QSO 489 Module 7 Final Project Example

Reviewed by Portia Lambrick, MBA

This QSO 489 Module 7 Final Project sample presents a complete operations improvement plan with its diagnosis, recommendations, financial case, implementation, risks, governance and measures. SNHU QSO 489 (QSO-489) assigns this final project in Module 7 of the BS Operations Management capstone, drawing together the earlier milestones. The operation is Copperline Finishing Company, an invented Muncie, Indiana, powder coating job shop that quotes seven days and takes almost twelve. The plan explains why, recommends four inexpensive changes that act on its constraint and its queue, shows what they cost and save and sets out how the shop would run and measure them.

CourseQSO 489 Capstone in Operations Management
ModuleModule 7
Paper typeundergraduate capstone final project presenting a complete operations improvement plan with diagnosis, recommendations, financial case, implementation, risks, governance and measures
LengthAbout 1,360 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 489 Module 7

1

From 11.6 Days to Seven: The Operations Improvement Plan for Copperline Finishing Company

[Student Name]

Southern New Hampshire University

QSO 489: Capstone in Operations Management

Final Project

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe diagnosis, costs, savings and targets for Copperline Finishing Company in this QSO 489 project are invented.
2

From 11.6 Days to Seven: The Operations Improvement Plan for Copperline Finishing Company

Executive Summary

Copperline Finishing Company promises a seven-day lead time but averages 11.6 days and ships 71 percent of orders on time, and two large customers left last year over delays. The capstone study found the days were lost in queues, created by admitting more work than the conveyor line, the shop's constraint, can process, and that cleanouts between colors and second passes for rework use up the line's day. Four changes are recommended: sequencing colors, capping the work on the floor, controlling the washer bath daily and planning shipments. They cost about $50,000 to put in place and about $95,000 a year to run, and they should save about $526,000 a year, bring lead time to about seven days and lift on-time delivery to about 92 percent within a year.

What this page is doingGives the plan on one page.
3

The Organization and the Problem

Copperline, founded in 1984, finishes metal parts for roughly two hundred regional manufacturers whose own paint lines are too small or too busy, and its sales of about $18.5 million come mainly from farm equipment, outdoor furniture and sign makers. Its edge over the big regional coaters is responsiveness: it takes short runs, custom colors and tight dates. That edge is eroding. Saturday overtime has become routine at about $310,000 a year, nearly one rack in thirteen is coated twice and credits and expedited deliveries cost about $120,000 more. The targets set at the start of the capstone remain: 92 percent on time, an average lead time of seven days and rework below 3.5 percent within twelve months.

What this page is doingSets the context.
4

What the Analysis Found

When operators stamped every traveler for three weeks, the records showed that a job spends only a few hours of its 11.6 days being washed, coated or cured; about 11.4 days are waiting, most of it in front of the conveyor line. Morning counts found about 3,100 racks in the building. At throughput of about 267 racks a day, Little's law gives 11.6 days, matching the travelers. The conveyor line has a theoretical capacity of about 260 racks a day but delivers about 181, because 22 color changes a day take about 27.5 percent of its time, against demand of about 202 including rework. Rework is led by adhesion failures, 84 percent of which occurred on days when the washer's phosphate stage was out of specification, a drift the weekly test missed. Packed jobs wait about two days for pickup.

The law of swift, even flow set out by Schmenner and Swink (1998) holds that a process grows more productive as materials move through it faster and more steadily. The analysis points to exactly that: Copperline's workers are busy, but its work does not flow.

What this page is doingSummarizes the evidence.
5

Root Causes

Read together, the milestones point to four causes. The shop admits work faster than it can finish it, so racks pile up. Its constraint spends much of its day changing colors because the schedule ignores color. A drifting phosphate bath creates rework that has to go around the constraint a second time. And finished work sits waiting because nobody plans pickups against what will be done.

What this page is doingNames what the plan must fix.
6

Recommendations

Color sequencing. Within a window of one working day, booth leads will run jobs from light colors to dark and group repeats, which roughly halves the daily cleanouts and lifts the conveyor line's effective output from about 181 to about 212 racks.

A work-in-progress limit. Following the CONWIP approach proposed by Spearman et al. (1990), in which a fixed ceiling on work in the system means a job enters only when another leaves, the scheduler will hold new jobs in receiving whenever more than about 1,850 racks are already on the floor. At current throughput, that cap is what a seven-day lead time requires.

Daily bath control. A daily titration plotted on a control chart, backed by an automatic dosing pump, will hold the phosphate stage in specification, removing most adhesion failures and bringing total rework to about 3.5 percent.

Planned shipping. Customers will book pickups in a morning or afternoon window, and the dispatcher will build Copperline's own delivery runs each afternoon from the next day's expected completions, halving the time packed parts wait.

A second booth for dark colors, at about $185,000, is deferred until volume grows, and adding Saturday shifts is rejected because it treats the symptom.

What this page is doingTies each change to a cause.
7

Financial Case

Costs and benefits

ItemOne timeAnnual
Dosing pump, titration equipment and lab training$14,000
Color scheduling boards and booth lead training$24,000
Shipping schedule tool and labels for release control$12,000
Additional lab time for daily titrationminus $22,000
On-time bonus sharing one-third of overtime savingsminus $73,000
Lower Saturday overtime, $310,000 to about $90,000$220,000
Lower rework, 7.8% to about 3.5% of racks$226,000
Fewer credits and expedites$80,000
Total$50,000Net about $431,000

The one-time cost is repaid in under two months of net savings. The figures exclude the value of new business: with about 10 percent spare capacity on the conveyor line and reliable delivery, the shop could pursue work worth perhaps $1.5 million a year in sales, including the two customers lost last year.

What this page is doingShows that the plan pays.
8

Implementation

Fourteen-week implementation

WeeksStepOwner
1 to 3Daily titration, control chart and dosing pumpLab supervisor
2 to 5Booth leads design and pilot color grouping on first shiftLine 1 supervisor
6Sequencing on both shifts; expedite slot agreed with salesLine 1 supervisor, sales manager
6 to 14Release limit introduced at 2,600 racks and lowered in steps to 1,850Scheduler
8 to 10Pickup windows and truck route planningShipping supervisor
14Review of all measures and decision on second booth timingPlant manager

Bath control goes first because it is cheap and reduces the load on the constraint immediately. The release limit is introduced only after the constraint has spare capacity, and lowered in steps so the queue drains rather than moving to receiving.

What this page is doingSets the sequence and owners.
9

People and Change

Booth leads gain responsibility for sequencing and will design the color wheel themselves. The scheduler's role shifts from juggling a spreadsheet to managing a single release rule. Sales gives up unlimited rush promises in exchange for one guaranteed expedite slot a day and a seven-day promise it can keep. Operators lose most Saturday shifts, worth about $4,000 a year to a typical operator; the on-time bonus returns about a third of the savings to them, paid quarterly when on-time delivery meets target. The plan was reviewed with each group before this report.

What this page is doingExplains how the changes will be accepted.
10

Risks

Sequencing could delay a few urgent jobs; the expedite slot and a one-day grouping limit protect promises. A release limit set too low could starve the line; it starts high and falls in steps while the constraint is watched. The dosing pump could fail; daily titration remains the control. Sales may keep promising rush jobs outside the slot; the plant manager will review every exception weekly for the first three months.

What this page is doingPairs risks with responses.
11

Governance and Measures

Bititci et al. (2012) argue that performance measurement should support the conversations and decisions people actually have, not only report results. A 20-minute flow meeting at the start of each week, led by the plant manager with the line supervisors, scheduler, lab and shipping, will review the measures below, decide on any adjustments to the release limit and color rules and record problems for follow-up.

Measures

MeasureBaselineTwelve-month target
Days from arrival to shipping, average11.67
On-time delivery71%92%
Racks on the floor, daily average3,100Under 1,900
Color changes per day on the conveyor line2212 or fewer
Rework7.8% of racksUnder 3.5%
Days with bath out of specification6 of 15 in studyNone
Saturday overtimeAbout $310,000 a yearUnder $100,000
What this page is doingKeeps the changes in place.
12

Conclusion

Copperline does not need a new line to keep its seven-day promise. It needs to stop flooding its floor with work, stop wasting a quarter of its constraint's day on color changes and keep its washer in specification. Four inexpensive changes, introduced over 14 weeks and reviewed every week, should bring lead time to about seven days, on-time delivery to about 92 percent and savings of about $431,000 a year, while giving the shop room to win back the customers it lost.

What this page is doingCloses the plan.
13

References

Bititci, U., Garengo, P., Dörfler, V., & Nudurupati, S. (2012). Performance measurement: Challenges for tomorrow. International Journal of Management Reviews, 14(3), 305-327. https://doi.org/10.1111/j.1468-2370.2011.00318.x

Schmenner, R. W., & Swink, M. L. (1998). On theory in operations management. Journal of Operations Management, 17(1), 97-113. https://doi.org/10.1016/S0272-6963(98)00028-X

Spearman, M. L., Woodruff, D. L., & Hopp, W. J. (1990). CONWIP: A pull alternative to kanban. International Journal of Production Research, 28(5), 879-894. https://doi.org/10.1080/00207549008942761

What the QSO 489 Module 7 instructions ask for

The QSO 489 final project brings the capstone milestones together into one complete plan for improving an operation. Students are typically expected to include an executive summary, a profile of the organization and its strategy, the problem and goals, the analysis and its findings, the root causes, the recommended changes and their expected effects, the costs and benefits, an implementation plan with owners and timing, attention to the people affected, risks and responses, how the changes will be governed and sustained and the measures that will show success. Strong final projects read as one argument rather than stapled milestones, revise earlier work in light of feedback, tie every recommendation to a root cause, quantify costs and benefits, and leave the organization with a plan it could start on Monday.

How this QSO 489 Module 7 final project example is built

The final project presents the improvement plan for Copperline Finishing Company, a fictional powder coating job shop in Muncie, Indiana. The diagnosis shows that waiting accounts for about 11.4 of the 11.6 days of lead time and that the conveyor line runs about 21 racks a day short of demand. Four recommendations follow: color sequencing, a CONWIP limit of about 1,850 racks, daily bath control with a dosing pump and planned shipping. The financial case sets about $50,000 one time and about $95,000 a year in new costs, including a bonus sharing a third of overtime savings, against about $526,000 a year in savings. A 14-week implementation, risks, a weekly flow meeting and seven measures complete the plan. Schmenner and Swink, Spearman and colleagues and Bititci and colleagues support it.

Where the QSO 489 Module 7 rubric puts the points

Instructors grading the QSO 489 final project look for one coherent argument from problem to plan, an organization profile tied to strategy, analysis built on data with clear root causes, recommendations tied to those causes with estimated effects, a financial case with costs, benefits and payback, an implementation plan with owners and timing, attention to the people affected, risks with responses, governance for sustaining the changes and measures with baselines and targets. Projects that score highest show how the milestones were revised and leave a plan the organization could actually start. Credit drops when milestones are pasted together, recommendations float free of the analysis, benefits are unquantified, people are ignored or measures lack baselines. Tables, clarity and APA citations count too.

QSO 489 Module 7 help: the mistakes that cost points

Draft the executive summary after everything else, as a single page a manager could act on. Then tell one story: the organization and what it competes on, the problem in numbers, what the data showed, the few root causes, the changes that address them and what they will achieve. Revise the milestones using your instructor's feedback rather than copying them. Give the financial case in a table with one-time costs, yearly costs, yearly benefits and payback. Lay out the implementation in weeks with owners. Explain how the people affected were involved and what they gain. Add risks with responses, the routine that will keep the changes in place and measures with baselines and targets. A common mistake is a final project that reads like four separate papers; another is a plan with no owners.

Get QSO 489 Module 7 written to your instructions

Upload the QSO 489 final project guidelines and your milestones. A writer assembles the complete improvement plan: an executive summary, the organization and problem, the analysis and root causes, recommendations with expected results, the financial case, implementation, people and change, risks, governance and measures, revised from milestone feedback and supported by operations research. Your first QSO 489 project is free, written in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 489 papers and related BS Operations Management samples

QSO 489 Module 7 questions, answered

Where can I find a free QSO 489 Module 7 Final Project sample?

This page holds the complete QSO 489 Final Project: an operations improvement plan for an invented powder coating job shop.

What should an operations capstone final project include?

An executive summary, organization profile, problem and goals, analysis and root causes, recommendations with expected effects, costs and benefits, implementation, people, risks, governance and measures.

How should milestones be combined in a final project?

By revising each with feedback and rewriting them as one argument, so the analysis leads to the causes and the causes lead to the recommendations and plan.

What is a financial case in an improvement plan?

A summary of one-time and ongoing costs and expected benefits, with payback or return, showing that the recommendations are worth their cost.

How are operational improvements sustained?

Through routines such as regular performance reviews, clear ownership, measures visible to the people doing the work and standards that are updated as the process improves.