QSO 645 Module 5 Procurement Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 645 Module 5 Procurement Assignment sample plans procurement for several work packages, makes make-or-buy decisions, matches each contract type to how certain its work is, sets source selection criteria and works the incentive arithmetic. SNHU QSO 645 (QSO-645) covers procurement management in Module 5 of its MS Project Management PMP preparation course, a topic the exam tests with contract-type and calculation questions. The project is the dome renewal at Halloran Science Center, an invented Omaha museum buying a dome surface, seating, a projection system and new show content. Each package carries a different kind of uncertainty, so each gets a different contract, and the incentive arithmetic shows exactly where the integrator's risk begins.

CourseQSO 645 Project Management for PMP® Certification
ModuleModule 5
Paper typegraduate assignment planning procurement for several work packages, making make-or-buy decisions, matching contract types to the certainty of each package, setting source selection criteria and working the incentive arithmetic
LengthAbout 1,060 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Project Management
UpdatedOctober 2026

Free sample paper for QSO 645 Module 5

1

Four Packages, Four Contracts: Procurement Planning for the Halloran Dome Renewal

[Student Name]

Southern New Hampshire University

QSO 645: Project Management for PMP Certification

Procurement Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe packages, prices, contract terms and vendors for Halloran Science Center in this QSO 645 assignment are invented.
2

Four Packages, Four Contracts: Procurement Planning for the Halloran Dome Renewal

Introduction

Halloran Science Center's dome renewal will buy almost all of its work. The center has a small facilities team and a show production staff of two, so the dome surface, seats, room alterations and projection system must come from outside, and show content could come from inside, from outside or from a partner. The packages differ sharply in how well their scope can be defined before work begins. This paper decides what to make and what to buy, matches each package to a contract type, sets selection criteria, works the incentive arithmetic for the most complex contract and describes how procurements will be controlled and closed.

What this page is doingStates the procurement task.
3

Make or Buy

Installation work is clearly a buy: the center has no crews or equipment for dome fabrication, seating or projector integration. Show content is the real make-or-buy decision. Making a 24-minute full-dome show entirely in-house would need animators the center does not employ and would cost an estimated $310,000. Licensing an existing show from a distributor costs about $55,000 for five years. Co-producing with the university astronomy department, which supplies scientists and student animators, costs an estimated $210,000. The center will license one existing show to have content ready on reopening day and co-produce one original show, the Great Plains sky show, because it serves Nebraska's science standards and keeps the content's rights at Halloran.

What this page is doingDecides what to do in-house.
4

Contract Types by Package

Bajari and Tadelis (2001) treat the buyer as trading one cost for another. A lump-sum price keeps the seller thrifty, yet every later design change becomes a fresh haggle; paying actual cost plus a fee makes changes painless but leaves the seller little reason to economize. Their model therefore pairs lump sums with simple, fully drawn work and cost-based payment with intricate work that will surely change. Turner and Simister (2001) sort contracts by two unknowns, whether the buyer can describe the finished thing and whether anyone knows the method for building it, and pair each combination with a payment form.

Contract type by package

PackageScope certaintyContract typeEstimated valueMain risk and who carries it
Dome surfaceHigh: drawings and specification completeFirm fixed price, sealed bidabout $640,000Fabrication cost: seller
Seating and room alterationsHigh for new work; low for hidden conditions in 1987 structureFirm fixed price with unit-price allowancesabout $760,000 plus allowancesNew work: seller; hidden conditions: buyer at agreed unit prices
Projection system and integrationPerformance specified; integration effort uncertainFixed price incentive feetarget $2.38 million (cost plus fee)Shared within the share ratio up to the ceiling
Show co-productionLow: content discovered in sprintsTime and materials, not to exceed $230,000up to $230,000Buyer, controlled by the cap and sprint reviews

The unit-price allowances for the seating contract cover removing old anchor bolts, patching the concrete floor and correcting any electrical work found below code, each priced per unit in the bid. This keeps the fixed price honest: bidders do not pad their prices for conditions no one can see, and the center pays only for what is found.

What this page is doingMatches contracts to certainty.
5

The Incentive Contract

The projection system contract has a target cost of $2.2 million, a target fee of $180,000, a share ratio of 80/20 (the center pays 80 percent of any overrun and keeps 80 percent of any underrun) and a ceiling price of $2.55 million.

Projection contract outcomes

Actual costVariance from targetSeller's feePrice to center
$2.0 million$200,000 under$180,000 + 20% of $200,000 = $220,000$2.22 million
$2.2 millionnone$180,000$2.38 million
$2.4 million$200,000 over$180,000 minus 20% of $200,000 = $140,000$2.54 million
$2.5 million$300,000 overceiling applies$2.55 million

The point of total assumption, above which the seller bears every added dollar, is the target cost plus the difference between the ceiling and the target price divided by the buyer's share: $2.2 million plus ($2.55 million minus $2.38 million) divided by 0.8, or about $2.41 million. Above that cost, the seller absorbs the overrun. Eisenhardt (1989) explains agency relationships as a choice between contracts based on outcomes, which shift risk to the agent, and contracts based on behavior, which require the principal to monitor what the agent does, with the right choice depending on how measurable outcomes are and how much risk each party can bear. The incentive contract sits between these: the integrator is rewarded for outcomes but does not carry all of the integration uncertainty, which would only raise its bid.

What this page is doingWorks the arithmetic.
6

Source Selection

Source selection criteria and weights

CriterionDome surfaceSeating and alterationsProjection system
Price60%50%25%
Technical approach15%20%35%
Past performance on similar work15%20%25%
Schedule and capacity to finish by July 1510%10%15%

Price dominates where scope is fully defined, while technical approach and past performance dominate for the projection system, where a cheap bid that cannot integrate two systems would cost far more later. Each proposal will be scored by a panel of three, with the planetarium manager, the project manager and an outside planetarium consultant for the projection system.

What this page is doingSets criteria by package.
7

Controlling Procurements

Each contract has a named contract administrator and a monthly review. The fixed-price contracts are monitored on schedule and quality against their milestones. The incentive contract requires monthly cost reports, since the share ratio makes the center a partner in overruns. The time-and-materials show contract is controlled by the sprint reviews in Module 4 and by a running total against its cap; when spending reaches 75 percent of the cap, the product owner and project manager will decide which remaining scenes to fund. Changes to any contract follow the project's integrated change control.

What this page is doingPlans monitoring.
8

Closing Procurements

Each contract closes when its deliverables pass acceptance, the final invoice is reconciled, warranties and manuals are received and lessons about the vendor are recorded for future selections. The projection system's final payment will be held until the acceptance tests in Module 6 are passed.

What this page is doingPlans formal completion.
9

Conclusion

Halloran's four packages receive four contract types because their uncertainty differs. Fully specified work goes to fixed price, hidden conditions are priced by the unit, an integration whose cost is uncertain shares risk through an incentive contract, and creative work runs on capped time and materials under sprint control. Source selection weights match what each package needs, and the incentive arithmetic shows the center and the integrator where their interests meet.

What this page is doingSummarizes the plan.
10

References

Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. The RAND Journal of Economics, 32(3), 387-407. https://doi.org/10.2307/2696361

Eisenhardt, K. M. (1989). Agency theory: An assessment and review. Academy of Management Review, 14(1), 57-74. https://doi.org/10.2307/258191

Turner, J. R., & Simister, S. J. (2001). Project contract management and a theory of organization. International Journal of Project Management, 19(8), 457-464. https://doi.org/10.1016/S0263-7863(01)00051-5

What the QSO 645 Module 5 instructions ask for

For Module 5, QSO 645 wants a plan for buying what the project cannot make, set out package by package. Expect to identify what will be purchased, perform make-or-buy analysis, decide for each package how the seller will be paid, whether a set sum, actual costs plus a fee or hourly rates, define source selection criteria and describe how procurements will be controlled and closed. Strong papers explain each contract choice by the certainty of the scope and who is best placed to manage the risk, show the arithmetic for any incentive contract under more than one outcome, weight selection criteria to reflect what matters for each package, and note how the choice affects the buyer's workload in monitoring. Because the exam tests contract types through scenarios, clear reasoning matters as much as definitions.

How this QSO 645 Module 5 procurement assignment example is built

The assignment plans procurement for the dome renewal at Halloran Science Center, a fictional Omaha museum's $4.8 million planetarium project. The fully specified dome surface goes to sealed bids on a firm fixed price of about $640,000. Seating and room alterations use a fixed price with unit-price allowances for hidden conditions. The projection system, specifiable in performance but uncertain in integration, gets a fixed-price-incentive-fee contract with a $2.2 million target cost, $180,000 fee, 80/20 share and $2.55 million ceiling, worked for overrun and underrun. A make-or-buy analysis licenses one show for about $55,000 and co-produces another under capped time and materials. Bajari and Tadelis, Turner and Simister and Eisenhardt are cited.

Where the QSO 645 Module 5 rubric puts the points

Grading in the QSO 645 procurement assignment usually credits a complete list of purchases, sound make-or-buy reasoning, contract types matched to scope certainty with risk allocation explained, correct incentive calculations under several outcomes, weighted source selection criteria suited to each package, attention to controlling procurements and to closing them and research that supports the choices. Papers stand out when the reader can see why each package got a different contract. They lose points for using one contract type for everything, for arithmetic errors in incentive contracts, for choosing cost-reimbursable contracts without a plan to monitor costs or for selection based on price alone where performance matters. Tables, APA references and precise writing complete the grade.

QSO 645 Module 5 help: the mistakes that cost points

List what you will buy and ask, for each, whether you could do it yourself and at what cost; that is your make-or-buy. Then ask how well the work can be specified. If the scope is fully defined, a firm fixed price puts the risk on the seller. If performance can be defined but cost is uncertain, an incentive contract shares the risk. If the work cannot be defined, cost-reimbursable or time and materials with a cap keeps it moving while you control it. For incentive contracts, work the numbers for an overrun and an underrun and check the ceiling. Set selection criteria and weights for each package. Papers often define every contract type and then pick one; the marks come from showing why this package needs this contract.

Get QSO 645 Module 5 written to your instructions

Share the QSO 645 Module 5 instructions and your project's purchases. A writer runs make-or-buy analyses, matches each package to a contract type by how well its work can be specified, works incentive and share calculations, sets weighted source selection criteria and explains how procurements will be controlled and closed, drawing on contracting research. The first QSO 645 assignment is free, normally finished within two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 645 papers and related MS Project Management samples

QSO 645 Module 5 questions, answered

Where can I find a free QSO 645 Module 5 procurement sample?

This page holds the full QSO 645 Module 5 assignment: four packages, four contract types and the incentive math for an invented museum project.

What is a fixed price incentive fee contract?

A contract with a target cost, target fee, share ratio and ceiling price, in which buyer and seller share overruns and underruns up to the ceiling.

When should a firm fixed price contract be used?

When the scope is well defined and unlikely to change, so the seller can price the risk and the buyer wants cost certainty.

What is a make-or-buy analysis?

A comparison of doing work in-house with buying it, considering cost, capability, capacity, control and risk.

What is the point of total assumption on an incentive contract?

The cost above which the seller bears every additional dollar, because the price has reached the ceiling.