Thirty-One Percent Could Open the Gate: The Sprint Four Review for the Big Lake Gallery
[Student Name]
Southern New Hampshire University
QSO 435: Adaptive Project Management
Sprint Review Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Thirty-One Percent Could Open the Gate: The Sprint Four Review for the Big Lake Gallery
Introduction
Sprint four of the Big Lake gallery ran from November 9 to November 20, 2026, and ended with a prototype test on Saturday, November 21. It was the first sprint in which three exhibits could be tested at once in rough form: a plywood water table with working lock gates, a cardboard and lumber freighter wheelhouse and a fabric-covered frame for the shipwreck tunnel. This assignment reports what the sprint delivered, what families did with the prototypes, how the findings change the backlog, what the team's velocity says about the release plan and what the product owner decided.
Sprint Results
The team planned 30 points and completed 27 to the definition of done. The three points not finished belonged to the wheelhouse steering linkage, which failed its pinch-point check and was returned to the backlog. Over four sprints, velocity has been 18, 24, 29 and 27, an average of 24.5 points against the forecast of 26. The first sprint was low because the team was learning the cadence and the shop was still being organized; the last three average about 26.7. The product owner chose to forecast with the four-sprint average rather than the recent three, because the winter holidays and the shop's repair load make the next stretch harder, not easier.
Prototype Test Findings
Fifty-eight families visited the test session, including nine children with disabilities. The evaluator and two volunteers observed each prototype and timed visits.
Prototype test results, November 21
| Prototype | What was measured | Result | Target |
|---|---|---|---|
| Water table, lock gates | Children aged 3 to 4 who opened a gate unaided | 31% of 26 | 80% |
| Water table, lock gates | Children aged 5 to 8 who opened a gate unaided | 92% of 38 | 80% |
| Freighter wheelhouse | Average family dwell time | 4.2 minutes | 3 minutes |
| Freighter wheelhouse | Times more than six children were inside at once | 7 in 3 hours | None |
| Shipwreck tunnel | Parents of toddlers who hesitated or refused | 18% of 22 | Under 5% |
| Shipwreck tunnel | Children using wheelchairs who found the lantern from a window | 3 of 3 | All |
The water table worked for older children but not for the youngest, the gallery's core audience on weekday mornings, when preschool groups and grandparents fill the museum. Watching them showed why: the gate handles were at 30 inches and needed a pull of about four pounds. The wheelhouse was more popular than expected, which is good for dwell time but led to crowding. Parents hesitated at the shipwreck because they could not see their toddlers once inside.
Backlog Changes
Backlog changes from the test
| Change | Type | Points | Priority |
|---|---|---|---|
| Lower gate handles to 22 inches and reduce pull to under 2 pounds | Revised story, new criteria | 8 | Must |
| Add a second viewing window and a parent sightline at the tunnel midpoint | New story | 14 | Must |
| Add a "captain's line" floor marking and timer at the wheelhouse | New story | 3 | Should |
| Repair steering linkage pinch point | Returned story | 3 | Must |
The first two are must-haves because they affect safety and the core audience; together they add 22 points of new scope, raising the backlog from 410 to 432 points. The wheelhouse crowding is a should-have: the gallery could open with it, managed by floor staff. Moe et al. (2010) found that teams work best when the whole team, not one specialist, owns product decisions; the fabricators proposed the gate redesign themselves after watching the children, and the educator proposed the sightline.
Velocity and the Release Plan
After sprint four, the team has completed 98 points, of which 90 are must-haves. Must-haves now total 274 points, the original 260 plus the 14-point tunnel story, with the 8-point gate change replacing part of an existing story. That leaves 184 must-have points. The should-have and could-have stories, 158 points, have barely started, since the team deliberately built must-haves first.
Must-have forecast after sprint four
| Velocity assumption | Sprints needed for 184 points | Must-haves done by |
|---|---|---|
| Low, 21 points | About 8.8 | Sprint 13 |
| Average, 24.5 points | About 7.5 | Sprint 12 |
| High, 29 points | About 6.3 | Sprint 11 |
The original plan finished must-haves in sprint 10. The new forecast puts them in sprint 11 to 13. Part of the slip is scope growth, 22 points that are worth building, and part is velocity slightly below forecast. The total backlog of 432 points against remaining capacity of about 14 sprints at 24.5, or 343 points, plus 98 done, means about 441 points of total capacity: just enough, with almost no buffer left for the could-haves.
Decisions
Serrador and Pinto (2015) found that the success of agile projects was associated with how much they used agile practices such as adapting scope, rather than with following a fixed plan. The product owner made three decisions. First, the two new must-have stories enter sprints five and six. Second, two should-have stories, the ice fishing house's sound effects and the storm interactive's tide chart, move behind all must-haves, so that must-haves can still finish by sprint 12. Third, the could-have stories are marked as unlikely for opening and will be reported to the board as such. The two-sprint buffer is kept for testing findings still to come. These decisions were explained to the executive director the following Monday, because the could-have stories include the live weather feed that a board member had championed, and the product owner wanted that news delivered in person rather than in a report.
Retrospective
At the retrospective, the team found that safety checks were done at the end of the sprint, which is why the steering linkage failed late. A broad review of agile research found that practices work differently in different settings and must be adapted by the team (Dybå & Dingsøyr, 2008). The team's adaptation is to do a quick pinch-point and edge check when each prototype part comes off the bench, not only at the end.
Conclusion
Sprint four showed that the water table failed its youngest users and that parents need to see into the shipwreck. Those findings add 22 points the gallery must have. With velocity averaging 24.5, must-haves now land around sprint 12, so two should-haves move back and the buffer stays.
References
Dybå, T., & Dingsøyr, T. (2008). Empirical studies of agile software development: A systematic review. Information and Software Technology, 50(9-10), 833-859. https://doi.org/10.1016/j.infsof.2008.01.006
Moe, N. B., Dingsøyr, T., & Dybå, T. (2010). A teamwork model for understanding an agile team: A case study of a Scrum project. Information and Software Technology, 52(5), 480-491. https://doi.org/10.1016/j.infsof.2009.11.004
Serrador, P., & Pinto, J. K. (2015). Does Agile work? A quantitative analysis of agile project success. International Journal of Project Management, 33(5), 1040-1051. https://doi.org/10.1016/j.ijproman.2015.01.006
What the QSO 435 Module 5 instructions ask for
The QSO 435 Module 5 assignment usually asks students to analyze a sprint or iteration and its results. Expect to summarize what was planned and completed, report feedback from the sprint review, calculate velocity and update a burndown or burnup chart, assess whether the release plan remains realistic, propose changes to the backlog and identify improvements for the team's process from the retrospective. Strong assignments connect specific user feedback to specific backlog changes, distinguish scope growth from slow delivery, use several sprints of velocity rather than one, show the effect of changes on the release forecast and make prioritization decisions explicit rather than simply adding work.
How this QSO 435 Module 5 sprint review assignment example is built
The assignment analyzes sprint four of Big Lake at Harborlight Children's Museum, a fictional Duluth museum. At the Saturday prototype test, 58 families used three prototypes: only 31 percent of three- and four-year-olds could open a lock gate on the water table, families stayed 4.2 minutes at the wheelhouse against a target of three and 18 percent of parents hesitated to let toddlers into the shipwreck tunnel. The findings add 22 points of stories, raising scope from 410 to 432. Velocity over four sprints averages 24.5 against a forecast of 26. The burnup shows must-haves landing around sprint 12 instead of 10, so two should-have stories move back and the buffer is kept. Moe and colleagues, Serrador and Pinto and Dybå and Dingsøyr inform the analysis.
Where the QSO 435 Module 5 rubric puts the points
The QSO 435 sprint review assignment is commonly graded on an accurate summary of planned and completed work, feedback reported with evidence, a clear link from findings to backlog changes, correct velocity and burnup calculations, a realistic reassessment of the release plan, explicit prioritization decisions and process improvements from the retrospective. The strongest assignments separate scope growth from delivery speed and show the forecast before and after the decisions. Credit drops when feedback is summarized without numbers, new work is simply added, velocity from one sprint drives the forecast or the release plan is declared on track without arithmetic. Tables, clear writing and APA citations complete the grade.
QSO 435 Module 5 help: the mistakes that cost points
Start with what the sprint planned and what met the definition of done. Then report what users did in the review, with numbers where you can: how many tried something, how many succeeded, how long they stayed. Turn each important finding into a backlog change: a new story, a changed acceptance criterion or a dropped idea, with an estimate. Update velocity using every sprint so far and redraw the burnup chart with the new scope. Divide the remaining work by a range of velocities and see whether the release dates still hold. If they do not, decide what moves, and say who decided. Finish with one process improvement from the retrospective. A common mistake is reporting feedback without changing the backlog; another is hiding scope growth as delay.
Get QSO 435 Module 5 written to your instructions
Share the QSO 435 Module 5 instructions and your sprint data or scenario. A writer analyzes the sprint review findings, turns feedback into backlog changes, calculates velocity and the burnup forecast, judges whether the release plan still holds and recommends what the product owner should reorder, add or defer, citing agile research. Your first QSO 435 paper is free, completed in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 435 papers and related BS Operations Management samples
- QSO 435 Module 1 Discussion: When an Exhibit Should Be Built Adaptively
- QSO 435 Module 2 Backlog and Release Planning Assignment: Visitor Stories and Planning Poker
- QSO 435 Module 3 Project One: The Adaptive Project Plan
- QSO 435 Module 4 Discussion: What Velocity Can and Cannot Promise
- QSO 435 Module 6 Discussion: Kanban for the Fabrication Shop
- QSO 435 Module 7 Project Two: The Release and Handover Review
- QSO 435 Module 8 Discussion: Retrospectives People Can Speak Up In
- HRM 400 Module 6 Reward Alignment Assignment: Retiring the Individual Bonus for Gainsharing
- OL 125 Module 2 Communication Analysis Assignment: Communication Breakdown at Shift Change
- OL 324 Module 4 Discussion: Blaming Workers or Fixing the System
- QSO 322 Module 7 Project Two: The Logistics Improvement Plan
QSO 435 Module 5 questions, answered
Where can I find a free QSO 435 Module 5 Sprint Review Assignment sample?
The complete QSO 435 Module 5 assignment is on this page: a sprint review analysis for an invented children's museum gallery.
What happens in a sprint review?
The team shows the increment to stakeholders or users, gathers feedback and discusses with the product owner what to build next, often changing the backlog.
What is a burnup chart?
A chart that plots cumulative completed work and total scope over time, so that progress and scope changes are visible separately.
How should feedback change the backlog?
Each significant finding should become a new or revised story with acceptance criteria and an estimate, prioritized against existing work by the product owner.
How does scope growth differ from slow delivery?
Scope growth means more work has been added to the backlog; slow delivery means the team completes less work per sprint than forecast; both delay releases but need different responses.