QSO 435 Module 5 Sprint Review Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 435 Module 5 Sprint Review Assignment sample analyzes a sprint review, its prototype test results and the team's agile metrics and decides how the backlog and release plan should change. SNHU QSO 435 (QSO-435) assigns this analysis in Module 5 of its adaptive project management course in the BS Operations Management. The sprint is the fourth of eighteen on Big Lake, a Lake Superior gallery at Harborlight Children's Museum, an invented museum in Duluth, Minnesota. The paper reads what 58 families did with three prototypes, turns the findings into new stories, recalculates the forecast and decides what moves.

CourseQSO 435 Adaptive Project Management
ModuleModule 5
Paper typeundergraduate assignment analyzing a sprint review, prototype test results and agile metrics and deciding how the backlog and release plan should change
LengthAbout 1,020 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 435 Module 5

1

Thirty-One Percent Could Open the Gate: The Sprint Four Review for the Big Lake Gallery

[Student Name]

Southern New Hampshire University

QSO 435: Adaptive Project Management

Sprint Review Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe test results, velocity and backlog figures for Harborlight Children's Museum in this QSO 435 assignment are invented.
2

Thirty-One Percent Could Open the Gate: The Sprint Four Review for the Big Lake Gallery

Introduction

Sprint four of the Big Lake gallery ran from November 9 to November 20, 2026, and ended with a prototype test on Saturday, November 21. It was the first sprint in which three exhibits could be tested at once in rough form: a plywood water table with working lock gates, a cardboard and lumber freighter wheelhouse and a fabric-covered frame for the shipwreck tunnel. This assignment reports what the sprint delivered, what families did with the prototypes, how the findings change the backlog, what the team's velocity says about the release plan and what the product owner decided.

What this page is doingSets the sprint in context.
3

Sprint Results

The team planned 30 points and completed 27 to the definition of done. The three points not finished belonged to the wheelhouse steering linkage, which failed its pinch-point check and was returned to the backlog. Over four sprints, velocity has been 18, 24, 29 and 27, an average of 24.5 points against the forecast of 26. The first sprint was low because the team was learning the cadence and the shop was still being organized; the last three average about 26.7. The product owner chose to forecast with the four-sprint average rather than the recent three, because the winter holidays and the shop's repair load make the next stretch harder, not easier.

What this page is doingReports what was done.
4

Prototype Test Findings

Fifty-eight families visited the test session, including nine children with disabilities. The evaluator and two volunteers observed each prototype and timed visits.

Prototype test results, November 21

PrototypeWhat was measuredResultTarget
Water table, lock gatesChildren aged 3 to 4 who opened a gate unaided31% of 2680%
Water table, lock gatesChildren aged 5 to 8 who opened a gate unaided92% of 3880%
Freighter wheelhouseAverage family dwell time4.2 minutes3 minutes
Freighter wheelhouseTimes more than six children were inside at once7 in 3 hoursNone
Shipwreck tunnelParents of toddlers who hesitated or refused18% of 22Under 5%
Shipwreck tunnelChildren using wheelchairs who found the lantern from a window3 of 3All

The water table worked for older children but not for the youngest, the gallery's core audience on weekday mornings, when preschool groups and grandparents fill the museum. Watching them showed why: the gate handles were at 30 inches and needed a pull of about four pounds. The wheelhouse was more popular than expected, which is good for dwell time but led to crowding. Parents hesitated at the shipwreck because they could not see their toddlers once inside.

What this page is doingReports what families did.
5

Backlog Changes

Backlog changes from the test

ChangeTypePointsPriority
Lower gate handles to 22 inches and reduce pull to under 2 poundsRevised story, new criteria8Must
Add a second viewing window and a parent sightline at the tunnel midpointNew story14Must
Add a "captain's line" floor marking and timer at the wheelhouseNew story3Should
Repair steering linkage pinch pointReturned story3Must

The first two are must-haves because they affect safety and the core audience; together they add 22 points of new scope, raising the backlog from 410 to 432 points. The wheelhouse crowding is a should-have: the gallery could open with it, managed by floor staff. Moe et al. (2010) found that teams work best when the whole team, not one specialist, owns product decisions; the fabricators proposed the gate redesign themselves after watching the children, and the educator proposed the sightline.

What this page is doingTurns findings into stories.
6

Velocity and the Release Plan

After sprint four, the team has completed 98 points, of which 90 are must-haves. Must-haves now total 274 points, the original 260 plus the 14-point tunnel story, with the 8-point gate change replacing part of an existing story. That leaves 184 must-have points. The should-have and could-have stories, 158 points, have barely started, since the team deliberately built must-haves first.

Must-have forecast after sprint four

Velocity assumptionSprints needed for 184 pointsMust-haves done by
Low, 21 pointsAbout 8.8Sprint 13
Average, 24.5 pointsAbout 7.5Sprint 12
High, 29 pointsAbout 6.3Sprint 11

The original plan finished must-haves in sprint 10. The new forecast puts them in sprint 11 to 13. Part of the slip is scope growth, 22 points that are worth building, and part is velocity slightly below forecast. The total backlog of 432 points against remaining capacity of about 14 sprints at 24.5, or 343 points, plus 98 done, means about 441 points of total capacity: just enough, with almost no buffer left for the could-haves.

What this page is doingRecalculates the forecast.
7

Decisions

Serrador and Pinto (2015) found that the success of agile projects was associated with how much they used agile practices such as adapting scope, rather than with following a fixed plan. The product owner made three decisions. First, the two new must-have stories enter sprints five and six. Second, two should-have stories, the ice fishing house's sound effects and the storm interactive's tide chart, move behind all must-haves, so that must-haves can still finish by sprint 12. Third, the could-have stories are marked as unlikely for opening and will be reported to the board as such. The two-sprint buffer is kept for testing findings still to come. These decisions were explained to the executive director the following Monday, because the could-have stories include the live weather feed that a board member had championed, and the product owner wanted that news delivered in person rather than in a report.

What this page is doingRecords what the product owner chose.
8

Retrospective

At the retrospective, the team found that safety checks were done at the end of the sprint, which is why the steering linkage failed late. A broad review of agile research found that practices work differently in different settings and must be adapted by the team (Dybå & Dingsøyr, 2008). The team's adaptation is to do a quick pinch-point and edge check when each prototype part comes off the bench, not only at the end.

What this page is doingRecords the process improvement.
9

Conclusion

Sprint four showed that the water table failed its youngest users and that parents need to see into the shipwreck. Those findings add 22 points the gallery must have. With velocity averaging 24.5, must-haves now land around sprint 12, so two should-haves move back and the buffer stays.

What this page is doingSummarizes the review.
10

References

Dybå, T., & Dingsøyr, T. (2008). Empirical studies of agile software development: A systematic review. Information and Software Technology, 50(9-10), 833-859. https://doi.org/10.1016/j.infsof.2008.01.006

Moe, N. B., Dingsøyr, T., & Dybå, T. (2010). A teamwork model for understanding an agile team: A case study of a Scrum project. Information and Software Technology, 52(5), 480-491. https://doi.org/10.1016/j.infsof.2009.11.004

Serrador, P., & Pinto, J. K. (2015). Does Agile work? A quantitative analysis of agile project success. International Journal of Project Management, 33(5), 1040-1051. https://doi.org/10.1016/j.ijproman.2015.01.006

What the QSO 435 Module 5 instructions ask for

The QSO 435 Module 5 assignment usually asks students to analyze a sprint or iteration and its results. Expect to summarize what was planned and completed, report feedback from the sprint review, calculate velocity and update a burndown or burnup chart, assess whether the release plan remains realistic, propose changes to the backlog and identify improvements for the team's process from the retrospective. Strong assignments connect specific user feedback to specific backlog changes, distinguish scope growth from slow delivery, use several sprints of velocity rather than one, show the effect of changes on the release forecast and make prioritization decisions explicit rather than simply adding work.

How this QSO 435 Module 5 sprint review assignment example is built

The assignment analyzes sprint four of Big Lake at Harborlight Children's Museum, a fictional Duluth museum. At the Saturday prototype test, 58 families used three prototypes: only 31 percent of three- and four-year-olds could open a lock gate on the water table, families stayed 4.2 minutes at the wheelhouse against a target of three and 18 percent of parents hesitated to let toddlers into the shipwreck tunnel. The findings add 22 points of stories, raising scope from 410 to 432. Velocity over four sprints averages 24.5 against a forecast of 26. The burnup shows must-haves landing around sprint 12 instead of 10, so two should-have stories move back and the buffer is kept. Moe and colleagues, Serrador and Pinto and Dybå and Dingsøyr inform the analysis.

Where the QSO 435 Module 5 rubric puts the points

The QSO 435 sprint review assignment is commonly graded on an accurate summary of planned and completed work, feedback reported with evidence, a clear link from findings to backlog changes, correct velocity and burnup calculations, a realistic reassessment of the release plan, explicit prioritization decisions and process improvements from the retrospective. The strongest assignments separate scope growth from delivery speed and show the forecast before and after the decisions. Credit drops when feedback is summarized without numbers, new work is simply added, velocity from one sprint drives the forecast or the release plan is declared on track without arithmetic. Tables, clear writing and APA citations complete the grade.

QSO 435 Module 5 help: the mistakes that cost points

Start with what the sprint planned and what met the definition of done. Then report what users did in the review, with numbers where you can: how many tried something, how many succeeded, how long they stayed. Turn each important finding into a backlog change: a new story, a changed acceptance criterion or a dropped idea, with an estimate. Update velocity using every sprint so far and redraw the burnup chart with the new scope. Divide the remaining work by a range of velocities and see whether the release dates still hold. If they do not, decide what moves, and say who decided. Finish with one process improvement from the retrospective. A common mistake is reporting feedback without changing the backlog; another is hiding scope growth as delay.

Get QSO 435 Module 5 written to your instructions

Share the QSO 435 Module 5 instructions and your sprint data or scenario. A writer analyzes the sprint review findings, turns feedback into backlog changes, calculates velocity and the burnup forecast, judges whether the release plan still holds and recommends what the product owner should reorder, add or defer, citing agile research. Your first QSO 435 paper is free, completed in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 435 papers and related BS Operations Management samples

QSO 435 Module 5 questions, answered

Where can I find a free QSO 435 Module 5 Sprint Review Assignment sample?

The complete QSO 435 Module 5 assignment is on this page: a sprint review analysis for an invented children's museum gallery.

What happens in a sprint review?

The team shows the increment to stakeholders or users, gathers feedback and discusses with the product owner what to build next, often changing the backlog.

What is a burnup chart?

A chart that plots cumulative completed work and total scope over time, so that progress and scope changes are visible separately.

How should feedback change the backlog?

Each significant finding should become a new or revised story with acceptance criteria and an estimate, prioritized against existing work by the product owner.

How does scope growth differ from slow delivery?

Scope growth means more work has been added to the backlog; slow delivery means the team completes less work per sprint than forecast; both delay releases but need different responses.