MGT 630 Module 2 Rework Cost Analysis Assignment Example

Reviewed by Portia Lambrick, MBA

This MGT 630 Module 2 Rework Cost Analysis Assignment sample measures what rework cost on a completed building and where it came from. SNHU MGT 630 (MGT-630) asks MS in Management students early in the course to quantify quality failures before proposing any fix. Merrymeeting Builders, a composite Maine multifamily builder, reviews its rework log from an 84-unit apartment project. The paper sorts 212 logged items into five causes, totals direct and indirect costs, compares the results with published studies of rework on Australian and North American projects and uses a Pareto view to show which two causes a prevention plan should target first.

CourseMGT 630 Construction Quality Management and Productivity
ModuleModule 2
Paper typegraduate assignment quantifying the causes and costs of rework on a completed project
LengthAbout 1,020 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 630 Module 2

1

$684,000 in Doing It Twice: The Causes and Costs of Rework at Pejepscot Commons

[Student Name]

Southern New Hampshire University

MGT 630: Construction Quality Management and Productivity

Rework Cost Analysis Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingMerrymeeting Builders, Pejepscot Commons and the rework log are fictional; all figures are illustrative.
2

$684,000 in Doing It Twice: The Causes and Costs of Rework at Pejepscot Commons

Introduction

Merrymeeting Builders completed Pejepscot Commons, an 84-unit, four-story wood-frame apartment building over a concrete podium, in 2025 for a contract value of $27.4 million. The project finished on time, but its rework log grew to 212 items, including 41 leaking windows repaired after occupancy. Before planning quality management for its next project, the company needs to know what rework cost and where it came from. This paper sorts the log by cause, totals direct and indirect costs, compares the results with published research and recommends where prevention should begin.

What this page is doingStates the question and the data.
3

Data and Method

The log combines superintendent records, warranty callbacks and back-charges to subcontractors. Each item records what was redone, by whom and what it cost in labor, material and equipment. Two reviewers assigned each item to one of five causes using written rules: document errors and omissions, owner changes after work was in place, workmanship by Merrymeeting crews or subcontractors, supplier and fabrication errors and damage by following trades. They disagreed on 17 items, which were settled by the project manager. Costs absorbed by subcontractors without a back-charge are not in the log, so totals understate the true figure.

What this page is doingExplains how items were classified.
4

Results by Cause

Rework at Pejepscot Commons by cause

CauseItemsShare of itemsDirect costShare of cost
Workmanship (including 41 leaking windows)7434.9 percent$247,00036.1 percent
Document errors and omissions5827.4 percent$214,00031.3 percent
Owner changes after work in place3114.6 percent$142,00020.8 percent
Supplier and fabrication errors2712.7 percent$58,0008.5 percent
Damage by following trades2210.4 percent$23,0003.4 percent
Total212100 percent$684,000100 percent

Direct rework cost equals 2.5 percent of contract value. The window leaks alone, at $186,000, are 27 percent of the total, the largest single problem on the project.

What this page is doingPresents the core table.
5

Indirect Costs

Rework also extended the work. Repairs to windows and to two misdrawn stair openings held up drywall on the third and fourth floors, and the project manager estimates that three weeks of the schedule were consumed by rework that the early framing had otherwise saved. At about $38,000 a week in general conditions, that is roughly $114,000, bringing the total to about $798,000, or 2.9 percent of contract value. Lost productivity on other tasks while crews were pulled to repairs is not counted, so this remains a floor.

What this page is doingAdds what the log leaves out.
6

Comparison With Research

Love and Li (2000) quantified rework on two Australian projects procured under different arrangements and found it cost 3.15 and 2.40 percent of contract value, driven mainly by client and end-user changes and by errors and omissions in contract documents. Pejepscot's 2.5 percent direct figure sits within that range, but its leading cause differs: here workmanship comes first, largely because of one systematic failure. Hwang et al. (2009), drawing on 359 projects in the Construction Industry Institute database, reported that direct rework costs often reach about five percent of construction cost and that the effect differed by project characteristics. Love (2002), surveying 161 Australian projects, found that rework accounted for 52 percent of cost growth and did not differ significantly by project type or procurement method. Together these suggest Pejepscot's figure is typical, not exceptional, and that rework deserves management attention on every project rather than only troubled ones.

What this page is doingSets the figures against benchmarks.
7

Pareto View

Cumulative share of rework cost

RankCauseCumulative share
1Workmanship36.1 percent
2Document errors and omissions67.4 percent
3Owner changes after work in place88.2 percent
4Supplier and fabrication errors96.6 percent
5Damage by following trades100 percent

Two causes account for two-thirds of the cost. Workmanship ranks first by count and by cost, but most of its cost comes from a single repeated error: windows installed before sill flashing was in place. Document errors rank second; 23 of the 58 came from conflicts between architectural and structural drawings at stairs, shafts and podium transfer beams.

What this page is doingShows where most of the money went.
8

Root Causes Behind the Top Two

The window failure was a sequencing decision, not a skill problem. Framers installed windows to keep pace because no one had assigned the order of window, flashing and weather barrier work, and no mockup was built to test it. The document errors arose because the coordination review at ninety percent drawings covered only mechanical systems; structural and architectural sheets were never overlaid. Both causes are matters of planning that Merrymeeting controls.

What this page is doingGoes one level deeper.
9

What Prevention Would Be Worth

If the window failure had not happened and document conflicts at stairs, shafts and transfer beams had been caught in review, the log suggests that about $186,000 and $96,000 of direct rework, plus most of the three weeks of extended supervision, would have been avoided. That is roughly $390,000 on one project. A water-tested mockup for each window type costs perhaps $6,000 including the testing agency, and a two-day structural and architectural overlay review costs about $9,000 in staff and consultant time. Even if prevention removed only half of these failures, the return would be many times its cost. The comparison also explains why rework rarely gets attention: its cost is scattered across dozens of small entries, while the cost of prevention appears as one visible line in the budget.

What this page is doingPuts a value on fixing the top two.
10

Recommendations

First, for every exterior opening type, build and water-test a mockup before production, and write the installation sequence into the framing and weather barrier scopes so that one foreman owns it. Second, extend the drawing coordination review to structural and architectural overlays at stairs, shafts and transfer levels before releasing panels for fabrication. Third, start logging rework by cause on the next project from the first week, including costs subcontractors absorb, so that the analysis is not reconstructed after the fact.

What this page is doingTargets prevention where it pays.
11

Limitations

The log records repairs, not every hour of disruption they caused. Classification involved judgment on 17 items. Owner changes are counted as rework when they altered completed work, which some studies treat separately as scope change.

What this page is doingStates what the analysis cannot show.
12

Conclusion

Rework at Pejepscot Commons cost at least $798,000, close to three percent of contract value and well above the margin the company earned on the job. Two planning failures explain most of it, and both can be addressed before the next project's first panel arrives.

What this page is doingSummarizes the finding.
13

References

Hwang, B.-G., Thomas, S. R., Haas, C. T., & Caldas, C. H. (2009). Measuring the impact of rework on construction cost performance. Journal of Construction Engineering and Management, 135(3), 187-198. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:3(187)

Love, P. E. D. (2002). Influence of project type and procurement method on rework costs in building construction projects. Journal of Construction Engineering and Management, 128(1), 18-29. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:1(18)

Love, P. E. D., & Li, H. (2000). Quantifying the causes and costs of rework in construction. Construction Management and Economics, 18(4), 479-490. https://doi.org/10.1080/01446190050024897

What the MGT 630 Module 2 instructions ask for

The rework or cost-of-quality assignment in MGT 630 usually asks you to analyze quality failures on a project, identify their causes, estimate their costs and recommend where to focus improvement. You may be given a case or asked to use a project you know. A strong paper organizes failures into a small number of clear causes, totals both direct costs and the indirect costs of delay, compares the results with research benchmarks and uses a Pareto view to rank priorities. It is careful about what a rework log can and cannot show, since logs record repairs but rarely the root cause, and it turns the findings into two or three targeted actions instead of a long list.

How this MGT 630 Module 2 rework cost analysis assignment example is built

The sample analyzes the rework log from Pejepscot Commons, an 84-unit, four-story apartment building that Merrymeeting Builders finished in 2025 for $27.4 million. Its 212 items cost $684,000 directly, 2.5 percent of contract value. Workmanship, led by the 41 leaking windows, accounts for 36 percent; document errors and omissions for 31 percent; owner changes after work was in place for 21 percent; supplier errors and damage by following trades for the rest. About $114,000 in extended general conditions brings the total near 2.9 percent. The paper compares this with Love and Li's two case projects, Hwang and colleagues' 359-project study and Love's 161-project survey before recommending where prevention should start.

Where the MGT 630 Module 2 rubric puts the points

Rework analyses are commonly scored on the clarity of the cause categories, the accuracy of cost totals, the inclusion of indirect costs, the use of research benchmarks, the quality of recommendations and APA writing. The strongest papers present the data in a table that reconciles, rank causes by cost as well as count, explain why the two rankings differ and limit recommendations to the causes that matter most. Marks fall for lists of defects with no categories, for direct costs only, for benchmarks quoted without context about project type and for recommendations unconnected to the data. Instructors also credit a candid note on gaps in the log, such as costs absorbed by subcontractors and never recorded.

MGT 630 Module 2 help: the mistakes that cost points

Gather every rework record you can: punch lists, change orders marked as corrections, warranty callbacks and subcontractor back-charges. Assign each to one cause using clear rules, and note which ones are uncertain. Total costs by cause and by count; the two rankings often differ, and the difference is informative. Add the indirect costs, such as extra weeks of supervision and equipment, since those are often larger than they look. Compare with benchmarks from studies of similar projects, noting differences in project type. Then pick the two causes that account for most of the cost and propose specific prevention for each. Avoid recommending everything at once.

Get MGT 630 Module 2 written to your instructions

Send the MGT 630 Module 2 brief and any rework, punch or callback data you have. We sort the items by cause, total direct and indirect cost, compare the result with published benchmarks and show where prevention pays most. The first analysis is on us and usually lands within two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 630 papers and related MS in Management samples

MGT 630 Module 2 questions, answered

Where can I find a free MGT 630 Module 2 Rework Cost Analysis Assignment sample?

The full MGT 630 Module 2 rework analysis is on this page, sorting 212 items from an apartment project by cause and cost.

How do you calculate the cost of rework on a construction project?

Total the labor, material and equipment spent correcting work, add indirect costs such as extended supervision, and divide by contract value for comparison.

What are the main causes of rework in construction?

Studies most often point to design errors and omissions, client changes after work is in place, poor workmanship, supplier errors and damage by other trades.

How much does rework add to construction costs?

Reported figures vary by project and method; case studies of Australian buildings found around 2.4 to 3.2 percent of contract value, and broader studies report higher figures once indirect costs are included.

What is a Pareto analysis of rework?

Ranking rework causes by cost so that the few causes responsible for most of the money receive attention first.