QSO 600 Module 2 Process Analysis Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 600 Module 2 Process Analysis Assignment sample maps a production process, measures effective capacity and utilization at each step, locates the bottleneck and uses Little's law to connect inventory with flow time. SNHU QSO 600 (QSO-600) assigns process analysis in Module 2 of the MS Operations Management core course. The process is the Indianapolis plant of Fallowmere Linen Services, an invented commercial laundry that pays for Saturday overtime nearly every week. The paper shows that the washers everyone blames are not the constraint, that the ironers are and that most of their lost capacity comes from downtime rather than from too few machines.

CourseQSO 600 Operations Management
ModuleModule 2
Paper typegraduate assignment mapping a production process, measuring effective capacity and utilization at each step, locating the bottleneck and using Little's law to relate inventory and flow time
LengthAbout 1,010 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 600 Module 2

1

The Ironers Run Eighty-One Percent of the Time: Finding Fallowmere's Bottleneck

[Student Name]

Southern New Hampshire University

QSO 600: Operations Management

Process Analysis Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe process, capacities and measurements at Fallowmere Linen Services in this QSO 600 assignment are invented.
2

The Ironers Run Eighty-One Percent of the Time: Finding Fallowmere's Bottleneck

Introduction

Fallowmere Linen Services' Indianapolis plant processes about 26 million pounds of linen a year, about 500,000 pounds a week. It runs two eight-hour shifts six days a week, 96 operating hours, so it must process about 5,200 pounds an hour on average to keep up. For most of the past year it has fallen behind by Friday and run Saturday overtime to protect its 48-hour return promise to hospitals. Managers blame the tunnel washers, which are older and visibly busy. This assignment maps the process, measures each step's capacity and utilization, finds the true bottleneck and relates the plant's inventory to its flow time.

What this page is doingStates the problem.
3

The Process

Soiled linen arrives in carts and is weighed and sorted by type and customer. Two tunnel washers, continuous machines that move batches through a sequence of wash and rinse chambers, wash all goods, and presses extract water. From there the routes divide. Towels, blankets and garments such as scrubs and gowns, about 38 percent of pounds, go to dryers and then to folding. Sheets, pillowcases and table linen, about 62 percent of pounds, go damp to three flatwork ironers, which dry and press them in one pass and feed automatic folders. All goods are then counted, wrapped and staged for delivery.

What this page is doingMaps the steps and routes.
4

Capacity and Utilization

Effective capacity was measured from three weeks of machine logs and production counts as pounds per operating hour actually achieved, not the manufacturer's rating. Demand at each step equals 5,200 pounds an hour times the share of pounds routed there.

Effective capacity, demand and utilization, Indianapolis plant

StepEffective capacity, pounds per hourDemand, pounds per hourUtilization
Sorting, four stations6,4005,20081%
Tunnel washers, two6,2005,20084%
Extraction presses6,4005,20081%
Dryers, eight, for 38% of pounds2,4001,98082%
Flatwork ironers, three, for 62% of pounds3,1503,230102%
Folding and packing7,0005,20074%

The washers are busy, but at 84 percent utilization they have spare capacity. The ironers are the bottleneck: at about 102 percent, they cannot keep up within normal hours, which is why the plant falls behind each week and why overtime is scheduled for the ironers, not the washers. Hopp and Spearman (2004) note that throughput is set by the bottleneck and that utilization close to 100 percent, combined with variability, makes queues grow quickly; the ironer queue, carts of damp sheets waiting in the staging area, is the largest in the plant.

What this page is doingMeasures each step.
5

Inside the Bottleneck

Each ironer is rated at 1,300 pounds an hour when running. Three ironers could therefore process 3,900 pounds an hour, well above demand. The logs show why they do not: each runs only about 81 percent of scheduled time.

Where the ironers' time goes, share of scheduled hours

CategoryShare
Running and feeding81%
Jams and wrapping on the rolls7%
Changeovers between sheet sizes and between hospital and hotel goods5%
Waiting for damp goods to arrive4%
Breaks not covered by relief staff3%

Nearly a fifth of the bottleneck's time is lost. Of the categories, jams have the most variable effect, since a bad jam can stop an ironer for 40 minutes. Waiting for goods means the bottleneck sometimes starves even while carts queue elsewhere, a sign that the washers are not sequenced to feed the ironers steadily.

What this page is doingBreaks down lost capacity.
6

Inventory and Flow Time

A count at shift change on six days found an average of about 180,000 pounds of linen inside the plant, from sorted soil to wrapped goods awaiting trucks. Little's law states that in a stable process average inventory equals throughput times average flow time. Average flow time is therefore about 180,000 divided by 5,200, about 35 hours. Adding collection and delivery, which take about eight hours on average, an average hospital order spends about 43 hours away, leaving a margin of about five hours against the 48-hour promise. Orders that arrive late on a Friday, when the ironer queue is longest, regularly exceed it, which is what Saturday overtime has been covering.

What this page is doingApplies Little's law.
7

Options at the Bottleneck

Schmenner and Swink (1998) argue that productivity improves with the swiftness and evenness of flow, and that the bottleneck deserves attention first. Shah and Ward (2003) found that bundles of lean practices, including preventive maintenance and setup reduction, were associated with better operating performance.

Effect of options on ironer effective capacity

OptionUptimeEffective capacity, pounds per hourUtilization at current demand
Current81%3,150102%
Cut jams by half with feeding training and roll maintenance84.5%3,30098%
Also sequence washers to feed ironers and cover breaks90%3,51092%
Add a fourth ironer at current uptime81%4,21077%

Raising uptime to 90 percent adds about 360 pounds an hour, more than the 80-pound shortfall, and brings utilization to about 92 percent, enough to absorb normal variation without Saturday overtime. A fourth ironer would add more capacity but costs about $640,000 installed. The uptime improvements cost mainly training, maintenance time and relief staffing.

What this page is doingCompares improvements.
8

Checking the Analysis

The analysis predicts that the plant's weekly output is limited to the ironers' 3,150 pounds an hour for flatwork over 96 hours, about 302,000 pounds a week, against weekly demand for flatwork of about 310,000. The difference, about 8,000 pounds, matches the volume the plant's records show being ironed on Saturdays in a typical week, which supports the conclusion that the ironers are the constraint. A second check came from the overtime itself: on the four Saturdays when an ironer broke down for more than two hours, the plant missed the 48-hour promise for at least one hospital, while breakdowns of the washers or dryers of similar length caused no missed returns, as the spare capacity at those steps would predict.

What this page is doingCompares with observed results.
9

Conclusion

The Indianapolis plant's bottleneck is its flatwork ironers, not its washers. The ironers' rated capacity is ample, but they run only 81 percent of the time, and the lost time from jams, changeovers, starving and uncovered breaks is the reason for Saturday overtime and the narrow margin on the 48-hour promise. Raising their uptime to 90 percent would remove the shortfall for far less than a fourth ironer would cost.

What this page is doingSummarizes the findings.
10

References

Hopp, W. J., & Spearman, M. L. (2004). To pull or not to pull: What is the question? Manufacturing & Service Operations Management, 6(2), 133-148. https://doi.org/10.1287/msom.1030.0028

Schmenner, R. W., & Swink, M. L. (1998). On theory in operations management. Journal of Operations Management, 17(1), 97-113. https://doi.org/10.1016/S0272-6963(98)00028-X

Shah, R., & Ward, P. T. (2003). Lean manufacturing: Context, practice bundles, and performance. Journal of Operations Management, 21(2), 129-149. https://doi.org/10.1016/S0272-6963(02)00108-0

What the QSO 600 Module 2 instructions ask for

In QSO 600 Module 2, students are typically given a business process to dissect. Expect to map the process from input to output, identify the resources at each step, calculate capacity, demand and utilization, find the bottleneck, estimate throughput, inventory and flow time and recommend improvements. Strong assignments distinguish rated from effective capacity, account for product mix when different items follow different routes, use Little's law correctly to relate work in process, throughput and flow time, check the results against observed performance, separate capacity lost to downtime and changeovers from capacity missing altogether and show how much each improvement would add at the bottleneck.

How this QSO 600 Module 2 process analysis assignment example is built

The assignment maps the Indianapolis plant of Fallowmere Linen Services, a fictional commercial laundry, which must process about 5,200 pounds an hour over 96 operating hours a week. Sorting, washing and extraction each have effective capacity above 6,000 pounds an hour, and the dryers run at 82 percent utilization. But the three flatwork ironers, rated at 1,300 pounds an hour each and running only 81 percent of the time, deliver 3,150 pounds an hour against demand of about 3,230, about 102 percent utilization. With about 180,000 pounds in the plant, Little's law gives an average flow time of about 35 hours, close to the 48-hour hospital promise. Raising ironer uptime to 90 percent would add about 360 pounds an hour. Hopp and Spearman, Schmenner and Swink and Shah and Ward inform the analysis.

Where the QSO 600 Module 2 rubric puts the points

The QSO 600 process analysis assignment is generally graded on an accurate process map, capacities measured as effective output, demand allocated by product route, correct utilization figures, a clearly identified bottleneck, correct use of Little's law, comparison with observed performance, a breakdown of lost capacity at the constraint and recommendations ranked by their effect on throughput. The strongest papers overturn a belief about where the constraint lies. Credit drops when nameplate capacity is used, mix is ignored, utilization above 100 percent goes unexplained, flow time is guessed rather than calculated or improvements are proposed at steps that are not the bottleneck. Tables, clear writing and APA citations complete the grade.

QSO 600 Module 2 help: the mistakes that cost points

Walk the process and draw each step in order, noting which products pass through which steps. For each resource, find its effective capacity: rated speed times the share of scheduled time it actually runs, which you can measure from logs or by observation. Work out demand at each step from total volume and the share of products routed there. Divide demand by capacity to get utilization; the step with the highest utilization is the bottleneck. Count the work in process and apply Little's law: average flow time equals inventory divided by throughput. Then break down the bottleneck's lost time into causes, such as jams, changeovers and idle gaps, and estimate how much each fix would add. Students frequently analyze the step that looks busiest rather than the one that limits output.

Get QSO 600 Module 2 written to your instructions

Share the QSO 600 Module 2 instructions and describe your process. A writer maps the steps and flows, measures effective rather than rated capacity, calculates demand and utilization at each step, identifies the bottleneck, applies Little's law to inventory and flow time, separates downtime from true capacity shortfalls and recommends where to act first, citing operations research. Your first QSO 600 paper is free, sent back within roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 600 papers and related MS Operations Management samples

QSO 600 Module 2 questions, answered

Where can I find a free QSO 600 Module 2 Process Analysis Assignment sample?

The complete QSO 600 Module 2 assignment is on this page: capacity, utilization and flow time at an invented commercial laundry.

What is a bottleneck in a process?

The resource with the highest utilization, whose capacity limits the output of the whole process.

What is Little's law?

A relationship stating that average inventory in a stable process equals throughput multiplied by average flow time.

How does rated capacity differ from effective capacity?

Rated capacity is a machine's speed when running; effective capacity accounts for the time lost to breakdowns, changeovers and other stoppages.

Why does product mix matter in capacity analysis?

Because different products follow different routes, so a step's demand depends on the share of volume that passes through it.