QSO 645 Module 3 Requirements Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 645 Module 3 Requirements Assignment sample collects requirements from several stakeholder groups using methods suited to each, documents them with priorities and acceptance criteria and builds a traceability matrix that links every requirement to its source, the work breakdown and a test. SNHU QSO 645 (QSO-645) covers requirements and scope in Module 3 of its MS Project Management PMP preparation course. The project is the dome renewal at Halloran Science Center, an invented Omaha museum replacing its planetarium. Teachers, visitors, presenters, astronomers and accessibility law all want something, and the matrix shows which wishes became commitments, which were declined and who asked for each one in the first place.

CourseQSO 645 Project Management for PMP® Certification
ModuleModule 3
Paper typegraduate assignment collecting requirements from several stakeholder groups with suitable elicitation methods, documenting them with priorities and acceptance criteria, and building a requirements traceability matrix linked to scope and testing
LengthAbout 1,150 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Project Management
UpdatedOctober 2026

Free sample paper for QSO 645 Module 3

1

From 140 Requests to 38 Requirements: Requirements and Traceability for the Halloran Dome Renewal

[Student Name]

Southern New Hampshire University

QSO 645: Project Management for PMP Certification

Requirements Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingHalloran Science Center, its stakeholders, survey results and requirements in this QSO 645 assignment are invented.
2

From 140 Requests to 38 Requirements: Requirements and Traceability for the Halloran Dome Renewal

Introduction

The business case for Halloran Science Center's dome renewal recommended a hybrid optical and digital planetarium with a new dome surface, accessible seating and new shows. Within weeks, the project team had heard dozens of requests: recliner seats, a bigger screen for the presenter's laptop, shows in Spanish, a quieter air system, cup holders, a larger lobby. Some came from people who will use the room every day, some from visitors who come once a year and some from law. Without a disciplined process, the loudest requests would shape the project. This paper describes how requirements were collected, how they were documented and prioritized and how a traceability matrix links each one to its source, to the work and to a test.

What this page is doingStates why requirements need care here.
3

Stakeholders and Elicitation Methods

Elicitation methods by stakeholder group

GroupMethodParticipantsWhy this method
Teachers who book school tripsThree focus groups26 teachers from 19 schoolsShared experience; discussion surfaces needs individuals forget
General visitorsOnline and lobby survey1,140 responsesLarge group; preferences can be counted
Dome presenters and techniciansIndividual interviews7 staffExpert knowledge of daily operation
University astronomy departmentInterviews3 facultyScientific accuracy and show production needs
AccessibilityReview of 2010 ADA Standards for Accessible Design and local codeFacilities manager, architectLegal requirements are found in documents
School shows in progressObservation12 showsReveals what people do without mentioning it

Davis et al. (2006) reviewed empirical studies of elicitation techniques and found that interviews, particularly structured ones, gathered more information than several more elaborate techniques, while warning that the evidence base was thin. Their findings support using interviews for the experts but do not argue against observation, which found something no one had said: during school shows, presenters spent several minutes each time moving classes into the room because the single entrance sits at the front, so groups arriving late interrupt the show.

What this page is doingMatches methods to groups.
4

From Requests to Requirements

The methods produced about 140 raw requests. Each was rewritten as a requirement stating what is needed rather than how to build it, combined with duplicates and classified as a business requirement (why the project exists), a stakeholder requirement (what a group needs), a solution requirement (what the system must do or be) or a transition requirement (what is needed to move from the old room to the new one). Hofmann and Lehner (2001) studied fifteen requirements engineering teams and found that the more successful ones devoted more effort to requirements and involved customers and users through a range of techniques rather than relying on one. Thirty-eight requirements remained, each with a priority set by the sponsor and the project team: must have, should have or could have.

What this page is doingShapes raw input into requirements.
5

The Traceability Matrix

Excerpt from the requirements traceability matrix

IDRequirementTypeSourcePriorityAcceptance criterionWBSTest
R04Night sky shows stars as sharp points to the naked eyeSolutionTeacher focus groups; astronomersMustStars to magnitude 6.5 appear as points, not discs, from every seat1.3.1 Optical systemSeat-by-seat inspection with astronomers
R07Full-dome video at least as bright and sharp as comparable new systemsSolutionVisitor survey; presentersMustContrast and brightness meet contract specification1.3.2 Video systemVendor acceptance test
R11Six wheelchair spaces with companion seats, dispersedStakeholder (legal)2010 ADA StandardsMustSpaces meet dimensional and dispersion requirements1.4.2 SeatingArchitect and inspector review
R12Assistive listening for the required number of receiversStakeholder (legal)2010 ADA StandardsMustSystem installed and tested; signage posted1.5.3 SoundAudio contractor test
R15Classes can enter without crossing in front of the presenterStakeholderObservation of school showsShouldSecond entrance at rear with light lock1.2.4 Room alterationsWalkthrough with a class
R22Shows available with Spanish narrationStakeholderVisitor survey; teachersShouldBoth new shows have Spanish audio track1.6.3 Show productionReview by native speakers
R29Seats recline enough to view the zenith comfortablySolutionVisitor survey; presentersMustRecline of at least 25 degrees; tested by 10 adults1.4.1 SeatingComfort trial
R36Presenters trained on new system before reopeningTransitionPresenter interviewsMustAll 7 pass operating checklist1.7.2 TrainingChecklist sign-off

The full matrix holds all 38 requirements. The source column matters because requirements change when people forget why they were written.

What this page is doingLinks sources, scope and tests.
6

Using the Matrix

Two weeks after the matrix was drafted, a board member asked for fully reclining seats, which would cost about $160,000 more and reduce capacity from 176 to 140. Tracing R29 back to its sources showed that visitors and presenters had asked for comfortable viewing of the zenith, not full recline, and that a 25-degree recline meets that need. Gotel and Finkelstein (1994) found that many traceability problems arise before the requirements specification is written, from losing track of who asked for a requirement and why, and argued that this kind of traceability to sources deserves as much attention as tracing requirements forward to design. The board member accepted the explanation once it was clear where the requirement came from.

Checking the matrix in both directions also found two requirements with no test, a quieter air-handling system and a presenter's control console reachable from a wheelchair, which now have acceptance tests, and one work package, a lobby display wall, that no requirement supports. The lobby wall was moved out of the project and into the exhibits budget.

What this page is doingSettles a dispute and finds gaps.
7

Managing Requirement Changes

Requirements will change during the project, and the matrix is the place where those changes are recorded. A new request is entered with its source and a provisional priority, assessed by the project manager for cost, schedule and effect on other requirements, and passed through the change control process before it joins the baseline. The university astronomers have already asked that the optical system show the sky as seen from the Southern Hemisphere, which the vendor can provide in software at no added cost; it became requirement R39 with a test. A request from the café to sell snacks inside the dome was declined, with the reason recorded, because it conflicts with R04's dark-room conditions.

What this page is doingKeeps the baseline stable.
8

Scope Validation

Each deliverable will be accepted by the sponsor against the matrix's acceptance criteria, with the test results attached: the optical and video systems after the vendor's acceptance tests and the astronomers' seat-by-seat inspection, the seating after the comfort trial and the inspector's review, the shows after review by teachers and native speakers. Requirements not met will be recorded as defects or as approved changes; none will be dropped quietly.

What this page is doingPlans formal acceptance.
9

Conclusion

Halloran's requirements process used six methods suited to six groups, turned about 140 requests into 38 testable requirements and built a matrix linking each to its source, its place in the work and its test. The matrix has already settled one costly request, found two missing tests and removed one piece of work nobody asked for. It becomes the reference for scope validation as each deliverable is accepted.

What this page is doingSummarizes the requirements baseline.
10

References

Davis, A., Dieste, O., Hickey, A., Juristo, N., & Moreno, A. M. (2006). Effectiveness of requirements elicitation techniques: Empirical results derived from a systematic review. In 14th IEEE International Requirements Engineering Conference (pp. 179-188). IEEE. https://doi.org/10.1109/RE.2006.17

Gotel, O. C. Z., & Finkelstein, C. W. (1994). An analysis of the requirements traceability problem. In Proceedings of IEEE International Conference on Requirements Engineering (pp. 94-101). IEEE. https://doi.org/10.1109/ICRE.1994.292398

Hofmann, H. F., & Lehner, F. (2001). Requirements engineering as a success factor in software projects. IEEE Software, 18(4), 58-66. https://doi.org/10.1109/MS.2001.936219

What the QSO 645 Module 3 instructions ask for

The Module 3 assignment in QSO 645 generally asks students to plan and carry out requirements collection for a project and document the results, often in a requirements traceability matrix. Expect to identify stakeholder groups, choose elicitation techniques such as interviews, focus groups, surveys, observation and document analysis, organize requirements by type, prioritize them and link them to project scope and to the tests that will confirm them. Strong papers match each technique to the group and the kind of information needed, write requirements that are specific and testable, separate needs from proposed solutions, record the source of every requirement so disputes can be settled, and check the matrix in both directions: every requirement has a test and a place in the scope, and every piece of scope traces to a requirement.

How this QSO 645 Module 3 requirements assignment example is built

The assignment collects requirements for the dome renewal at Halloran Science Center, a fictional Omaha museum's $4.8 million planetarium project. It uses three focus groups with 26 teachers, a 1,140-response visitor survey, interviews with presenters and university astronomers, a review of the 2010 ADA Standards and observation of 12 school shows. About 140 raw requests become 38 requirements, each with a priority, a source and an acceptance criterion, in a traceability matrix linked to the work breakdown and to tests. Tracing back settles a dispute over seat recline, and the check finds two untested requirements and one unrequested work package. Gotel and Finkelstein, Davis and colleagues and Hofmann and Lehner are cited.

Where the QSO 645 Module 3 rubric puts the points

Grading in the QSO 645 requirements assignment typically rewards stakeholder groups identified fully, elicitation methods matched to each group, requirements that are specific, testable and categorized, priorities with a stated method, a traceability matrix linking sources, scope and tests, a two-way check of the matrix and a plan for validating scope with the sponsor. Papers stand out when tracing a requirement to its source settles a real disagreement. They lose credit for requirements written as solutions, for vague criteria such as "user friendly," for a matrix with empty columns or for collecting requirements from managers only. Tables, APA references and plain writing complete the grade.

QSO 645 Module 3 help: the mistakes that cost points

List every group that will use, pay for, maintain or regulate the result. For each, choose a method that fits: interviews for experts, focus groups for groups with shared experience, surveys for large numbers, observation for work people do without thinking about it, document review for laws and standards. Then rewrite raw requests as requirements: what is needed, not how to build it, with a test someone could run. Sort and prioritize them. Build a matrix with columns for ID, requirement, source, priority, acceptance criterion, scope element and test. Check it both ways, looking for requirements with no test and scope nobody asked for. Papers often collect wishes and list them; the matrix is what turns wishes into commitments someone can check.

Get QSO 645 Module 3 written to your instructions

Share the QSO 645 Module 3 instructions and your project's stakeholders. A writer chooses elicitation methods for each group, turns raw requests into categorized requirements with priorities and acceptance criteria, builds a traceability matrix linking sources, scope and tests, and explains how scope will be validated, citing requirements research. Your opening QSO 645 matrix and write-up are drafted free, most within a two-day window. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 645 papers and related MS Project Management samples

QSO 645 Module 3 questions, answered

Where can I find a free QSO 645 Module 3 requirements sample?

This page carries the full QSO 645 Module 3 assignment: elicitation and a traceability matrix for an invented museum's planetarium project.

What is a requirements traceability matrix?

A table linking each requirement to its source, its priority, the scope element that delivers it and the test that confirms it.

What elicitation techniques are used to collect requirements?

Interviews, focus groups, surveys, observation, workshops, prototypes and document analysis, each suited to different stakeholders and information.

What makes a requirement testable?

It states a condition someone can check, with a measure or observable result, rather than a quality such as easy or attractive.

What is scope validation?

Formal acceptance of completed deliverables by the sponsor or customer, checking them against the documented requirements and acceptance criteria.