QSO 340 Module 7 Project Two Status Report Example

Reviewed by Portia Lambrick, MBA

This QSO 340 Module 7 project is a status report written for the sponsor of the composite food bank's warehouse software rollout at week 30, six weeks before cutover. SNHU QSO 340 (QSO-340) has BS Business Administration students report status to a decision maker in Project Two, and the report leads with the overall health rating, amber and improving. Progress against milestones follows in a short table. Budget and earned value figures show the cost overrun narrowing after a data specialist joined. A risk update names the top risks and changes since the last report. Open issues are listed with owners and dates. The report ends with decisions requested: approval of go-live criteria and a contingency plan if inventory accuracy falls short. It is written as a memo a busy sponsor could read in five minutes.

CourseQSO 340 Project Management
ModuleModule 7
Paper typeProject Two status report memo
LengthAbout 780 words, 4 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Business Administration
UpdatedOctober 2026

Free sample paper for QSO 340 Module 7

1

Memorandum

To: Executive Director (Project Sponsor), Tri-River Regional Food Bank

From: Director of Operations, Project Manager

Date: [Date], end of week 30

Re: Warehouse management system project status and two decisions requested

 

Overall Health: Amber, Improving

The project is on track to cut over in week 36, before the November 15 deadline, and cost performance has improved since the week 20 review. It remains amber rather than green because of one open data migration issue and a staffing risk in the main warehouse. Two decisions are requested by next Friday: approval of the cutover go and no-go criteria in the final section, and approval of 6,500 dollars of contingency for an additional evening training session for warehouse staff.

What this page is doingThe first paragraph gives health, the reason for the rating and the decisions needed, so a sponsor who reads nothing else can act. Leading with the conclusion is the core convention of status reporting.
2

Progress Against Milestones

System configuration was completed in week 26, two weeks later than the original plan but on the revised plan after the second vendor consultant joined in week 21. Warehouse user testing finished in week 28 with 41 defects found, of which 38 are fixed and three are minor display issues scheduled for the week 33 release. The pantry pilot began in week 27; six of the eight pilot pantries have placed at least two online orders, and the other two are receiving phone support. The second trial data migration was completed in week 29. Warehouse staff training begins in week 31 as planned. Pantry training, fast-tracked to overlap the last two weeks of the pilot, starts in week 31 with the eight pilot pantries acting as peer helpers for the others, an arrangement the pilot pantries proposed themselves.

Budget and Earned Value

At the end of week 30, planned value is 452,000 dollars, earned value is 438,000 dollars and actual cost is 471,000 dollars. The cumulative cost performance index has risen from 0.87 at week 20 to 0.93, and the schedule performance index from 0.90 to 0.97. The improvement reflects the change control freeze on custom fields and the consultant's speed on configuration. At the current cumulative index, the estimate at completion is about 624,000 dollars, within the 640,000 dollar total including contingency. Of the 60,000 dollar contingency, 24,000 dollars has been used for the consultant; 36,000 dollars remains (Fleming & Koppelman, 2010).

Risk Update

One risk has been retired: cold-rated scanners performed reliably in freezer testing at 5 degrees below zero Fahrenheit, although battery life is about 30 percent shorter, which is handled by a second battery for each freezer scanner at a cost of 1,400 dollars already within the hardware budget.

Two risks are new. First, the main warehouse supervisor, who is responsible for testing and training in the responsibility matrix, has scheduled surgery in week 34. Probability: certain; impact: medium. Response: the second-shift lead will shadow the supervisor during training in weeks 31 to 33 and take over go-live coordination. Second, the holiday food drive schedule has been moved earlier this year, with the first large deliveries arriving in week 37. Probability: high; impact: high. Response: cutover must finish in week 36 with no slack, which is why the go and no-go criteria below matter.

The pantry adoption risk remains open but is trending favorably given the pilot results. The project's largest remaining risk is not the software; it is the one week between cutover and the start of the holiday rush.

Open Issues

Issue 1: the second trial migration found that 3 percent of product records, about 420 items, have mismatched units of measure, such as cases recorded as pounds. Owner: inventory analyst. Action: correct in the source spreadsheets and rerun validation by week 33. Issue 2: two pilot pantries with part-time volunteers have not logged in. Owner: agency relations manager. Action: in-person visit in week 31. Issue 3: the funder's quarterly report template changed; the report has not yet been tested in the new system. Owner: project manager. Action: vendor to deliver the revised report in week 32.

Decisions Requested

Decision 1: approve the following go and no-go criteria, to be reviewed in week 35. The project will go live only if all open data issues are resolved and the final trial migration reconciles to within 0.5 percent of physical counts; at least 18 of 22 warehouse staff have completed training and passed a practical check; the funder report produces correct results from test data; and a two-week paper fallback procedure has been rehearsed. If any criterion is not met, cutover moves to January 6, after the holiday period, and the food bank continues on its current process (Project Management Institute [PMI], 2021).

Decision 2: approve 6,500 dollars from the remaining contingency for an evening training session so that second-shift warehouse staff can be trained without overtime pay, which would otherwise cost more.

The next status report will be issued at the end of week 32, following the reporting cadence set in the project plan (Kerzner, 2022).

References

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). Wiley.

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

What the QSO 340 Module 7 instructions ask for

Project Two in QSO 340 usually asks for a project status report or communication to stakeholders. QSO 340 prompts usually want overall health, schedule and budget progress, risks and issues and the decisions the sponsor must make. Memo format is common. Use earned value or other measures from earlier modules, updated to the report date. A short milestone table usually works better than paragraphs. Separate risks from issues clearly. Keep the report short and lead with what the sponsor most needs to know. Cite the QSO 340 textbook if you explain methods. The QSO 340 Project Two guidelines list required sections and whether a health rating system is expected.

How this QSO 340 Module 7 project two status report example is built

After the To, From, Date and Subject lines comes a one-line health rating with its reason. The milestones table shows each milestone's planned date, forecast date and status. The budget section gives the cost performance index and estimate at completion, and explains the improvement since week 20. The risk update lists the top three risks with changes in probability or impact and new responses. The issues section separates problems already happening, such as a delayed label printer, from risks, with owners and target dates for each. The decisions section asks the sponsor to approve go-live criteria, such as inventory accuracy above a threshold, and a contingency plan.

Where the QSO 340 Module 7 rubric puts the points

QSO 340 grades Project Two on the status summary, progress reporting, the risk and issue updates and the decisions requested, with QSO 340 rows on SNHU's four levels. The summary carries heavy weight; graders reward a health rating with a clear reason up front. Progress earns credit when it uses measures from earlier work. Risks and issues score well when they are separated and each has an owner. Decisions should be specific enough to approve. Memo format and brevity matter, since the assignment tests communication with a busy reader as much as project knowledge. Earned value figures should match the Module 6 work or explain the change.

QSO 340 Module 7 help: the mistakes that cost points

Status reports often lose points by burying the overall status at the end. Another common gap is mixing risks, which might happen, with issues, which are already happening. Some students write long narratives instead of tables and short sections. Others report numbers without saying whether they are good or bad. Watch decisions; a report that asks for nothing leaves the sponsor unsure why it was sent. Finally, keep it to what the sponsor needs, because a QSO 340 grader reads the memo as an executive would and expects the health, the trend and the decisions in the first half page. Put supporting detail in an attachment. Each open issue needs a named owner and a target date.

Get QSO 340 Module 7 written to your instructions

Send your QSO 340 Project Two guidelines, rubric and your Project One plan. A status report on progress and risks for your project comes back within 24 to 48 hours; your first is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 340 papers and related BS Business Administration samples

QSO 340 Module 7 questions, answered

What does QSO 340 Project Two require?

Project Two commonly asks students to write a status report on the project planned in Project One, communicating progress, schedule and budget performance, risks and issues to stakeholders, and recommending actions. The guidelines specify the audience and the elements to include.

What is the difference between a risk and an issue?

A risk is an uncertain event that might happen and would affect the project if it did. An issue is a problem that has already happened and needs to be resolved. Risks are managed with responses planned in advance; issues are managed with actions, owners and deadlines.

What are go and no-go criteria?

Go and no-go criteria are conditions agreed in advance that must be met before a major step, such as going live with a new system. Setting them before the decision date keeps the choice objective and prevents pressure to proceed when the system or the people are not ready.

Where can I find a free QSO 340 Module 7 Project Two example?

One is above in full: a week 30 status memo to a food bank's sponsor, with a health rating, milestones, earned value, risks, issues and decisions requested. Use it as a model for project communication.

What is a red, amber, green status rating?

It is a simple color code for project health: green on track, amber at risk but recoverable and red in serious trouble. A good report pairs the color with a one-line reason so the sponsor knows why.