QSO 600 Module 9 Final Project Example

Reviewed by Portia Lambrick, MBA

This QSO 600 Module 9 Final Project sample presents an integrated operations improvement plan with its analysis, costed recommendations, sequencing and measures. SNHU QSO 600 (QSO-600) closes the MS Operations Management core course with this plan. The organization is Fallowmere Linen Services, an invented commercial laundry whose owners face Saturday overtime, rising rewash, a hospital contract at risk and a request for a $640,000 machine. The plan shows how the separate analyses fit together around one constraint, what each change costs and returns, the order in which to make them and how the owners will know each one is working.

CourseQSO 600 Operations Management
ModuleModule 9
Paper typegraduate final project presenting an integrated operations improvement plan with analysis, costed recommendations, sequencing and measures
LengthAbout 1,010 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 600 Module 9

1

One Constraint, Six Changes: An Operations Improvement Plan for Fallowmere

[Student Name]

Southern New Hampshire University

QSO 600: Operations Management

Final Project

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingFallowmere Linen Services, its data, projections and plan in this QSO 600 project are invented.
2

One Constraint, Six Changes: An Operations Improvement Plan for Fallowmere

Summary

Fallowmere Linen Services can end Saturday overtime, cut rewash, protect its hospital contracts and reduce its largest material cost without buying a $640,000 ironer now. Six changes, most already tested in pilots, are projected to save about $1.2 million a year for about $370,000 in one-time costs and $85,000 a year in added running costs. A fourth ironer should be prepared but bought only if a pending hospital tender is won or ironer demand passes about 3,450 pounds an hour.

What this page is doingStates the plan and its value.
3

Strategy and Constraint

Fallowmere serves two customer groups through shared plants. Hospitals, 58 percent of pounds, value hygiene, a guaranteed 48-hour return and exact counts; hotels value price and quick turnaround. Ward et al. (1998) argue that competitive priorities should shape operations choices, so each change below is judged by what it does for hygiene and reliability for hospitals and cost for hotels. The process analysis found one constraint, the flatwork ironers at Indianapolis, running at about 102 percent of effective capacity because they work only 81 percent of scheduled time. Several other problems, rewash, uneven feeding from the washers and the 48-hour margin, either consume ironer time or depend on it.

What this page is doingFrames every change.
4

The Six Changes

First, an ironer uptime program: scheduled roll maintenance, feeding training and relief staff for breaks, raising uptime from 81 toward 90 percent. Second, extending the changeover redesign and wash-formula lock that cut rewash at Indianapolis to Fort Wayne, which needs new washer controllers. Third, an inventory policy for rental linen: orders of about 20,000 king sheets, a reorder point of about 64,500 and a supplier or domestic reserve that holds lead time within a week, applied to the eight highest-volume items. Fourth, monthly loss reports to every rental hotel and charges for losses above an agreed rate, aimed at the misuse and in-transit losses that make up nearly 30 percent of pool losses. Fifth, par-level replenishment fed by daily occupancy data, offered to all 120 hotels after a pilot cut delivery variability by about 61 percent. Sixth, staggering six routes' finish times so that no more than about 14 trucks reach the soil dock in any hour.

What this page is doingDescribes each recommendation.
5

Costs and Benefits

Projected annual benefits and costs

ChangeAnnual benefitOne-time costAnnual costBasis
Ironer uptime programAbout $175,000 in Saturday overtime avoidedAbout $85,000Module 2 capacity analysis; overtime records
Changeover redesign at both plantsAbout $200,000 in rewash avoidedAbout $90,000 for Fort Wayne controllersIndianapolis pilot; rewash cost of $0.21 a pound
Inventory policy and reliable supplierAbout $110,000 in holding costModule 5 safety stock analysis
Loss reports and chargesAbout $585,000 in replacement linenLoss tracking of 2,000 tagged sheets
Par-level replenishment for all hotelsAbout $59,000 in emergency deliveriesAbout $240,000 for property system links18-hotel pilot
Staggered route finishesAbout $55,000 in waiting timeAbout $5,000Dock queuing analysis
TotalAbout $1.18 millionAbout $335,000, about $370,000 with contingencyAbout $85,000

Par-level replenishment also reduces the linen assigned to hotels by about 8 percent, which avoids roughly $530,000 in pool purchases as the pool turns over; that one-time benefit is not counted in the annual figure. The firmest estimates rest on pilots; the loss reduction is both the biggest number and the shakiest, because it depends on hotels changing behavior once charges apply.

What this page is doingQuantifies each change.
6

How the Changes Interact

The changes reinforce one another around the constraint. Lower rewash means fewer sheets return to the ironers; steadier washer sequencing stops the ironers waiting for goods; par-level replenishment smooths the weekly load the ironers must handle; and fewer losses mean less new linen to process. Shah and Ward (2007) describe lean production as an integrated system rather than separate tools, and the plan works the same way: none of the changes alone would end Saturday overtime with a safe margin, but together they bring ironer utilization to about 89 percent.

What this page is doingShows the system effect.
7

Sequence and Timeline

Implementation sequence

QuarterStepsOwner
FirstRoute stagger; ironer maintenance schedule and training; loss reports begin without chargesPlant managers; transport manager; account managers
SecondFort Wayne controllers installed; supplier qualification; par-level rollout to first 40 hotelsFort Wayne manager; purchasing; account managers
ThirdLoss charges begin; par-level rollout to remaining hotelsSales director; account managers
FourthReview of all measures; decision on fourth ironer if triggeredOperations director

Cheap changes come first, and their savings fund the controllers and system links in later quarters.

What this page is doingOrders the work.
8

The Fourth Ironer

Capacity research describes how firms facing uncertain demand can keep options open instead of committing early (Van Mieghem, 2003). With the plan in place, the three ironers can meet expected growth of about 5 percent a year for about a year and a half before utilization passes 95 percent. Floor space will be cleared and long-lead parts ordered now. The fourth ironer will be bought on the day a pending hospital network tender for about 4 million pounds a year is won, or when ironer demand passes about 3,450 pounds an hour, whichever comes first.

What this page is doingSets the trigger.
9

Measures

Ironer uptime and utilization weekly; Saturday overtime hours weekly; rewash rate by cause weekly at each plant; hospital complaints monthly; hospital return time, with the share over 48 hours; pool loss rate by hotel monthly; safety stock and supplier lead-time variation quarterly; delivery variability and emergency runs monthly; and dock waiting time in the peak hour weekly. Cachon and Fisher (2000) showed that shared information improves supply chain performance, so the hotel measures will also be shared with each hotel.

What this page is doingDefines how progress will be tracked.
10

Risks

Hotels may resist loss charges or decline to share occupancy data. A qualified second supplier may cost more than expected. Ironer uptime gains could fade without sustained maintenance. Each risk has a measure that will show it early.

What this page is doingLists what could derail the plan.
11

Conclusion

Fallowmere's problems share one constraint and several connected causes. Six changes, most tested, address them for about $370,000 in one-time costs and are projected to save about $1.2 million a year, while keeping a fourth ironer ready for the moment demand justifies it. Fallowmere's owners are asked to sign off on the plan now and to release funds for its first-quarter steps.

What this page is doingAsks the owners to act.
12

References

Cachon, G. P., & Fisher, M. (2000). Supply chain inventory management and the value of shared information. Management Science, 46(8), 1032-1048. https://doi.org/10.1287/mnsc.46.8.1032.12029

Shah, R., & Ward, P. T. (2007). Defining and developing measures of lean production. Journal of Operations Management, 25(4), 785-805. https://doi.org/10.1016/j.jom.2007.01.019

Van Mieghem, J. A. (2003). Commissioned paper: Capacity management, investment, and hedging: Review and recent developments. Manufacturing & Service Operations Management, 5(4), 269-302. https://doi.org/10.1287/msom.5.4.269.24882

Ward, P. T., McCreery, J. K., Ritzman, L. P., & Sharma, D. (1998). Competitive priorities in operations management. Decision Sciences, 29(4), 1035-1046. https://doi.org/10.1111/j.1540-5915.1998.tb00886.x

What the QSO 600 Module 9 instructions ask for

The QSO 600 final project usually asks students to develop an operations improvement plan for an organization. Expect to introduce the organization and its strategy, analyze its key processes, identify problems and their causes, recommend improvements in areas such as capacity, quality, inventory and supply chain, estimate costs and benefits, plan implementation and define performance measures. Strong plans connect every recommendation to the strategy and to the operation's constraint, show how the parts interact, quantify costs and benefits with stated assumptions, sequence changes so early ones pay for later ones, treat large investments as decisions with triggers and assign each measure to an owner.

How this QSO 600 Module 9 final project example is built

The project presents an improvement plan to the owners of Fallowmere Linen Services, a fictional commercial laundry washing 41 million pounds a year for hospitals and hotels. It treats the flatwork ironers as the constraint and raises their uptime instead of buying a fourth now, extends the changeover redesign and wash-formula lock to Fort Wayne, orders about 20,000 king sheets at a time from a supplier holding lead time within a week, attacks pool losses with monthly loss reports and charges, offers par-level replenishment to all 120 hotels and staggers route finishes at the soil dock. The changes are projected to save about $1.2 million a year for about $370,000 in one-time costs. Ward and colleagues, Shah and Ward, Van Mieghem and Cachon and Fisher inform it.

Where the QSO 600 Module 9 rubric puts the points

Instructors assessing the QSO 600 final project look for a clear strategic frame, accurate analysis of the main processes, problems traced to causes, recommendations linked to the strategy and the constraint, quantified costs and benefits with assumptions, attention to how changes interact, a realistic sequence and timeline, investment triggers instead of open-ended spending and measures with owners. The strongest plans show how fixing one problem relieves others. Credit drops when recommendations are a list of unrelated fixes, savings are asserted without calculation, the bottleneck is ignored, timing is vague, large purchases are approved without considering cheaper options or measures have no owner. Tables, clear writing and APA citations complete the grade.

QSO 600 Module 9 help: the mistakes that cost points

Open with the problem the owners care about and your answer in a paragraph. Restate the strategy, what each customer group values, because every recommendation should serve it. Identify the constraint and show how the other findings connect to it, for example how quality problems consume bottleneck time. For each recommendation, give the cost, the benefit, the assumptions behind both and the measure that will track it. Arrange the changes in an order that makes sense: cheap, fast fixes first, then those that need investment, with large purchases tied to triggers. Assign an owner to each measure and a date to each step. Close with risks. Plans often read as a list of separate projects; a strong one shows how they add up around one constraint and one strategy.

Get QSO 600 Module 9 written to your instructions

Send the QSO 600 final project guidelines with the analyses from your earlier modules. A writer ties the strategy to the constraint, integrates the process, quality, inventory, supply chain and queuing findings, costs each recommendation, sequences the changes, sets triggers for larger investments and defines measures and owners, citing operations research. Your first QSO 600 paper is free, prepared within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 600 papers and related MS Operations Management samples

QSO 600 Module 9 questions, answered

Where can I find a free QSO 600 Module 9 Final Project sample?

Read the full QSO 600 Module 9 final project here: a costed improvement plan for an invented commercial laundry.

What should an operations improvement plan include?

The strategy, analysis of key processes and the constraint, recommendations with costs and benefits, a sequence and timeline, investment triggers, measures, owners and risks.

Why organize an improvement plan around the constraint?

Because improvements elsewhere only raise output if they relieve the constraint, directly or by reducing the work it must do, such as rework.

What is an investment trigger?

A stated condition, such as demand passing a level or a contract being won, that commits the organization to a larger investment it has prepared for.

How should savings in an operations plan be estimated?

From measured current costs and tested or well-reasoned effects, with assumptions stated so readers can judge how firm each estimate is.