QSO 700 Module 9 Final Project Example

Reviewed by Portia Lambrick, MBA

This QSO 700 Module 9 Final Project sample is a capstone report that brings the problem, research, current-state analysis, solution selection and validation, implementation plan, expected results and limitations together into one recommendation for decision makers. SNHU QSO 700 (QSO-700) ends the MS Project Management program with this report. The organization is Harbor Pines Credit Union, an invented Michigan credit union losing dealer car loans to lenders that answer faster. The report tells one story from the gap to the plan, leads with what the credit union should do, keeps every figure consistent with the milestones and is candid about what the evidence cannot yet show.

CourseQSO 700 Project Management and Operations Capstone
ModuleModule 9
Paper typegraduate capstone report integrating problem, research, current-state analysis, solution selection and validation, implementation plan, expected results and limitations into one recommendation for decision makers
LengthAbout 1,210 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Project Management
UpdatedOctober 2026

Free sample paper for QSO 700 Module 9

1

A Faster, Fair Yes: Capstone Report on Indirect Auto Lending at Harbor Pines Credit Union

[Student Name]

Southern New Hampshire University

QSO 700: Project Management and Operations Capstone

Capstone Report

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingHarbor Pines Credit Union, its data, findings and plans in this QSO 700 capstone report are invented.
2

A Faster, Fair Yes: Capstone Report on Indirect Auto Lending at Harbor Pines Credit Union

Executive Summary

Harbor Pines Credit Union should redesign how it decides and funds indirect auto loans by expanding validated automated decision rules, separating simple from complex applications, staffing evenings and Saturdays from its current team, removing interruptions from underwriters' days and requiring complete applications from dealers. Today dealers wait about 3.8 business hours for a decision, and much longer for applications sent in the evening or on weekends, while competing lenders answer in minutes; only about 17 percent of applications become funded loans. Modeled on last year's arrivals, the redesign answers roughly seven applications in ten inside a quarter hour and lifts look-to-book toward 24 percent, adding roughly 2,400 funded loans and an estimated $900,000 a year in net income. It costs about $398,000 once and $62,000 a year. The new rules approved loans with lower delinquency than the portfolio in a two-year back-test and showed no disparities beyond policy in fairness testing. The main risk, rules that perform worse in practice, is controlled by a four-week shadow run before launch, waves of dealers and a rollback threshold.

What this page is doingLeads with the recommendation.
3

The Problem and Objectives

Indirect auto loans arrive from 214 dealers through an online portal while customers wait in showrooms, about 2,900 a month. Whichever lender says yes first, at a tolerable rate, usually gets the contract. Harbor Pines' slow answers cost it loans and strain its dealer relationships. The targets set in the proposal have not moved: seven decisions in ten inside a quarter hour, complete contracts paid by the next business day, look-to-book at 24 percent, serious delinquency held under three-quarters of a percent and no new fairness gaps.

What this page is doingRestates the gap.
4

What Research Suggested

The literature review produced six design rules. Waiting, not working, usually dominates flow time, so the target is waiting. Staffing must follow when work arrives, which for car dealers means evenings and Saturdays. Simple and complex cases should take different paths. Automated decisions can improve outcomes: Evidence from a used-car finance company that moved to scoring shows profits climbing as terms were fitted more closely to each borrower's risk (Einav et al., 2013), though any rule set still has to prove itself on local loans. Fairness must be tested, because Fuster et al. (2022) showed that better statistical prediction in credit can spread its benefits unevenly across racial and ethnic groups. And speed targets must be paired with quality measures so that workers under pressure do not cut corners.

What this page is doingSummarizes design rules.
5

Current State

Analysis of 34,800 applications showed that two applications in five land in the evening or on a weekend, when no underwriter works, and that only 12 percent are decided by the current automated rules. Manual applications receive about 31 minutes of work within an average of 3.8 business hours; the rest is waiting in a single queue and for dealers to supply missing information. The timestamps also satisfy the identity Little (1961) proved for queues: about 48 applications sit in the system on an average business hour, and Monday's weekend backlog takes until Tuesday afternoon to clear, because underwriters' effective capacity, after time spent on dealer calls and other duties, barely matches demand. Delay is expensive: answers inside half an hour convert at roughly four times the rate of answers that wait for the next business day. Funding takes 4.2 days, largely because nearly two contracts in five show up short of some required paper.

What this page is doingReports the evidence.
6

The Solution and Why It Was Chosen

Three alternatives were compared on speed, cost, loan quality, fairness, dealer and member experience and effects on staff. Hiring four evening underwriters would cover after-hours applications but leave daytime waiting largely unchanged. Outsourcing after-hours underwriting would do the same and worried staff. The combined redesign scored highest because it addresses every root cause found: narrow rules, no triage, no after-hours coverage, diluted underwriter time and incomplete applications. Its funding changes, a document checklist at approval and electronic upload, address the second delay.

What this page is doingExplains the selection.
7

Validation

Two underwriters and the credit union's risk analyst built the expanded rules and back-tested them on 24 months of applications with known results. Loans that the new rules and underwriters would both approve, about 41 percent of funded loans, had 60-day delinquency of about 0.41 percent, well under the portfolio's rate. Rules that would approve applications underwriters had declined were narrowed until such cases fell below 2 percent of approvals, because their outcomes cannot be observed. The compliance officer tested approval rates and pricing across groups using the proxy method regulators apply when demographic data are not collected and found no disparities beyond policy limits; the new rules slightly narrowed one existing approval gap.

What this page is doingTests the solution before recommending it.
8

Implementation

Implementation summary

ElementPlan
Duration30 weeks in seven phases
Key testFour-week shadow run, rules scoring silently beside underwriters
LaunchWaves of 40, 80 and the remaining dealers from week 17
One-time costabout $398,000
Annual costabout $62,000 plus a small shift differential
PeopleNo underwriter positions cut; volunteers for evening shift; underwriters lead shadow review and dealer training
RollbackOld rules kept in the engine; reversal if early delinquency exceeds 1.5 times the portfolio rate for two months or any fairness breach

Oreg et al. (2011), reviewing decades of research on how employees react to change, found that participation, communication and trust in management strongly shape reactions. The plan reflects what the underwriters said in Module 4: their concerns about jobs, rule quality and judgment led to the no-cuts commitment, their role in testing and the reservation of complex cases for people.

What this page is doingSummarizes the plan.
9

Expected Results and Measures

Expected results

MeasureCurrentExpected by week 30
Decisions within 15 minutesabout 9%about 72%
Complete contracts paid out by the next business dayabout 22%about 80%
Look-to-bookabout 17%about 24%
Added funded loans a yearabout 2,400
Added net income a yearabout $900,000
Loans 60 or more days late, new indirect book0.62%under 0.75%

The weekly dashboard tracks each measure against action thresholds, and fairness tests are repeated quarterly and reported to the loan committee.

What this page is doingTies outcomes to the dashboard.
10

Limitations

The back-test cannot observe outcomes for applications that were declined, so the rules were narrowed where that mattered. Twelve months of timestamps cover one interest rate environment. The estimate of added loans assumes dealers respond to faster answers as the current data suggest, which may partly reflect dealers sending their best deals to faster lenders. Twenty dealer interviews may not represent all 214. Each limitation is addressed by monitoring after launch rather than by assumption.

What this page is doingStates what the evidence cannot show.
11

Recommendations

The capstone recommends that the credit committee approve the expanded rules for a shadow run, that the board's loan committee fund the $398,000 implementation with quarterly fairness and delinquency reporting, that the vice president of lending sponsor the 30-week plan with the rollback thresholds above, and that the same approach, measure waiting before adding staff and validate any automation locally, be applied next to direct auto loans in branches.

What this page is doingStates what to do next.
12

Conclusion

Harbor Pines loses car loans because its answers wait while competitors' arrive. The evidence shows the time is spent waiting, not working, and that waiting costs funded loans. A redesign that automates validated decisions, triages the rest, staffs when dealers work and removes interruptions can answer most dealers in minutes, with loan quality and fairness tested before launch and watched after it.

What this page is doingCloses the report.
13

References

Einav, L., Jenkins, M., & Levin, J. (2013). The impact of credit scoring on consumer lending. The RAND Journal of Economics, 44(2), 249-274. https://doi.org/10.1111/1756-2171.12019

Fuster, A., Goldsmith-Pinkham, P., Ramadorai, T., & Walther, A. (2022). Predictably unequal? The effects of machine learning on credit markets. The Journal of Finance, 77(1), 5-47. https://doi.org/10.1111/jofi.13090

Little, J. D. C. (1961). A proof for the queuing formula: L = λW. Operations Research, 9(3), 383-387. https://doi.org/10.1287/opre.9.3.383

Oreg, S., Vakola, M., & Armenakis, A. (2011). Change recipients' reactions to organizational change: A 60-year review of quantitative studies. The Journal of Applied Behavioral Science, 47(4), 461-524. https://doi.org/10.1177/0021886310396550

What the QSO 700 Module 9 instructions ask for

The QSO 700 final project usually asks students to submit a complete capstone report that integrates the work of the course: the problem and its significance, a review of relevant research, analysis of the current state, the selected solution and its justification, the implementation plan, expected outcomes and measures, limitations and recommendations. Strong reports are written for the decision makers who will act on them, lead with the recommendation, reconcile numbers so that every figure matches across sections, show how evidence shaped each choice, state limitations plainly and incorporate feedback received on earlier milestones. Each section should carry the same argument forward instead of restarting it, and they make clear what the organization should do next.

How this QSO 700 Module 9 final project example is built

The report integrates the capstone at Harbor Pines Credit Union, a fictional Michigan credit union whose dealer car loan applications took about 3.8 business hours to decide while 17 percent became funded loans. It leads with the recommendation, then covers the problem and objectives, six design rules from research, current-state findings that files get about 31 minutes of work and hours of waiting and that look-to-book falls from 31 to 7 percent as decisions slow, why a combined redesign beat added staff and outsourcing, back-testing at about 0.41 percent delinquency, fairness results, the 30-week plan and an estimate of about 2,400 more funded loans and $900,000 a year in added net income. Little, Einav and colleagues, Fuster and colleagues and Oreg and colleagues are cited.

Where the QSO 700 Module 9 rubric puts the points

Marks on the QSO 700 capstone report typically go to a clear executive summary with the recommendation first, a problem and objectives consistent with the proposal, research integrated into design choices, a data-based current-state analysis, a justified and validated solution, a credible implementation plan, expected results tied to measures, honest limitations, recommendations, consistency of figures across sections and evidence that milestone feedback was used. Reports stand out when a decision maker could act on the executive summary alone and find support in every section. Points slip away when milestones are pasted in unrevised, when figures disagree from one section to the next, for recommendations not supported by the analysis or for missing limitations. Tables, APA references and professional writing complete the grade.

QSO 700 Module 9 help: the mistakes that cost points

Draft the summary after everything else and place it at the front: problem, recommendation, expected results, cost and the main risk, in under a page. Then build the report as one argument: why the problem matters, what research says, what your data showed, which solution you chose and why, how you tested it, how it will be implemented and how success will be measured. Check every number against your milestones and fix any that changed. Show where instructor or sponsor feedback changed the work. State limitations honestly and say what further evidence would settle them. End with specific recommendations. Reports often run each milestone in sequence; a strong report cuts what does not serve the argument.

Get QSO 700 Module 9 written to your instructions

Send the QSO 700 capstone report guidelines, your milestones and the instructor feedback you received. A writer integrates them into one report that leads with the recommendation, reconciles figures across sections, shows how research and data shaped the solution, summarizes the plan and states limitations, ready for your sponsor or committee. Your first QSO 700 report is drafted free, typically in two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 700 papers and related MS Project Management samples

QSO 700 Module 9 questions, answered

Where can I find a free QSO 700 Module 9 Final Project sample?

This page holds the full QSO 700 Module 9 capstone report for an invented credit union's dealer loan redesign.

What goes in a QSO 700 capstone report?

An executive summary, problem and objectives, research, current-state analysis, solution and validation, implementation plan, expected results, limitations and recommendations.

How long should an executive summary be?

Usually one page or less, stating the problem, the recommendation, expected results, cost and the main risks.

Can I reuse my milestone papers in the final capstone report?

Yes, but revise and integrate them, reconciling figures, applying feedback and cutting material that does not serve the final argument.

How should limitations be presented in a capstone report?

Plainly, with what each limitation affects and what further evidence or monitoring would address it.