the budget at completion at the top. The QSO 340 Module 6 guidelines list the measures required.
How this QSO 340 Module 6 earned value analysis assignment example is built
The baseline section explains the planned budget and schedule through week 20. A table shows planned value, earned value and actual cost for each work package and the total. The variance section calculates cost and schedule variance with formulas and signs. The index section reports the cost performance index below one and the schedule performance index slightly below one, meaning over budget and a little behind. The forecast section calculates the estimate at completion and the variance at completion. The source section shows that data migration accounts for most of the overrun. Corrective actions include adding a data specialist and resequencing two migration tasks. The reporting section translates the numbers into a sponsor update.
Where the QSO 340 Module 6 rubric puts the points
QSO 340 grades the earned value assignment on the calculations, the interpretation, the analysis of variance sources and the recommendations, with each QSO 340 row on SNHU's four levels. Calculations carry heavy weight; graders check formulas, signs and the forecast. Interpretation earns credit when every index is turned into a sentence the director would understand. Tracing variance to work packages shows deeper analysis. Recommendations score well when they target the source, here the data migration package. A forecast that names which formula was used, and why, earns credit too. A plain-language note to the sponsor shows that the numbers can be used, not only calculated.
QSO 340 Module 6 help: the mistakes that cost points
Earned value papers often lose points by mixing up the signs of variances or the meaning of an index above or below one. Another common gap is reporting totals without finding which work package caused the problem. Some students forecast the final cost without saying which formula they used or why. Others list numbers without interpretation. Watch planned value against earned value, since confusing them reverses the schedule conclusion. Finally, translate for the sponsor, because a QSO 340 grader expects the analysis to end with a few sentences a nonexpert could act on, such as the project will finish about eight percent over budget unless migration is fixed.
Get QSO 340 Module 6 written to your instructions
Share the QSO 340 Module 6 instructions, rubric and project figures you were assigned. An earned value analysis with forecasts and corrective actions comes back within 24 to 48 hours; the first is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 340 papers and related BS Business Administration samples
- QSO 340 Module 1 Projects and Operations Discussion: Food bank projects versus operations
- QSO 340 Module 2 Project Selection Case Analysis: Choosing among three food bank projects
- QSO 340 Module 3 Project One Project Plan: Project plan for a warehouse system
- QSO 340 Module 4 Project Schedule and Critical Path Assignment: Critical path against a holiday deadline
- QSO 340 Module 5 Project Planning Analysis: Point-of-sale rollout across 14 stores
- QSO 340 Module 7 Project Two Status Report: Week 30 status report to the sponsor
- QSO 340 Module 8 Project Closure and Lessons Learned Report: Closing the warehouse project
- PSY 270 Module 4 Performance Appraisal and Training Report: Fixing appraisal and training for technicians
- HRM 400 Module 8 Discussion: Did Ownership Take Hold?
- BUS 225 Module 5 Business Writing Assignment: An Email the Owner Will Actually Read
- BUS 307 Module 8 Discussion: Protecting the Brand on the Jar
QSO 340 Module 6 questions, answered
What does QSO 340 Module 6 usually cover?
The sixth module of a project management course commonly covers project budgeting and cost control, including earned value management: planned value, earned value, actual cost, cost and schedule variances, performance indices and forecasts of final cost. Assignments ask students to calculate these for a project and interpret them.
What is earned value?
Earned value is the budgeted cost of the work actually completed. If a 96,000 dollar work package is 55 percent complete, its earned value is 52,800 dollars, regardless of how much was actually spent. Comparing earned value with planned value shows schedule performance, and comparing it with actual cost shows cost performance.
How is the estimate at completion calculated?
A common method divides the budget at completion by the cost performance index, which assumes future work will continue at the current cost efficiency. Another adds the remaining budgeted work to the actual cost to date, which assumes future work will be performed at the budgeted rate.
Where can I find a free QSO 340 Module 6 sample?
The complete analysis is on this page: a food bank warehouse system project at week 20, with planned value, earned value and actual cost by work package, variances, indices, a forecast and corrective actions. Use it as a model.
What does a cost performance index below one mean?
It means the project is getting less work done per dollar than planned, so it is over budget for the work completed. A CPI of 0.9, for example, means each dollar spent produced about ninety cents of planned work.