OL 324 Module 5 Milestone Two Example

Reviewed by Portia Lambrick, MBA

This OL 324 Module 5 Milestone Two sample plans a structured quality improvement project, from root causes to solutions, a pilot and the controls that keep gains in place. SNHU OL 324 (OL-324) has BS Business Administration students design this project as part of their final plan. The project targets the 7.9 percent defect rate on a 40-cavity diagnostic housing mold at Nashoba Precision Molding, a composite injection molder. Following the DMAIC sequence, the milestone charters a cross-shift team, matches a solution to each root cause, pilots them for four weeks, verifies results with control charts and sets operator-run controls and audits, supported by research on Six Sigma, lean and quality practices.

CourseOL 324 Managing Quality
ModuleModule 5
Paper typeundergraduate milestone planning a structured quality improvement project with solutions, piloting and controls
LengthAbout 1,090 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Business Administration
UpdatedOctober 2026

Free sample paper for OL 324 Module 5

1

The DMAIC Project on Press 23: An Improvement Plan for Nashoba Precision Molding

[Student Name]

Southern New Hampshire University

OL 324: Managing Quality

Milestone Two: Quality Improvement Project Plan

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe team, solutions, pilot results and costs are fictional, built for this OL 324 milestone.
2

The DMAIC Project on Press 23: An Improvement Plan for Nashoba Precision Molding

Introduction

Milestone One traced the 7.9 percent defect rate on Press 23's 40-cavity diagnostic housing mold to four root causes: damp resin following lot changes, shift-by-shift differences in how the press is started, a check ring past its wear limit and blocked vents in six cavities, made worse by technicians raising pressure to compensate. This milestone plans the improvement project that will remove those causes and keep them removed, using the five-step DMAIC sequence.

What this page is doingLinks the project to the analysis.
3

Project Charter

The project covers the diagnostic housing mold on Press 23 and the resin handling and maintenance that serve it. It aims to push defects under 2 percent inside sixteen weeks, get shot weight into statistical control and raise the medical customer's scorecard above 85 within two quarters. The team includes one process technician from each of the three shifts, including one of the two technicians who were written up and later cleared, the mold maintenance lead, a materials handler and the quality engineer as project leader. The plant manager is the sponsor and will clear obstacles. The team meets for an hour twice a week.

What this page is doingDefines scope and team.
4

Why a Structured Method

Zu et al. (2008), studying manufacturing plants, found that Six Sigma's distinctive practices, a defined role structure, a structured improvement procedure and its reliance on measures, added to the older quality practices instead of displacing them. Kaynak (2003) found that quality management practices affected performance through connected paths, with leadership, training and employee relations supporting process management, which in turn improved quality and operating results. The plan follows that logic: the method gives the team structure, and the involvement of technicians and the sponsor's support make the method work.

What this page is doingApplies Six Sigma research.
5

Solutions Matched to Causes

Solutions for each root cause

Root causeSolutionOwner
Wet resin after lot changesDryers preheated before each lot change; moisture tested at the hopper and logged; material held until below 0.02%Materials handler; technicians
Startup procedures differ by shiftA written startup sheet built by the three shift technicians, with photos, setpoints and purge steps; all technicians trainedShift technicians
Worn check ringCheck ring and screw inspected every 2,000 hours and replaced on a fixed intervalMold maintenance lead
Clogged ventsVents cleaned at each mold pull; cavity pressure sensors in the six problem cavities to flag filling issuesMold maintenance lead
Raising pressure to compensateProcess window locked; changes outside it require the shift lead's approval and a log entryQuality engineer

Each solution removes a confirmed cause rather than adding inspection. The startup sheet is written by the technicians themselves because they understand how the press behaves at each shift's start, and their ownership makes it more likely to be followed.

What this page is doingProposes the improvements.
6

Involving the Technicians

The technicians on the team will do more than carry out solutions designed by engineers. Each will lead one piece of the work: the night-shift technician will draft the startup sheet with the other two, the day-shift technician will run the moisture checks during the pilot and the swing-shift technician will train the rest of the technicians on the new process window. Project meetings will be held at shift overlap so that nobody gives up a day off for the project, and the technicians' improvement hours will be paid at their regular rate. The two technicians who were written up after the rejected lots have had the write-ups withdrawn, and one asked to join the team; his knowledge of how the press behaves at night has already shaped the startup sheet.

What this page is doingExplains how the team will work.
7

Lean Practices That Support the Project

Shah and Ward (2003), studying manufacturing plants, found that bundles of lean practices, including total preventive maintenance, quality practices and human resource practices, went with stronger operating results, and that the bundles worked best together. Two lean practices support this project. Scheduled check ring and vent maintenance is a form of preventive maintenance that stops failures before they produce defects. And standard work, the startup sheet, makes the best known method the normal method on every shift.

What this page is doingConnects to lean.
8

Pilot and Verification

The solutions will be piloted on Press 23 for four weeks. During the pilot, technicians will record shot weight every two hours on the same control charts used in the analysis, inspectors will continue the defect check sheet and the team will review both weekly. Success will be judged by three tests: the defect rate below 2 percent for the final two weeks, no special-cause signals on the shot weight chart attributable to the known causes and no new defect type rising to replace the old ones. If a test fails, the team will return to analysis before rolling the solutions out.

What this page is doingTests the solutions.
9

Controls

Control plan for Press 23

What is controlledHowFrequencyWhoReaction if out of limits
Resin moistureMoisture analyzer at hopperEach lot change and every 8 hoursMaterials handlerHold material; redry
Shot weightAverage and range chart at the pressEvery 2 hoursTechnician on shiftStop, check startup and resin; notify shift lead
Cavity pressure in six cavitiesSensor alarmContinuousAutomatic; technicianInspect vents
Check ring wearScheduled inspectionEvery 2,000 hoursMaintenanceReplace
Startup sheet followedAuditWeeklyQuality engineerRetrain
What this page is doingHolds the gains.
10

Costs and Benefits

The project's main costs are cavity pressure sensors and controller at about $38,000, a moisture analyzer at $9,000, a spare check ring and screw at $11,000 and team time of about $24,000, a total of about $82,000. If defects fall from 7.9 percent to 2 percent, annual scrap on this mold will fall by roughly $230,000, inspection time will drop and the risk of losing the medical account, worth about $6 million a year in sales, will fall sharply.

What this page is doingEstimates the return.
11

Risks to the Project

Three risks could derail the project. Production pressure could pull technicians off the team during busy weeks; the sponsor has agreed that project meetings will not be canceled without his approval. The cavity pressure sensors could take longer to install than planned, since the mold must be pulled; installation is scheduled for the mold's next planned maintenance. And the medical customer could reject another lot before the improvements take hold; until the pilot is complete, every lot from Press 23 will receive an extra sample inspection before shipment.

What this page is doingNames what could derail it.
12

Schedule

The team will finalize solutions in weeks one to three, install sensors and train technicians in weeks four to six, run the pilot in weeks seven to ten, review results in week eleven and hand the controls to production in weeks twelve to sixteen. If the pilot succeeds, the same approach will be applied to the plant's next two highest-scrap molds.

What this page is doingSets milestones.
13

References

Kaynak, H. (2003). The relationship between total quality management practices and their effects on firm performance. Journal of Operations Management, 21(4), 405-435. https://doi.org/10.1016/S0272-6963(03)00004-4

Shah, R., & Ward, P. T. (2003). Lean manufacturing: Context, practice bundles, and performance. Journal of Operations Management, 21(2), 129-149. https://doi.org/10.1016/S0272-6963(02)00108-0

Zu, X., Fredendall, L. D., & Douglas, T. J. (2008). The evolving theory of quality management: The role of Six Sigma. Journal of Operations Management, 26(5), 630-650. https://doi.org/10.1016/j.jom.2008.02.001

What the OL 324 Module 5 instructions ask for

Milestone Two in OL 324 has students plan a structured improvement project for the quality problem they analyzed. You will define the project's scope and team, propose solutions for each root cause, plan how solutions will be tested, describe how results will be verified and set up controls to sustain the gains. OL 324 improvement plans that score well use a recognized structure such as DMAIC, match each solution to a confirmed cause, pilot changes before rolling them out, verify results with data such as control charts and capability, bring press operators and technicians into the work and design controls, including procedures, process monitoring and reaction plans, so that improvement does not fade when the project ends.

How this OL 324 Module 5 milestone two example is built

The sample plans the improvement project for a 40-cavity diagnostic housing mold on Press 23 at Nashoba Precision Molding, a composite injection molder in Leominster, Massachusetts. A chartered team with a technician from each shift, the mold maintenance lead and the quality engineer works through DMAIC. Solutions match the four root causes: a resin drying protocol with moisture checks, a written startup procedure trained on all shifts, check ring replacement on a fixed interval and a vent cleaning schedule with cavity pressure sensors. A four-week pilot is verified with control charts, and controls include operator-run charts, a reaction plan and monthly audits. Research by Zu, Fredendall and Douglas, Shah and Ward and Kaynak supports the plan. Technicians lead pieces of the work, and the project's risks are named.

Where the OL 324 Module 5 rubric puts the points

Grading for the second OL 324 milestone usually centers on a clear project charter, solutions matched to confirmed root causes, a sound pilot and verification plan, effective controls to sustain gains, involvement of front-line staff, realistic costs and schedule and use of research, presented clearly. Strong OL 324 plans show the before-and-after data they will use to prove the improvement. Submissions lose credit for proposing solutions unconnected to the analysis, rolling out changes without a pilot, declaring success from a few good days, leaving out the control phase or assigning the work entirely to engineers.

OL 324 Module 5 help: the mistakes that cost points

Write a short project charter: the problem, scope, goals, team and timeline. For each confirmed root cause, propose a solution and explain how it removes the cause. Plan a pilot: what will change, for how long and what data you will collect. Decide how you will know it worked, such as defect rates and control charts before and after. Involve the people who run the process in designing and testing changes. Then plan controls: written procedures, training, monitoring by the people doing the work, a reaction plan for out-of-control signals and periodic audits. Estimate costs and savings, and set a schedule with milestones. Name the risks to the project and how you will manage them.

Get OL 324 Module 5 written to your instructions

Send the brief for Milestone Two in OL 324 and your problem analysis. We charter the improvement team, match solutions to each root cause, plan a pilot and how results will be verified, design controls that hold the gains and set costs and a schedule, with quality research behind the plan. Your first OL 324 improvement plan is free and returned in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More OL 324 papers and related BS Business Administration samples

OL 324 Module 5 questions, answered

Where can I find a free OL 324 Module 5 Milestone Two sample?

The full OL 324 Milestone Two is on this page: a DMAIC improvement project on a 40-cavity medical mold at a composite injection molder.

What is DMAIC?

A five-step improvement method used in Six Sigma: define the problem, measure the current process, analyze causes, improve with tested solutions and control to sustain gains.

Why pilot a quality improvement before rollout?

A pilot tests whether solutions work in real conditions, reveals side effects and provides data to convince others before the change spreads.

What is a control plan?

A document listing what will be monitored, how often, by whom, the acceptable limits and the reaction if a measure goes out of control.

How do Six Sigma and lean relate to quality management?

Six Sigma adds structured roles, a project method and metrics to traditional quality management, and lean adds practices to remove waste; research suggests they complement each other.