SPT 620 Module 5 Capital Budgeting Assignment Example

Reviewed by Portia Lambrick, MBA

This SPT 620 Module 5 Capital Budgeting Assignment sample evaluates a sport facility investment with capital budgeting, projecting incremental cash flows, discounting them to net present value, testing sensitivity and comparing alternatives. SNHU SPT 620 (SPT-620) asks MS Sport Management students to judge facility proposals by their cash flows, not by excitement. The project is a proposed $58 million stadium for Salt Creek FC, an invented women's soccer club in Lincoln. Discounted honestly, the full stadium destroys value even with $24 million in public money, while a smaller stadium built to grow later comes far closer to paying for itself.

CourseSPT 620 Finance and Economics of Sport
ModuleModule 5
Paper typegraduate assignment evaluating a sport facility investment with capital budgeting, projecting incremental cash flows, discounting them to net present value, testing sensitivity and comparing alternatives
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Sport Management
UpdatedOctober 2026

Free sample paper for SPT 620 Module 5

1

Does the Stadium Pay? A Capital Budgeting Analysis for Salt Creek FC

[Student Name]

Southern New Hampshire University

SPT 620: Finance and Economics of Sport

Capital Budgeting Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingSalt Creek FC, the stadium proposal and all cash flow figures are invented for this SPT 620 assignment.
2

Does the Stadium Pay? A Capital Budgeting Analysis for Salt Creek FC

Introduction

Haymarket Sports Partners, the owners of Salt Creek FC, propose a 7,000-seat stadium in Lincoln's Haymarket district at a cost of $58 million, with $24 million to come from public sources and the rest from the owners and borrowing. This paper evaluates the project from the club's point of view, asking whether the stadium's added cash flows justify its cost. It identifies incremental cash flows, projects them over 30 years, calculates net present value, tests sensitivity and compares a smaller alternative.

What this page is doingStates the investment question.
3

Incremental Cash Flows

The analysis counts only what changes because of the stadium, a discipline that the owners' own presentation did not follow. Revenue the club earns at its current venue is excluded except where the stadium increases it. This rule matters more than it seems. The owners' own presentation counted all ticket and concession revenue at the new stadium as a benefit, including the roughly $1.2 million the club already earns at the high school stadium. Counting that revenue again would make the project look about $13 million more valuable in present terms than it is.

Annual incremental cash flows, stabilized year

ItemAnnual amountBasis
Additional ticket revenue$1,050,000Average attendance from 2,400 to 4,900 after novelty fades, at $22
Premium seating and suites$650,000300 club seats and 10 suites
Additional concessions and parking$820,000Club keeps all venue revenue
Naming rights$350,000Comparable small venues
Non-match events, concerts, high school and college games$600,00045 event days a year, net
Saved rent and game operations$690,000Current venue costs
Stadium operating costs($1,650,000)Staffing, utilities, insurance
Capital repairs reserve($580,000)One percent of cost a year
Net annual cash flow$1,930,000
What this page is doingIdentifies what changes.
4

Attendance and the Novelty Effect

Coates and Humphreys (2005) found that new facilities produce a novelty effect: attendance rises in the first seasons and then declines as the newness wears off. The projection therefore assumes average attendance of 6,200 in the first season, falling to 4,900 by the fifth and holding there. Early years produce net cash flows of about $2.4 million, declining to the stabilized $1.9 million. The stabilized figure is the one that matters, because it applies to 26 of the 30 years. A plan that relied on first-season crowds would look attractive in a presentation and disappoint in the accounts, which is the pattern Coates and Humphreys observed across many new facilities.

What this page is doingModels attendance realistically.
5

Discount Rate

The club's cash flows are risky: attendance in a young league is uncertain, sponsorship depends on the local economy and the league itself is only three seasons old. The owners can earn about 8 percent on comparable investments of similar risk, so that is the rate used here. A lower rate would flatter the project; the sensitivity analysis shows the effect.

What this page is doingJustifies the rate.
6

Net Present Value

Discounting 30 years of net cash flows at 8 percent gives a present value of about $23 million, of which about $1 million comes from the novelty years. Against a $58 million cost, the private net present value is about negative $35 million. Even if the $24 million public contribution is treated as free money to the club, the net present value remains about negative $11 million. On its own cash flows, the stadium does not pay.

Siegfried and Zimbalist (2000) observed that sports facilities rarely generate enough revenue to cover their costs, which is why teams seek public subsidies. Long (2005) showed that the real public cost of facilities is often far higher than reported once land, infrastructure, forgone taxes and operating support are counted. Both points matter here: the private case is weak, and a public contribution would need to be larger and costlier than it looks to make the project work.

What this page is doingCalculates the result.
7

Sensitivity

Sensitivity of private net present value, with $24 million public contribution

Assumption changedNet present value
Base caseAbout ($11 million)
Stabilized attendance 5,800 instead of 4,900About ($6 million)
Stabilized attendance 4,000 instead of 4,900About ($17 million)
Non-match events 70 days instead of 45About ($7 million)
Naming rights $500,000 instead of $350,000About ($9 million)
Discount rate 6% instead of 8%About ($6 million)
Construction cost 15% over budgetAbout ($20 million)

Attendance and non-match events matter most, and construction overruns can sink the project. Overruns deserve particular attention, because they are common in stadium projects and fall on whoever has agreed to cover them. If the public contribution is fixed at $24 million, the owners bear overruns; if the city guarantees completion, the public does. That question belongs in the financing agreement, not in a later dispute. No plausible single change makes the full stadium positive, and even favorable combinations of two or three changes leave it near break-even at best.

What this page is doingTests key assumptions.
8

A Smaller Alternative

A 4,500-seat stadium designed to expand to 7,000 later would cost about $31 million. Because Salt Creek's realistic stabilized attendance is near 4,900, the smaller stadium would capture most of the ticket and concession gains while avoiding the cost of empty seats. It would sell out more often, which supports higher prices and a better atmosphere, and the expansion option preserves the chance to grow if the league and the club succeed. Expansion would cost more per seat later than building it now, but paying that premium only if demand appears is cheaper than paying for 2,500 empty seats every match in the meantime. Its net annual cash flow would be about $1.55 million, giving a present value of about $18 million. With a public contribution of $13 million, roughly half the amount sought for the full stadium, its net present value would be close to zero, and modest gains in attendance or events would make it positive.

What this page is doingCompares options.
9

Conclusion

The full $58 million stadium does not pay for itself on the club's cash flows, even with $24 million in public money. Attendance after the novelty effect and non-match events drive the result, and cost overruns are the largest risk. A 4,500-seat stadium built to expand later captures most of the benefit at about half the cost and comes close to paying for itself with a much smaller public share.

What this page is doingSummarizes the analysis.
10

References

Coates, D., & Humphreys, B. R. (2005). Novelty effects of new facilities on attendance at professional sporting events. Contemporary Economic Policy, 23(3), 436-455. https://doi.org/10.1093/cep/byi033

Long, J. G. (2005). Full count: The real cost of public funding for major league sports facilities. Journal of Sports Economics, 6(2), 119-143. https://doi.org/10.1177/1527002504264614

Siegfried, J., & Zimbalist, A. (2000). The economics of sports facilities and their communities. Journal of Economic Perspectives, 14(3), 95-114. https://doi.org/10.1257/jep.14.3.95

What the SPT 620 Module 5 instructions ask for

The SPT 620 capital budgeting assignment typically asks students to evaluate a major investment for a sport organization, such as a facility, using discounted cash flow tools and simpler checks such as payback. Expect to project cash flows and justify assumptions. Strong papers count only incremental cash flows, include the long-run costs of keeping a building usable, such as capital repairs, model attendance realistically including any novelty effect that fades, choose a discount rate that reflects risk, calculate net present value correctly, test sensitivity to the key assumptions and compare the proposal with alternatives, including doing less. They separate the private case from any public contribution, since the two answer different questions.

How this SPT 620 Module 5 capital budgeting assignment example is built

The assignment evaluates the proposed $58 million, 7,000-seat stadium for Salt Creek FC, a fictional women's soccer club in Lincoln, Nebraska, from the club's view. Incremental cash flows, tickets, premium seating, concessions, naming rights, events and saved rent, are set against operating costs and capital repairs over 30 years, with a fading novelty effect. At 8 percent the private net present value is about negative $35 million, still negative with $24 million in public money. Sensitivity shows attendance and events matter most. A 4,500-seat, $31 million alternative built to expand later reaches about break-even with roughly half the public money. Siegfried and Zimbalist, Long and Coates and Humphreys are cited. A smaller option is costed.

Where the SPT 620 Module 5 rubric puts the points

Grading for the SPT 620 capital budgeting paper usually rewards correct identification of incremental cash flows, complete costs, realistic attendance including novelty effects, a justified discount rate, accurate net present value, meaningful sensitivity analysis, comparison with alternatives and a clear separation of private and public money. Papers score highest when the recommendation would survive a skeptical lender. They lose points for counting revenue the club already earns, for forgetting capital repairs, for discount rates without reasoning or for analyses with only one option. Clear tables, APA references and written assumptions are expected, and so is a one-paragraph answer to the question a board would ask first: does it pay?

SPT 620 Module 5 help: the mistakes that cost points

List what changes if the facility is built: new revenue, saved costs and new costs. Leave out what would happen anyway. Project those changes year by year, and be honest about attendance after the first exciting seasons. Choose a discount rate that reflects how risky the cash flows are and explain it. Calculate net present value, then change one assumption at a time to see which ones matter. Compare the proposal with a cheaper or smaller version and with doing nothing. Papers often show one optimistic projection; the stronger ones show which assumptions would have to be true for the project to pay. Then state the answer plainly.

Get SPT 620 Module 5 written to your instructions

Share the SPT 620 Module 5 instructions and the project's figures. A writer identifies incremental cash flows, builds a multi-year projection, chooses and explains a discount rate, calculates net present value, tests sensitivity and compares alternatives, grounded in sports facility economics with tables and APA references. We write your first SPT 620 assignment free, normally in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More SPT 620 papers and related MS Sport Management samples

SPT 620 Module 5 questions, answered

Where can I find a free SPT 620 Module 5 capital budgeting sample?

The full SPT 620 Module 5 net present value analysis of an invented Lincoln stadium is on this page.

What is net present value?

Today's worth of every future cash flow a project produces, after subtracting what it costs to build; above zero, the project earns more than the required return.

What are incremental cash flows?

The changes in cash that happen only because of the project, such as new revenue, saved rent and new operating costs.

What is the novelty effect of a new stadium?

A rise in attendance in a new facility's first seasons that tends to fade as the venue's newness wears off.

Why compare a stadium with smaller alternatives?

Because a smaller or phased facility may capture most of the benefits at much lower cost and risk.