QSO 600 Module 4 Lean Improvement Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 600 Module 4 Lean Improvement Assignment sample applies lean methods to reduce changeover time and frequency, weighs batch size against flow and measures the effect of a pilot. SNHU QSO 600 (QSO-600) assigns lean improvement in Module 4 of its MS Operations Management core course. The process is the pair of tunnel washers at the Indianapolis plant of Fallowmere Linen Services, an invented commercial laundry where frequent, rushed switches between wash formulas cause quality problems and starve the bottleneck. The paper studies a changeover in detail, redesigns it, plans hospital loads in blocks and reports what a three-week trial changed.

CourseQSO 600 Operations Management
ModuleModule 4
Paper typegraduate assignment applying lean methods to reduce changeover time and frequency, weighing batch size against flow and measuring the effect of a pilot
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 600 Module 4

1

From Nine Changeovers to Four: Lean Work at Fallowmere's Tunnel Washers

[Student Name]

Southern New Hampshire University

QSO 600: Operations Management

Lean Improvement Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe changeover data and pilot results at Fallowmere Linen Services in this QSO 600 assignment are invented.
2

From Nine Changeovers to Four: Lean Work at Fallowmere's Tunnel Washers

Introduction

Module 2 found that Fallowmere Linen Services' Indianapolis tunnel washers are not the plant's bottleneck; the flatwork ironers are. Yet the washers matter. Module 3 traced most stained hospital goods to under-washed batches after rushed changeovers between wash formulas, and the ironers lose about 4 percent of their time waiting for damp goods that the washers deliver unevenly. This assignment studies the washers' changeovers, redesigns them with lean methods and reports a three-week pilot.

What this page is doingStates the problem.
3

The Current Changeover

Each tunnel washer is a long machine through which batches of about 110 pounds move chamber by chamber. Hospital goods use a hotter, longer formula with different chemicals than hotel goods. Switching formulas means changing the chemical feeds and temperature settings and running buffer batches until the new formula is established in every chamber. Hopp and Spearman's emphasis on variability in flow applies here, but the first step was simpler: watching. Twenty changeovers on both shifts were timed.

Steps in a current changeover, average minutes

StepMinutesInternal or external
Wait for operator to notice the next carts are a different customer type3Internal
Walk to chemical room and switch feed lines5Internal
Adjust temperature and cycle settings at the control panel2Internal
Run buffer batches until the new formula reaches every chamber6Internal
Find and move the next customer's sorted carts to the loading belt2Internal
Total18

Every step was done while the washer was stopped or running buffer batches. Each washer made about 9.1 changeovers a day, losing about 164 minutes, roughly 17 percent of a 16-hour day. On busy days, operators often skipped part of the buffer step, which is how hospital goods ended up under-washed.

What this page is doingObserves and times the work.
4

Redesigning the Changeover

Shah and Ward (2007) define lean production as an integrated system that produces with minimal waste and variability by bringing together practices inside the firm and with customers and suppliers. Setup reduction is one of its core practices. Three changes were made, each with the operators who run the washers. First, the next customer's carts are staged at the loading belt before the changeover, and a colored tag shows the customer type, so the operator does not need to notice or search. Second, the chemical feeds for both formulas were connected to a single selector at the washer, so the walk to the chemical room disappeared. Third, each formula's temperature and cycle settings were stored as a program the operator selects with one button. The buffer batches remain, because they protect hygiene, but are now counted by the controller, which locks hospital loading until the right number has run.

The redesigned changeover takes about 10 minutes: one minute to select the program and confirm the staged carts, and about nine minutes of buffer batches, which can no longer be skipped.

What this page is doingMoves work outside the stoppage.
5

Grouping Hospital Loads

The second improvement reduces how often changeovers happen. Instead of washing customers' carts in the order they arrive, sorting now groups hospital goods into four planned blocks a day per washer, timed so each block's goods reach the ironers well within the 48-hour promise. Holweg (2007) traces how lean ideas developed from practical efforts to make flow smooth and level, and leveling the mix of work into a predictable pattern is one of those ideas.

Grouping has a cost. Sorted carts wait longer for their block, adding an average of about 6,000 pounds of sorted linen to the plant's inventory. By Little's law, at a throughput of about 5,200 pounds an hour, that adds about 1.2 hours to average flow time, from about 35 to about 36 hours. That is acceptable against the 48-hour promise and is offset by steadier flow to the ironers.

What this page is doingWeighs fewer changeovers against inventory.
6

The Pilot

Both washers at Indianapolis ran the new method for three weeks.

Pilot results, Indianapolis tunnel washers

MeasureThree weeks beforeThree-week pilot
Changeovers per washer per day9.14.2
Average changeover time, minutes1810
Washer time lost to changeovers, minutes per dayAbout 164About 42
Hospital batches failing the chemical test strip check3.1%0.6%
Rewash rate, all goods6.8%5.1%
Ironer time spent waiting for goods4%2%

The washers gained about two hours a day each, which matters little because they were not the constraint. The larger gains were downstream. Under-washed hospital batches fell by four-fifths, rewash fell by a quarter and the ironers spent half as much time waiting. Together, lower rewash and less starving added about 120 pounds an hour of effective ironer capacity, more than the 80-pound weekly shortfall found in Module 2. Shah and Ward (2003) found that lean practices work best as bundles rather than singly, and the pilot combined setup reduction, leveled scheduling and a mistake-proofing lock in one change.

What this page is doingMeasures before and after.
7

Limits and Next Steps

Three weeks is short, and operators knew they were being watched, so the results will be checked again after three months. Rewash causes unrelated to washing, such as torn sheets from worn ironer rolls, remain and need their own fix. The Fort Wayne plant uses older washers that cannot store programs, so the selector and staging changes can be copied there but the lock cannot without a controller upgrade costing about $45,000 per washer. The operators who helped design the new method also asked for two things that should become part of the standard: a short checklist posted at each washer for the changeover steps, and a weekly review of test strip results with the shift leads, so that any drift back toward rushed changeovers is seen within days rather than months.

What this page is doingStates what remains.
8

Conclusion

By moving cart staging and chemical switching outside the changeover, storing formulas as programs, locking hospital loading until buffer batches are complete and grouping hospital goods into planned blocks, Fallowmere cut changeovers at its Indianapolis washers from about nine to about four a day and their length from 18 to 10 minutes. The washers were not the bottleneck, but the improvement raised quality and steadied flow enough to add more effective capacity at the ironers than the plant was short.

What this page is doingSummarizes the improvement.
9

References

Holweg, M. (2007). The genealogy of lean production. Journal of Operations Management, 25(2), 420-437. https://doi.org/10.1016/j.jom.2006.04.001

Shah, R., & Ward, P. T. (2003). Lean manufacturing: Context, practice bundles, and performance. Journal of Operations Management, 21(2), 129-149. https://doi.org/10.1016/S0272-6963(02)00108-0

Shah, R., & Ward, P. T. (2007). Defining and developing measures of lean production. Journal of Operations Management, 25(4), 785-805. https://doi.org/10.1016/j.jom.2007.01.019

What the QSO 600 Module 4 instructions ask for

The QSO 600 Module 4 assignment usually asks students to apply lean principles to an operation. Expect to identify waste, map the current process, select lean methods such as setup reduction, standardized work, flow and pull or visual management, propose changes and estimate or measure their effect. Strong assignments observe and time the actual work, show where waste comes from with data, apply methods to a specific problem rather than listing tools, separate work that must stop the process from work that can be done while it runs, consider trade-offs such as larger batches and more inventory, link the improvement to the bottleneck and to quality and report results from a trial.

How this QSO 600 Module 4 lean improvement assignment example is built

The assignment applies lean methods to the tunnel washers of Fallowmere Linen Services, a fictional commercial laundry, where each washer switches between the hospital and hotel wash formulas about nine times a day and loses about 18 minutes each time. Rushed changeovers send under-washed hospital batches downstream and leave the bottleneck ironers waiting for goods. The paper separates internal from external changeover work, moves chemical staging and cart sequencing outside the changeover, groups hospital loads into blocks and checks the extra inventory with Little's law. A three-week pilot cut changeovers from 9.1 to 4.2 a day per washer and their length from 18 to 10 minutes, and rewash fell from 6.8 to 5.1 percent. Shah and Ward and Holweg inform it.

Where the QSO 600 Module 4 rubric puts the points

The QSO 600 lean improvement assignment is commonly graded on direct observation and timing of the current method, waste identified with data, methods applied to a specific problem, a clear separation of internal and external work, attention to trade-offs between batch size, inventory and flow, a link to the bottleneck and to quality, a pilot with measured results and sound use of lean research. The strongest papers show that improving a non-bottleneck step can still raise output and quality downstream. Credit drops when lean is presented as a list of tools, results are estimated without measurement, trade-offs are ignored or changes are proposed without asking the people who do the work. Tables, clear writing and APA citations complete the grade.

QSO 600 Module 4 help: the mistakes that cost points

Watch the work and time it, step by step, ideally on several occasions and shifts. Classify each step as internal, meaning the process must stop for it, or external, meaning it could be done while the process runs. Move as much as you can outside the stoppage, then simplify what remains, for example by pre-measured chemicals or standard settings. Decide whether doing the change less often by grouping similar work is worth the extra inventory it creates, and use Little's law to estimate the effect on flow time. Link the change to the bottleneck and to quality, not only to the machine you improved. Run a short trial with the operators and measure before and after. Weak papers describe five or six lean tools in general terms and never time a single changeover.

Get QSO 600 Module 4 written to your instructions

Share the QSO 600 Module 4 instructions and describe the process you want to improve. A writer observes and times the current method, separates internal from external work, redesigns the changeover or flow, weighs batch size against inventory and flow time, plans and measures a pilot and explains the results with lean research, avoiding a bare list of tools. Your first QSO 600 paper is free, done within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 600 papers and related MS Operations Management samples

QSO 600 Module 4 questions, answered

Where can I find a free QSO 600 Module 4 Lean Improvement Assignment sample?

The complete QSO 600 Module 4 assignment is on this page: reducing changeovers at an invented commercial laundry's tunnel washers.

What is setup reduction in lean operations?

Shortening the time needed to change a process from one product or setting to another, often by moving work outside the stoppage and simplifying what remains.

How do internal and external setup work differ?

Internal work can only be done while the process is stopped; external work can be done while it is still running.

Why does changeover time matter at a non-bottleneck step?

Because rushed or frequent changeovers can cause defects and uneven flow that starve the bottleneck downstream.

What is the trade-off in grouping work into larger batches?

Fewer changeovers save time, but larger batches mean more items waiting, which raises inventory and flow time.