Free sample paper for QSO 700 Module 7
Thirty Weeks to a Faster Yes: The Implementation Plan for Harbor Pines' Dealer Loan Redesign
[Student Name]
Southern New Hampshire University
QSO 700: Project Management and Operations Capstone
Implementation Plan
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Thirty Weeks to a Faster Yes: The Implementation Plan for Harbor Pines' Dealer Loan Redesign
Introduction
The solution design recommended a combined redesign of dealer loan decisions at Harbor Pines Credit Union: expanded automated rules validated on two years of loan results and tested for fairness, a triage of remaining applications into simple and complex queues, an evening shift and Saturday rotation for underwriters, a dealer support specialist, required income fields in the dealer portal and electronic documents for funding. This plan sets out how to put that design into practice over 30 weeks, what it will cost, what could go wrong, how the people affected will be involved and how the credit union will know whether it is working or should be reversed.
Phases and Schedule
Implementation phases
| Phase | Weeks | Owner | Depends on |
|---|---|---|---|
| 1. Approvals: credit committee, compliance sign-off on rules, board notice | 1 to 4 | Vice president of lending | Solution design |
| 2. Decision engine configuration and testing | 3 to 12 | Information technology with vendor | Phase 1 rule approval |
| 3. Shadow run of new rules beside underwriters | 13 to 16 | Risk analyst | Phase 2 |
| 4. Staffing: shift changes with 30 days' notice, hire dealer support specialist, triage training | 5 to 14 | Underwriting manager, human resources | Phase 1 |
| 5. Portal required fields and electronic document upload | 6 to 16 | Information technology | Phase 1 |
| 6. Dealer communication and training | 12 to 18 | Dealer relations manager | Phases 4 and 5 |
| 7. Go-live in waves and stabilization | 17 to 30 | Project lead | Phases 3 and 6 |
The shadow run is the plan's center. For four weeks, every application will be scored by the new rules and the triage logic, but decisions will still be made by underwriters, and the two will be compared. Any rule that disagrees with experienced underwriters more than expected, or that produces approval differences across groups in the compliance officer's test, will be corrected before launch. Go-live then proceeds in waves: 40 dealers in week 17, mixing big new-car franchises with a few corner used-car lots, another 80 in week 20 and the rest in week 22, with weeks 22 to 30 for stabilization.
Budget
Implementation budget
| Item | One-time | Annual |
|---|---|---|
| Decision engine configuration and testing (vendor) | $180,000 | |
| Portal required fields and electronic documents | $120,000 | |
| Dealer support specialist | $62,000 | |
| Training and dealer communication | $28,000 | |
| Project lead time and underwriter backfill during shadow run | $70,000 | |
| Total | $398,000 | $62,000 |
The evening shift and Saturday rotation use existing underwriters and add a shift differential of about $9,000 a year, which the underwriting budget absorbs.
Risks
Main implementation risks
| Risk | Owner | Early signal | Response |
|---|---|---|---|
| Vendor configuration runs late | IT director | Missed test milestone in week 9 | Vendor's contract penalty; shorten shadow run to three weeks only with sponsor approval |
| Shadow run shows rules disagreeing with underwriters | Risk analyst | Disagreement above 8% on approvals | Narrow rules and rerun for two weeks |
| Fairness test finds a disparity | Compliance officer | Any group outside policy limits | Suspend affected rule; redesign before launch |
| Underwriters decline evening shift | Underwriting manager | Fewer than two volunteers by week 6 | Rotation with differential; temporary hire if needed |
| Dealers do not complete required fields | Dealer relations manager | Over 10% of submissions rejected in first wave | Portal prompts and dealer coaching |
Survey evidence from project managers in New Zealand, Israel and Japan suggests that a modest amount of risk planning already blunts much of the damage risky conditions do to outcomes (Zwikael & Ahn, 2011). The plan therefore keeps the risk list short and tied to owners and early signals, rather than exhaustive.
People and Change
Pooling 79 quantitative studies stretching back to the 1940s, Oreg et al. (2011) concluded that how employees respond to a change hinges on how it is run: participation, communication and trust in management shaped how people responded as much as the content of the change itself. The plan builds on the underwriters' feedback from Module 4. The written commitment that no underwriter positions will be cut is repeated at the start of every phase. The two underwriters who helped validate the rules will lead the shadow run review. Underwriters will help train dealers on what complete applications look like, since they know which missing items cause the most calls. Evening seats go to underwriters who raise their hands before anyone is assigned, and those hours carry a differential. Each wave's results will be shared with the whole team before the next wave starts.
Stabilization
Weeks 22 to 30 are reserved for stabilization rather than declared a success at go-live. During those weeks the project lead and underwriting manager review every application the triage logic sent to the wrong queue, adjust the rules that route thin-file and self-employed applicants and rebalance evening and daytime staffing against the actual arrival curve. The risk analyst compares early payment results on automatically approved loans with the back-test each month. The project closes in week 30 only when the dashboard has stayed inside its thresholds for four consecutive weeks, and responsibility for the measures then passes to the underwriting manager as part of normal operations.
Communication
Underwriters and funding specialists will meet weekly with the project lead through go-live. Dealers will receive a notice six weeks before their wave, a short video on the new portal fields and electronic documents and a direct line to the dealer support specialist. The credit committee will receive the shadow run and fairness results before go-live, and the board's loan committee a summary after the first wave.
Measures and Rollback
Weekly dashboard and thresholds
| Measure | Target | Action threshold |
|---|---|---|
| Applications decided within 15 minutes | 70% by week 30 | Below 50% after week 24: review triage and staffing |
| Look-to-book | 24% by week 30 | No rise by week 26: review with dealers |
| Clean contracts funded within one business day | 80% | Below 60% after week 24: review funding steps |
| 30-day delinquency on automatically approved loans | at or below portfolio rate | Above 1.5 times portfolio rate for two months: roll back expanded rules |
| Fairness test of approvals and pricing | within policy limits | Any breach: suspend affected rule immediately |
The rollback is simple because the old rules remain in the decision engine; switching back takes one configuration change approved by the vice president of lending and the chief risk officer. Ika (2009) found that the project management literature has moved from judging success by time, cost and scope toward the judgments of stakeholders and the benefits delivered, which is why the dashboard measures dealers' behavior and loan quality as well as speed.
Conclusion
The redesign will be implemented in seven phases over 30 weeks for about $398,000 one-time and $62,000 a year. A silent shadow run proves the rules before dealers depend on them, go-live proceeds in waves, underwriters have real roles in testing and training, and a weekly dashboard with thresholds tells the credit union when to adjust and when to reverse. The plan is ready for the sponsor's approval.
References
Ika, L. A. (2009). Project success as a topic in project management journals. Project Management Journal, 40(4), 6-19. https://doi.org/10.1002/pmj.20137
Oreg, S., Vakola, M., & Armenakis, A. (2011). Change recipients' reactions to organizational change: A 60-year review of quantitative studies. The Journal of Applied Behavioral Science, 47(4), 461-524. https://doi.org/10.1177/0021886310396550
Zwikael, O., & Ahn, M. (2011). The effectiveness of risk management: An analysis of project risk planning across industries and countries. Risk Analysis, 31(1), 25-37. https://doi.org/10.1111/j.1539-6924.2010.01470.x
What the QSO 700 Module 7 instructions ask for
The QSO 700 Module 7 milestone usually asks students to develop an implementation plan for their recommended solution. Expect to define phases or work packages, a schedule, resources and budget, risks and responses, a communication and change management approach and measures for monitoring results. Strong plans test risky elements before full launch, for example with a pilot or a parallel run, sequence work so that approvals and training come before go-live, assign owners to each phase and risk, give the people affected real roles, define the measures and thresholds that will show success or trigger corrective action and include a plan for reversing the change if it causes harm. A plan that a sponsor could approve as written is the goal.
How this QSO 700 Module 7 implementation plan example is built
The milestone plans the redesign of dealer loan decisions at Harbor Pines Credit Union, a fictional Michigan credit union. Seven phases over 30 weeks run from credit committee and compliance approval through decision engine configuration, a four-week shadow run in which the new rules decide silently beside underwriters, shift changes with 30 days' notice, a dealer support hire, portal and electronic document changes, dealer training and go-live in waves starting with 40 dealers. The budget is about $398,000 one-time plus $62,000 a year. Risks have owners and triggers, underwriters help test and train, and a weekly dashboard drives a rollback if delinquency or fairness tests cross thresholds. Oreg and colleagues, Zwikael and Ahn and Ika are cited.
Where the QSO 700 Module 7 rubric puts the points
The QSO 700 implementation rubric generally rewards clear phases with owners, a realistic schedule with dependencies, a budget tied to the work, risks with responses and triggers, a change management approach that involves affected people, communication with each stakeholder group, measures with targets and thresholds, a pilot or parallel test before full launch, a rollback plan and research supporting the approach. Plans stand out when a sponsor could approve them without asking for more. They lose points for a single go-live date with no testing, for budgets with no basis, for change management that consists of announcements, for measures without thresholds or for no way back if the change misfires. A phase table a sponsor can sign and correct APA entries close out the marks.
QSO 700 Module 7 help: the mistakes that cost points
Break the work into phases in the order it must happen: approvals, build, test, prepare people, launch, stabilize. Give each a start, an end, an owner and its dependencies. Price each phase. Test the riskiest part before anyone depends on it, with a pilot or a silent parallel run. List the risks that could derail the plan, with owners and the signal that would show each is happening. Plan for the people: who is affected, what they need to know and do and what role they can play. Define a few measures, their targets and the thresholds that trigger action, including a threshold that sends you back to the old way. Plans often jump from approval to launch; the weeks between, testing and preparing people, decide whether launch succeeds.
Get QSO 700 Module 7 written to your instructions
Share the QSO 700 Module 7 guidelines and your selected solution. A writer breaks implementation into phases, builds a schedule and budget, sets risks with owners and triggers, designs the change plan for the people affected, defines measures and a rollback plan and supports the plan with research on change and project success. Your first QSO 700 milestone is drafted free, generally inside two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 700 papers and related MS Project Management samples
- QSO 700 Module 1 Discussion: Choosing the Capstone Problem
- QSO 700 Module 2 Capstone Proposal: The Proposal and Problem Statement
- QSO 700 Module 3 Literature Review Assignment: What Research Says About Faster Decisions
- QSO 700 Module 4 Discussion: Underwriters Who Fear the Change
- QSO 700 Module 5 Current-State Analysis: Where the Hours Go
- QSO 700 Module 6 Solution Design Assignment: Three Ways to a Faster Yes
- QSO 700 Module 8 Discussion: Presenting to the Board
- MGT 550 Module 7 Persuasive Presentation Assignment: Asking a Hospital to Accept One Delivery a Day
- QSO 690 Module 5 Forecasting and Postponement Assignment: Last Winter's Snow and the Final Build
- HRM 630 Module 3 Discussion: Who the Customers Really Are
- MGT 701 Module 2 Stakeholder Analysis Assignment: Stakeholder Analysis of a Critical Issue
QSO 700 Module 7 questions, answered
Where can I find a free QSO 700 Module 7 implementation plan sample?
This page holds the full QSO 700 Module 7 milestone: a 30-week plan for an invented credit union's dealer loan redesign.
What is a shadow run or parallel run?
Running a new system or rules alongside the old process without using its outputs, to compare results before switching over.
What goes in a capstone implementation plan?
Phases, schedule, owners, budget, risks with responses, change management and communication, measures with thresholds and a rollback plan.
Why include a rollback plan?
Because if a change causes harm, a predefined way to reverse it limits damage and makes approval easier.
How should employees be involved in implementation?
By giving them roles in testing, training and refining the change, which builds understanding and improves the design.