QSO 440 Module 2 Portfolio Selection Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 440 Module 2 Portfolio Selection Assignment sample selects and sequences a project portfolio with a weighted scoring model, mandatory projects and capital and resource constraints. SNHU QSO 440 (QSO-440) assigns portfolio selection in Module 2 of its project management topics course for BS Operations Management students. The organization is Coldwater Valley Electric Cooperative, an invented Missouri utility with eight projects asking for more money and engineering time than it has. The paper scores the projects, separates what the co-op must do from what it chooses to do, fits the rest to a $38 million limit and explains what waits.

CourseQSO 440 Topics in Project Management
ModuleModule 2
Paper typeundergraduate assignment selecting and sequencing a project portfolio with a weighted scoring model, mandatory projects and capital and resource constraints
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 440 Module 2

1

Seventy-Nine, Seventy-Three, Seventy-Two: Selecting the Coldwater Valley Project Portfolio

[Student Name]

Southern New Hampshire University

QSO 440: Topics in Project Management

Portfolio Selection Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe projects, scores, costs and constraints for Coldwater Valley Electric Cooperative in this QSO 440 assignment are invented.
2

Seventy-Nine, Seventy-Three, Seventy-Two: Selecting the Coldwater Valley Project Portfolio

Introduction

Coldwater Valley Electric Cooperative has eight capital projects asking for funding over the next three years. The board has set a capital limit of about $38 million a year, based on what the cooperative can borrow from its lender without raising rates beyond its plan, and the cooperative has 24 line crews and eight engineers. Until now each project was approved on its own case, which is how the total came to exceed the limit. This assignment scores the projects against common criteria, separates mandatory work, fits the portfolio to money and people and explains what waits.

What this page is doingFrames the selection problem.
3

Candidate Projects

Candidate projects

ProjectTotal costYear-one cost, net of grantsMain benefit
Fiber broadband, three phases$96.0 million over 5 years$10.8 millionBroadband for 20,400 rural homes; grant covers about $41 million
Smart meter replacement$14.0 million over 2 years$7.0 millionAbout $1.9 million a year in savings; outage detection
Three substation rebuilds$22.0 million over 3 years$7.3 millionReliability for about 9,000 members
Storm hardening program$9.0 million a year$9.0 millionFewer and shorter outages
Billing and customer system$4.5 million over 18 months$3.0 millionReplaces a system losing vendor support in 2028
Community solar$3.0 million$3.0 millionMember demand; small energy savings
Electric vehicle chargers$0.8 million$0.16 millionGrant covers 80%; member convenience
Warehouse and yard$6.0 million over 3 years$2.0 millionReplaces leased storage
Total$42.3 million

In year one the projects need about $42.3 million net of grants, about $4.3 million more than the limit.

What this page is doingLists what is competing.
4

Criteria and Weights

The cooperative's strategic plan names four goals: reliable service, affordable rates, economic development in the territory and member engagement. The criteria and weights below were agreed with the general manager and approved by the board's finance committee before scoring began, which kept anyone from tuning the weights to suit a favorite project.

Criteria and weights

CriterionWeightMeaning of a high score
Strategic alignment25%Directly advances a plan goal
Member benefit25%Large, visible benefit to many members
Financial return20%Savings or revenue that pay back the cost
Reliability and risk reduction20%Fewer or shorter outages, lower safety or regulatory risk
Feasibility10%Skills, vendors and capacity available

Cooper et al. (1999) found that companies combining several portfolio methods, rather than relying only on financial measures, and applying them consistently tended to achieve better portfolio results. The model above mixes financial and strategic criteria for that reason.

What this page is doingTies selection to strategy.
5

Scores

Weighted scores, 1 to 5 on each criterion

ProjectStrategyMembersReturnReliabilityFeasibilityScore out of 100
Smart meters4354479
Storm hardening3425573
Fiber broadband5522372
Substation rebuilds3425471
Billing system3334364
Community solar3321450
Chargers3221547
Warehouse1132438

Smart meters score highest because they pay back through savings on meter reading and truck rolls and also detect outages. Fiber broadband scores highest on strategy and member benefit but lower on return, because even with the grant it takes many years to pay back, and on feasibility, because the cooperative has never run a telecommunications build. Storm hardening and the substations score on reliability. The warehouse would save lease costs but advances no plan goal, and the leased storage it would replace is adequate for at least three more years.

A sensitivity check moved ten points of weight from member benefit to financial return. The top four stayed the top four, though fiber dropped from third to fourth, which suggests the ranking does not hinge on the weights.

What this page is doingExplains each project's result.
6

Mandatory Work

The billing system scores only 64, but its vendor will end support in 2028, after which the cooperative could not bill members reliably. It is mandatory and is funded first, outside the competition. Storm hardening was also considered for mandatory status, since the board approved it after two winters of long outages, but it is discretionary in pace: the program can be scaled from $9 million to $7 million in a year without breaking a commitment.

What this page is doingSeparates what must be done.
7

Fitting the Constraints

Teller et al. (2012) found that formalizing portfolio management, with clear processes and criteria, was associated with better portfolio results, particularly in portfolios with many interdependent projects. Applying the limit formally, starting from the mandatory billing system and moving down the ranking, the cooperative funds the billing system, smart meters, storm hardening, fiber and the substations, which together need about $37.1 million in year one. Adding the chargers, with their small net cost, brings the total to about $37.3 million. Community solar, at $3 million, would break the limit and moves to year three, when smart meter spending ends. The warehouse is deferred and will be reconsidered in two years.

Money is not the only limit. Engwall and Jerbrant (2003) describe a resource allocation syndrome in multi-project organizations, in which projects compete constantly for the same scarce people and managers spend their time reallocating them. The cooperative's eight engineers cannot design smart meter communications, two substation rebuilds and fiber make-ready at the same time. The second substation rebuild therefore starts in month 13 instead of month 1, after meter design is complete, and fiber make-ready engineering is contracted out for its first phase.

What this page is doingApplies money and people limits.
8

Recommended Portfolio

Portfolio by year, net capital in millions

ProjectYear 1Year 2Year 3
Billing system, mandatory3.01.5
Smart meters7.07.0
Storm hardening9.09.09.0
Fiber broadband10.811.211.6
Substation rebuilds7.37.37.4
Chargers0.2
Community solar3.0
Total37.336.031.0

The portfolio stays within the limit in every year, leaving room in year three for the warehouse if the board wishes to reconsider it.

What this page is doingStates what is funded.
9

Conclusion

Scoring all eight projects against the same criteria, funding the billing system as mandatory and applying both the capital limit and the engineers' capacity produces a portfolio that fits: smart meters, storm hardening, fiber, the substations and chargers now, community solar in year three and the warehouse deferred.

What this page is doingSummarizes the selection.
10

References

Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (1999). New product portfolio management: Practices and performance. Journal of Product Innovation Management, 16(4), 333-351. https://doi.org/10.1111/1540-5885.1640333

Engwall, M., & Jerbrant, A. (2003). The resource allocation syndrome: The prime challenge of multi-project management? International Journal of Project Management, 21(6), 403-409. https://doi.org/10.1016/S0263-7863(02)00113-8

Teller, J., Unger, B. N., Kock, A., & Gemünden, H. G. (2012). Formalization of project portfolio management: The moderating role of project portfolio complexity. International Journal of Project Management, 30(5), 596-607. https://doi.org/10.1016/j.ijproman.2012.01.020

What the QSO 440 Module 2 instructions ask for

The QSO 440 Module 2 assignment usually asks students to select a portfolio of projects for an organization. Expect to identify candidate projects with their costs and benefits, define selection criteria and weights tied to strategy, score each project, rank them, apply constraints such as budget, people and capacity, identify mandatory or regulatory projects, recommend the portfolio and explain the sequencing and what is deferred or rejected. Strong assignments base criteria on the organization's goals, explain every score, treat mandatory work separately rather than forcing it through the scoring model, check resource constraints as well as money and show the effect of the choices on the years ahead.

How this QSO 440 Module 2 portfolio selection assignment example is built

The assignment selects the portfolio for Coldwater Valley Electric Cooperative, a fictional member-owned utility in Missouri. Eight projects are scored on strategic alignment, member benefit, financial return, reliability and feasibility. Smart meters rank first at 79, storm hardening 73, fiber broadband 72 and substation rebuilds 71; the billing system scores 64 but is mandatory because vendor support ends in 2028. Net of grants, the eight need about $42.3 million in year one against a $38 million limit. The warehouse is deferred, community solar moves to year three and the second substation rebuild is staggered so engineers are not double-booked. Cooper and colleagues, Teller and colleagues and Engwall and Jerbrant inform the method.

Where the QSO 440 Module 2 rubric puts the points

The QSO 440 portfolio selection assignment is commonly marked on candidate projects described with costs and benefits, criteria and weights tied to strategy, scores explained project by project, mandatory work handled separately, capital and resource constraints applied, a recommended portfolio with sequencing and a clear account of what is deferred. The strongest assignments show that the chosen portfolio fits people as well as money and test whether different weights would change the result. Credit drops when scores are unexplained, mandatory projects are scored like discretionary ones, only the budget is checked or deferred projects simply disappear. Tables, clear writing and APA citations complete the grade.

QSO 440 Module 2 help: the mistakes that cost points

Start by listing every candidate project with its cost by year, its main benefits and the people or equipment it needs. Choose four to six criteria drawn from the organization's strategy, weight them and define what a low and a high score mean. Score each project and explain each score in a sentence. Before ranking, pull out mandatory work, such as regulatory requirements or systems losing support, because it must be funded whatever it scores. Then fit the remaining projects to the money and people available, starting from the top of the ranking, and sequence them so that shared staff are not double-booked. Say what is deferred and when it will be reconsidered. A common mistake is checking only the budget; another is a scoring model that makes the favorite project win.

Get QSO 440 Module 2 written to your instructions

Share the QSO 440 Module 2 instructions and your organization's candidate projects. A writer builds a weighted scoring model, scores each project with reasons, separates mandatory work, applies capital and resource limits, sequences what fits and explains what is deferred and why, citing research on portfolio selection. Your first QSO 440 paper is free, done in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 440 papers and related BS Operations Management samples

QSO 440 Module 2 questions, answered

Where can I find a free QSO 440 Module 2 Portfolio Selection Assignment sample?

The complete QSO 440 Module 2 assignment is on this page: scoring and selecting an invented electric cooperative's project portfolio.

What is a weighted scoring model?

A way of ranking projects by rating each against agreed criteria, giving the criteria different importance and adding the weighted ratings into one comparable total.

How should mandatory projects be handled in portfolio selection?

They should be identified first and funded outside the competitive scoring, since regulatory, safety or end-of-support work must be done regardless of its score.

What constraints apply in portfolio selection?

Budgets, people with specific skills, equipment, management attention, regulatory windows and dependencies between projects.

Why sequence projects in a portfolio?

So that shared resources are not overloaded, dependencies are respected and the organization's cash and capacity are spread across years.