| Course | QSO 450 Transportation Management |
|---|---|
| Module | Module 7 |
| Paper type | undergraduate project presenting a costed transportation improvement plan with initiatives, savings, measures, timeline and risks |
| Length | About 1,040 words, 6 pages |
| Format | APA 7 student paper |
| School | Southern New Hampshire University |
| Program | BS Operations Management |
| Updated | October 2026 |
Free sample paper for QSO 450 Module 7
From 6.8 to 6.2 Percent of Sales: The Transportation Improvement Plan for Bristol Creek
[Student Name]
Southern New Hampshire University
QSO 450: Transportation Management
Project Two: Transportation Improvement Plan
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
From 6.8 to 6.2 Percent of Sales: The Transportation Improvement Plan for Bristol Creek
Current State
Last year Bristol Creek Coach Components paid about $9.6 million to move its freight, a share of sales well above what a short-haul manufacturer should need. The transportation analysis found that its private fleet runs about 58 percent full on fixed routes, that late plant deliveries drive most of its $600,000 of expedites, that oversized doors cost more and break more by parcel, that its LTL freight is scattered across about 140 carriers, that nobody audits invoices and that inbound containers incur detention at the Chicago ramp. Opportunities worth about $1.07 million a year were identified. This plan turns them into initiatives with costs, owners, measures and a timeline.
Initiatives
Reroute the milk runs. A routing tool will plan the next day's plant deliveries every afternoon from the releases the plants send, departures set by delivery windows and drivers dispatched by tablet. The redesign reduces daily routes from 14 to 11.
Ship oversized doors by LTL. Entry doors will be palletized and shipped by regional LTL carriers, singly for urgent orders and consolidated weekly for large dealers.
Contract four LTL carriers. A bid among twelve carriers, scored on on-time delivery, damage, cost, billing accuracy and coverage, will award aftermarket LTL freight to one national, two regional and one specialty carrier.
Adopt a transportation management system. A subscription system will rate and book aftermarket shipments, hold the plant routes, track deliveries, audit invoices before payment and store a history of every shipment.
Schedule inbound container appointments. Receiving will book appointments with the drayage carrier when containers are released at the ramp, so containers are unloaded within free time.
Pilot a shared backhaul. Bristol Creek's drayage trucks return empty to Chicago, as do those of a cabinet maker two miles away. A three-month pilot will test loading the cabinet maker's outbound freight on returning trucks.
Costs and Savings
Effect on the freight bill
| Initiative | Annual saving | Annual cost | Net |
|---|---|---|---|
| Rerouted milk runs | $430,000 | Included in system | $430,000 |
| Fewer expedites from on-time plant deliveries | $105,000 | $105,000 | |
| Oversized doors by LTL, freight and damage | $188,000 | $188,000 | |
| Contracted LTL carriers | $144,000 | $144,000 | |
| Invoice audit | $56,000 | $56,000 | |
| Inbound appointments | $36,000 | $36,000 | |
| Transportation management system subscription | $85,000 | minus $85,000 | |
| Total | $959,000 | $85,000 | $874,000 |
| Measure | Last year | After the plan | |
| Freight spend | About $9.6 million | About $8.7 million | |
| Freight as a share of sales | 6.8% | About 6.2% |
One-time costs are about $60,000 to implement the system and about $12,000 for drivers' tablets, about $72,000 in total. The expedite saving counts only half the fleet-related hot shots, and only those caused by late deliveries, so it does not overlap with the rerouting saving, which comes from fewer trucks and miles. The shared backhaul is not counted until the pilot shows results.
Measures
Measures, baselines and targets
| Measure | Baseline | Target after one year | Owner |
|---|---|---|---|
| Daily plant routes | 14 | 11 | Transportation manager |
| Average fleet fill by cube | 58% | 75% | Transportation manager |
| On-time to plant windows | 96.1% | 98.5% | Transportation manager |
| Expedite spend | $600,000 | Under $400,000 | Customer service manager |
| Door damage rate | 6.1% | Under 2% | Shipping supervisor |
| Active LTL carriers | About 140 | 4 | Logistics manager |
| Invoices matching contracted rates | About 96.5% | 99.5% | Accounts payable supervisor |
| Container detention | About $48,000 | Under $12,000 | Receiving supervisor |
McKinnon and Piecyk (2009) show that measuring freight performance, including emissions, depends on recording loads and distances consistently, which the transportation system will make routine. Fewer miles also mean lower diesel use; the system's records will let Bristol Creek report fleet fuel and emissions for the first time.
Timeline
Six-month timeline
| Months | Work |
|---|---|
| 1 | Select and configure the transportation system; load plant locations, windows and product dimensions |
| 2 | Run new routes in parallel with old ones for two weeks; driver training |
| 2 to 3 | Switch plant routes; return three leased trucks as leases end |
| 2 to 4 | Run the LTL bid and sign carrier contracts |
| 4 | Move doors to palletized LTL with contracted carriers; start invoice audit |
| 4 | Begin inbound appointment scheduling |
| 5 to 6 | Shared backhaul pilot |
Routing comes first because it is the largest saving and because the expedite saving depends on it. Doors move to LTL only after carrier contracts are signed, so that pallets go to carriers already measured on damage.
Stakeholders
Drivers will run different routes each day, which some will resist. They will help test the new routes during the parallel run, no driver will lose a job and two will become floaters for second deliveries. RV plants will receive more reliable deliveries; six with the tightest windows will be asked whether a slight widening would allow further combining. Carriers gain a larger, steadier share of Bristol Creek's freight in exchange for quarterly scorecards. Dealers will see doors arrive a day later on average but intact. For the backhaul pilot, Mason et al. (2007) show that horizontal collaboration between shippers can fill empty trucks when both gain, so the cabinet maker will pay a share of the drayage cost below its current rate.
Future Procurement
Once a year of shipment data is in the system, Bristol Creek could bid its inbound truckload lanes as well. Sheffi (2004) reports that combinatorial auctions, in which a carrier may offer one price for a whole bundle of lanes, have cut costs for shippers because carriers can price bundles that balance their own networks. Bristol Creek's inbound lanes are few, but grouping them with backhaul opportunities could attract better prices.
Risks
Plants may change release times late in the day, upsetting next-day routes; the response is a cutoff agreed with each plant and one floater truck for late changes. Drivers may resist; the response is their involvement in testing and no job losses. The system may rate doors wrongly if dimensions are wrong; the response is checking product data before launch. New LTL carriers may underperform; the response is quarterly scorecards and volume shifts.
Conclusion
The plan cuts Bristol Creek's freight bill by about $874,000 a year, from 6.8 to about 6.2 percent of sales, for about $72,000 up front, while raising on-time delivery to plants and cutting damage to dealers. Its largest gains come from routing the company's own trucks well, and its most lasting gain is the data a transportation system will collect on every shipment.
References
Mason, R., Lalwani, C., & Boughton, R. (2007). Combining vertical and horizontal collaboration for transport optimisation. Supply Chain Management: An International Journal, 12(3), 187-199. https://doi.org/10.1108/13598540710742509
McKinnon, A. C., & Piecyk, M. I. (2009). Measurement of CO2 emissions from road freight transport: A review of UK experience. Energy Policy, 37(10), 3733-3742. https://doi.org/10.1016/j.enpol.2009.07.007
Sheffi, Y. (2004). Combinatorial auctions in the procurement of transportation services. Interfaces, 34(4), 245-252. https://doi.org/10.1287/inte.1040.0075
What the QSO 450 Module 7 instructions ask for
The last QSO 450 project usually brings the course's analysis together into one plan for moving an organization's freight better. Students set out where the company stands, propose changes to routes, modes, carriers, technology or facilities, cost each change and its savings, choose a few measures with starting values and goals, give each change an owner and a schedule and say how drivers, carriers, customers and suppliers will be affected. Plans earn the most credit when every saving traces back to a measured problem, overlapping savings are counted only once, the order of the work follows the size of each gain and what it depends on and service to customers is measured as carefully as cost.
How this QSO 450 Module 7 project two example is built
The project turns Bristol Creek Coach Components' transportation analysis into a plan. Bristol Creek, a fictional RV parts maker in Elkhart, Indiana, would reroute its milk runs to RV plants with a routing tool and order-based departures, ship oversized doors palletized by LTL, contract four LTL carriers through a scored bid, adopt a transportation management system with invoice audit, schedule inbound container appointments and pilot a shared backhaul with another Elkhart shipper. One-time costs of about $72,000 and annual net savings of about $874,000 would cut the freight bill from about $9.6 million to about $8.7 million. Eight measures, a six-month timeline and risks are set out. Sheffi, McKinnon and Piecyk and Mason and colleagues inform the plan.
Where the QSO 450 Module 7 rubric puts the points
Grading for QSO 450 Project Two weighs whether the plan rests on the earlier freight analysis, whether its savings and costs add up once and only once, whether each measure starts from a real figure and has a named owner, whether the order of work makes sense given what depends on what and whether drivers, plants, carriers and suppliers have a part to play. Top projects report the change in the freight bill and in delivery performance side by side. Marks are lost for savings counted twice, measures with no starting point, a schedule that ignores dependencies, a plan that forgets the people who drive the trucks or risks described in general terms. Tables, plain writing and APA citations are graded too.
QSO 450 Module 7 help: the mistakes that cost points
Open with three or four numbers that describe today: what freight costs, how much of sales it takes and how reliable deliveries are. Give each change you propose a line of its own showing the problem it fixes, what it costs once, what it costs every year and what it saves, then look for places where two changes claim the same money and keep only one. Total the effect on the freight bill. Pick a short list of measures, with today's figure, a goal and the person accountable. Put the biggest gain first unless something else must happen before it. Explain what drivers, plants, carriers and suppliers need to do and what they get. Close with the risks you can name. Plans often fail by quoting savings without costs or by measuring cost while ignoring service.
Get QSO 450 Module 7 written to your instructions
Upload the QSO 450 Project Two guidelines and the freight analysis you have already done. A writer turns it into one plan: each change tied to a measured problem, its one-time cost, yearly cost and saving, the effect on the freight bill, a few measures with starting figures and owners, a schedule and the risks, with transportation research behind it. Your first QSO 450 project is free, delivered in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 450 papers and related BS Operations Management samples
- QSO 450 Module 1 Discussion: What Transportation Costs and Why It Matters
- QSO 450 Module 2 Mode and Carrier Selection Assignment: Doors, Windows and Steps to 2,600 Dealers
- QSO 450 Module 3 Project One: A Transportation Analysis of Every Flow
- QSO 450 Module 4 Discussion: Private Fleet or Dedicated Carriage?
- QSO 450 Module 5 Routing Assignment: Milk Runs to 42 RV Plants
- QSO 450 Module 6 Discussion: What a Transportation Management System Would Change
- QSO 450 Module 8 Discussion: Electric Trucks on the 60-Mile Routes
- INT 422 Module 5 Milestone Two: Joint Venture, License or Retreat in China
- FIN 336 Module 1 Discussion: Why a Grain Bin Maker Looks to Brazil
- OL 211 Module 4 Discussion: Recruitment and Selection Methods
- HRM 300 Module 1 Discussion: Experience Is More Than Engagement
QSO 450 Module 7 questions, answered
Where can I find a free QSO 450 Module 7 Project Two sample?
This page holds the complete QSO 450 Project Two: a transportation improvement plan for an invented RV parts maker.
What should a transportation improvement plan include?
A short account of today's freight cost and service, the changes proposed and the problems they fix, what each costs and saves, a handful of measured goals with owners, a schedule and the main risks.
How do you avoid double counting transportation savings?
By assigning each saving to one initiative and checking overlaps, such as routing changes that also reduce expedites, so the total reflects real change.
Which measures track transportation performance?
Freight cost per unit and as a share of sales, on-time delivery, damage, vehicle fill, empty miles, expedite spend, invoice accuracy and carrier scorecards.
Why involve drivers in transportation changes?
Drivers know the routes, customers and problems, and changes to routes and schedules affect their days, so their input improves the plan and their support makes it work.