QSO 325 Module 2 Value Stream Mapping Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 325 Module 2 Value Stream Mapping Assignment sample builds a current-state value stream map of a production process and identifies the waste in it. SNHU QSO 325 (QSO-325) assigns value stream mapping in Module 2 of its BS Operations Management continuous improvement course. The process is the making of a mid-size play structure at Maumee Playworks, an invented Fort Wayne manufacturer. The map follows an order from quote to shipping through nine steps, records cycle times, changeovers, inventory and information flows and shows a lead time of 46 working days for about 14 hours of work that adds value. The paper names the largest wastes and where improvement should begin.

CourseQSO 325 Continuous Improvement Tools and Techniques
ModuleModule 2
Paper typeundergraduate assignment building a current-state value stream map of a production process and identifying waste
LengthAbout 1,050 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 325 Module 2

1

Nine Weeks for Fourteen Hours: A Current-State Value Stream Map at Maumee Playworks

[Student Name]

Southern New Hampshire University

QSO 325: Continuous Improvement Tools and Techniques

Value Stream Mapping Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe process steps, times and inventories for Maumee Playworks in this QSO 325 map are invented.
2

Nine Weeks for Fourteen Hours: A Current-State Value Stream Map at Maumee Playworks

Introduction

Maumee Playworks builds commercial play structures to order. Most orders combine steel posts and decks, rotomolded slides, swings and hardware into a structure designed for a site. This assignment maps the current-state value stream for the plant's largest product family, mid-size structures for school playgrounds, which make up about 60 percent of orders. The goal is to see how long an order takes from quote to shipment, how much of that time adds value and where the largest wastes are. Serrano et al. (2008) evaluated value stream mapping in several plant redesigns and found it useful for seeing the whole flow, while noting that it works best when the product family is chosen carefully and data are gathered at each step.

What this page is doingIntroduces the product family and the purpose.
3

Mapping Method

The process was walked twice in April, from shipping back to the sales office, and data were gathered at each step by observation, from the production system and by talking with operators. Inventory between steps was counted on one day and converted into days of demand at the plant's average of about six mid-size structures per working day.

What this page is doingExplains how data were gathered.
4

The Process Steps

Current-state process data for mid-size play structures (invented data)

StepCycle time per structureChangeoverUptimeOperatorsInventory before step
Quote and design3.0 hoursNoneNot applicable4 designers41 orders awaiting approval
Order entry and scheduling0.5 hoursNoneNot applicable2 planners18 orders
Steel cutting and welding4.2 hours45 minutes91 percent14 welders2 days of steel stock
Powder coating1.8 hours50 minutes per color84 percent69 days of welded parts
Slide rotomolding1.5 hours3.5 hours per color80 percent56 days of molded slides
Deck coating1.2 hours30 minutes93 percent44 days of coated steel
Hardware kitting0.6 hoursNoneNot applicable33 days of parts
Packing0.8 hoursNoneNot applicable55 days of finished parts
Shipping0.4 hoursNoneNot applicable33 days of packed orders
What this page is doingDescribes each step with its data.
5

Information Flow

Customers request quotes from sales representatives, who send them to the design team. After the customer approves the design, which often takes weeks because school boards meet monthly, the order is entered and the planners build a weekly schedule. The schedule is pushed to every department each Monday, and each department works through its list in its own sequence. Powder coating and slide molding batch work by color to reduce changeovers, so a structure's parts can be coated or molded days apart. No signal tells upstream departments what downstream departments need next.

What this page is doingShows how work is scheduled.
6

The Timeline

Converting the inventories into days at six structures per day gives about 7 days waiting for design approval, 3 days in order entry, 2 days of steel, 9 days before coating, 6 days of slides, 4 days before deck coating, 3 days before kitting, 5 days before packing and 3 days before shipping, plus 4 days of processing and moves between buildings, a total of about 46 working days, just over nine weeks. Value-added time, the welding, coating, molding, deck coating, kitting and packing that change the product, totals about 14 hours. About 4 percent of the lead time adds value; the rest is waiting.

What this page is doingCalculates lead time and value-added time.
7

Wastes Visible on the Map

The largest wastes are three. First is waiting in the office: 41 orders sit awaiting design approval, and design itself is redone often because customers change their minds after the first drawing. Second is inventory before powder coating, about nine days of welded parts, caused by batching by color and by the coating line's 84 percent uptime, which suffers from oven faults and frequent color changes. Third is overproduction of slides: because a color change takes three and a half hours, the molding team makes large batches of each color, producing slides weeks before they are needed and storing them in a warehouse across the parking lot, where some warp in summer heat. Smaller wastes include motion in kitting, where workers walk to bins across the building, and defects, discussed in Project One.

What this page is doingNames the main sources of waste.
8

Measuring Leanness

Shah and Ward (2007) developed measures of lean production covering practices such as pull scheduling, flow, setup time reduction and employee involvement. On these measures Maumee scores low: scheduling is push, flow is interrupted by batches, setup reduction has not been attempted and employee involvement is limited to the winter push. Bhamu and Sangwan (2014), reviewing lean research, found that value stream mapping is among the most widely used lean tools but is often applied without follow-up, so the map should lead directly to a future state.

What this page is doingConnects the map to lean measures.
9

Flow and Pull

The map also shows why the plant feels busy and still ships late. Because every department works from its own weekly list, each optimizes its own work: coating runs long color batches, molding runs long slide batches and welding finishes whatever is easiest to weld. The parts of any one structure therefore arrive at kitting and packing at different times, and a structure cannot ship until its last part arrives. A pull system would work differently: packing would signal which structure it needs next, kitting would pull those parts and each upstream step would make only what the next step has used. Even a partial move toward pull, such as scheduling coating and molding by structure rather than by color for the plant's ten most common colors, would cut the queues that the map shows before kitting and packing.

What this page is doingNotes what the map says about scheduling.
10

Takt Time

At about six mid-size structures per working day over an eight-hour shift, takt time, the pace at which structures must be finished to meet demand, is about 80 minutes per structure. Welding, with 14 welders and 4.2 hours of work per structure, keeps pace comfortably. Coating, with 1.8 hours of line time per structure but only 84 percent uptime and frequent color changes, is the step most likely to fall behind takt during the spring peak, which is consistent with the queue in front of it.

What this page is doingCompares demand with capacity.
11

Where to Start

Improvement should start where the map shows the most waiting: the coating line, where batching and downtime create nine days of queue, and slide molding, where long changeovers drive overproduction. Shortening design approval would also cut lead time sharply but depends on customers. Project One will analyze the coating defects behind much of the rework.

What this page is doingRecommends the focus.
12

References

Bhamu, J., & Sangwan, K. S. (2014). Lean manufacturing: Literature review and research issues. International Journal of Operations & Production Management, 34(7), 876-940. https://doi.org/10.1108/IJOPM-08-2012-0315

Serrano, I., Ochoa, C., & De Castro, R. (2008). Evaluation of value stream mapping in manufacturing system redesign. International Journal of Production Research, 46(16), 4409-4430. https://doi.org/10.1080/00207540601182302

Shah, R., & Ward, P. T. (2007). Defining and developing measures of lean production. Journal of Operations Management, 25(4), 785-805. https://doi.org/10.1016/j.jom.2007.01.019

What the QSO 325 Module 2 instructions ask for

The Module 2 assignment in QSO 325 usually asks students to create a current-state value stream map for a product family or service process. Expect to identify the process steps from customer order to delivery, gather data for each step, such as cycle time, changeover time, uptime, number of operators and inventory or queues between steps, map the information flows that schedule the work and calculate total lead time and value-added time. Many versions also ask students to identify the types of waste visible on the map and suggest where to focus. Strong submissions use observed or realistic data, follow one product family, show both material and information flows and explain what the gap between lead time and value-added time reveals.

How this QSO 325 Module 2 value stream mapping assignment example is built

The assignment maps the value stream for a mid-size play structure at Maumee Playworks, a made-up manufacturer. Nine steps, quote and design, order entry, steel cutting and welding, powder coating, slide rotomolding, deck coating, hardware kitting, packing and shipping, are each given cycle time, changeover time, uptime, operators and batch size, with inventory counts between them. Information flows show a weekly schedule pushed from the office to every department. Lead time totals 46 working days, value-added time about 14 hours, or about 4 percent. Serrano, Ochoa and De Castro's evaluation of mapping in plant redesign, Shah and Ward's lean measures and Bhamu and Sangwan's review guide the analysis of waiting, batching and overproduction.

Where the QSO 325 Module 2 rubric puts the points

The QSO 325 value stream mapping assignment is generally assessed on a correctly scoped product family, complete process steps with relevant data, accurate inventory and information flows, a correct timeline of lead time and value-added time, identification of specific wastes linked to the map and use of mapping concepts and research. Submissions that score highest gather data at each step, show how scheduling information flows drive the material flow and connect each waste to a location on the map. Points drop when maps omit information flows, use averages that hide changeovers, confuse cycle time with lead time or list wastes in general terms. Clear presentation and APA citations complete the rubric.

QSO 325 Module 2 help: the mistakes that cost points

Pick one product family that shares most process steps and walk the process from shipping back to order entry, as mapping guides recommend, so you see it from the customer's end. At each step record cycle time, changeover time, uptime, operators and batch size, and count the inventory waiting before it. Draw how information moves: who sends the schedule, how often and to whom. Convert inventory into days of demand to build the timeline, and add up value-added time separately. A common mistake is mapping the process as it should work rather than as it does; another is leaving out the office steps, such as design approval, where much of the waiting happens. End by naming the three largest sources of waste and where they sit on the map.

Get QSO 325 Module 2 written to your instructions

Share the QSO 325 Module 2 instructions and describe the process you will map. A writer builds the current-state value stream map with process boxes, data boxes, inventory triangles and information flows, calculates lead time and value-added time, identifies the main wastes and explains where improvement should start. Your first QSO 325 mapping assignment is free, ready within two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 325 papers and related BS Operations Management samples

QSO 325 Module 2 questions, answered

Where can I find a free QSO 325 Module 2 Value Stream Mapping Assignment sample?

The complete QSO 325 Module 2 assignment is on this page: a current-state value stream map of an invented playground equipment plant with its lead time and wastes.

What is a value stream map?

A diagram of every step, material flow and information flow needed to deliver a product or service, with data such as cycle times and inventories, used to find waste and design a better future state.

How do you calculate lead time on a value stream map?

Add the time items wait in each inventory, converted to days of demand, to the processing times, giving the total time from order or raw material to shipment.

What is value-added time?

Time spent on activities that change the product in ways the customer is willing to pay for, such as welding or coating, as opposed to waiting, moving or inspecting.

What are the main types of waste in lean?

Commonly listed wastes are overproduction, waiting, transportation, overprocessing, inventory, motion, defects and unused employee ideas.