MGT 630 Module 7 Cost Control Assignment Example

Reviewed by Portia Lambrick, MBA

This MGT 630 Module 7 Cost Control Assignment sample uses earned value to show where a construction package stands and where it is heading. SNHU MGT 630 (MGT-630) links productivity to cost control and scheduling in this part of its MS in Management course. Merrymeeting Builders, a composite Maine apartment builder, reviews its own framing and carpentry package at week 14 of 24. The paper computes cost and schedule variances and indexes, adds an earned schedule measure, forecasts final cost and finish date by three methods, traces the cost overrun to its causes and costs the corrective actions needed to recover.

CourseMGT 630 Construction Quality Management and Productivity
ModuleModule 7
Paper typegraduate assignment applying earned value to control cost and schedule on a construction package
LengthAbout 1,110 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 630 Module 7

1

CPI 0.92, SPI 0.89: Earned Value Control of the Framing Package at Cathance Landing

[Student Name]

Southern New Hampshire University

MGT 630: Construction Quality Management and Productivity

Cost Control Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingMerrymeeting Builders, Cathance Landing and all cost and schedule figures are fictional and illustrative.
2

CPI 0.92, SPI 0.89: Earned Value Control of the Framing Package at Cathance Landing

Introduction

Merrymeeting Builders self-performs framing, sheathing, blocking and rough carpentry at Cathance Landing, its current Topsham job. The package is budgeted at $2.96 million over 24 weeks, and with fourteen weeks gone, Merrymeeting's project manager wants two answers: is the package on track, and what will finishing it cost? The analysis below runs the package through earned value, adds an earned schedule measure, forecasts the final cost and duration, traces the variance to causes measured in the field and recommends corrective actions with their costs.

What this page is doingFrames the control question.
3

The Data

Planned value comes from the cost-loaded schedule set at the start of the package. Earned value is the budget of work actually completed, measured weekly by panels set, floors sheathed and blocking installed against the estimate's quantities. Actual cost comes from payroll, equipment rental and material invoices posted to the package. In the tables, PV, EV and AC stand for planned value, earned value and actual cost, BAC for the $2.96 million budget at completion and CPI and SPI for the cost and schedule performance indexes.

Cumulative values, weeks 10 to 14

WeekPlanned valueEarned valueActual cost
10$1,090,000$1,005,000$1,071,000
11$1,320,000$1,170,000$1,262,000
12$1,560,000$1,330,000$1,446,000
13$1,705,000$1,490,000$1,622,000
14$1,850,000$1,640,000$1,790,000
What this page is doingShows the inputs.
4

Performance at Week 14

Earned value measures at week 14

MeasureFormulaResultMeaning
Cost varianceEV less ACMinus $150,000The work done cost $150,000 more than budgeted
Schedule varianceEV less PVMinus $210,000$210,000 of planned work is not yet done
Cost performance indexEV over AC0.916Each dollar spent earns about 92 cents of budgeted work
Schedule performance indexEV over PV0.886Work is being completed at about 89 percent of the planned rate

Both indexes have worsened steadily since week 10, when the cost index was 0.938 and the schedule index 0.922, so the problem is not a single bad week.

What this page is doingComputes and interprets variances and indexes.
5

Earned Schedule

Anbari (2003) described how earned value integrates scope, cost and time and set out extensions that make the method easier to apply and read. One limitation of the dollar-based schedule index is that it drifts toward 1.0 as work nears completion, whatever the delay. Earned schedule avoids this by reading the planned curve backward: at what week did the plan expect today's earned value? Earned value of $1.64 million falls between the planned values of weeks 12 and 13, so earned schedule is 12 plus the fraction (1,640,000 minus 1,560,000) divided by (1,705,000 minus 1,560,000), or 12.55 weeks. The time-based index is 12.55 divided by 14, or 0.897, and at that rate the 24-week package would take about 26.8 weeks, finishing roughly 2.8 weeks late. Vandevoorde and Vanhoucke (2006) compared duration forecasting methods based on earned value and found that the earned schedule method gave the most reliable forecasts, which is why it is used here.

What this page is doingMeasures delay in time.
6

Forecasts at Completion

Cost forecasts at completion

MethodFormulaForecastOverrun
Budget rate for remaining workAC plus BAC less EV$3,110,000$150,000
Current cost efficiency continuesBAC over CPI$3,230,700$270,700
Cost and schedule pressure combinedAC plus (BAC less EV) over (CPI times SPI)$3,415,200$455,200

The first forecast assumes the problems stop today, which nothing in the data supports. The second assumes they continue at the current rate. The third assumes that schedule pressure will also add cost, through overtime or extra crews, and is the pessimistic case. Lipke et al. (2009) showed that statistical analysis of performance indexes can produce reliable forecasts of final cost and duration, and that forecasts made this way stabilize well before a project ends. With 14 weeks of steady decline, the second forecast, about $3.23 million, is the most defensible point estimate, with the third as the warning case. Holding the package to its $2.96 million budget would demand a cost index of 1.128 on everything left to build, far better than anything achieved so far, so the budget will not be met without changes.

What this page is doingGives a range of outcomes.
7

Causes of the Cost Variance

Sources of the $150,000 cost variance

CauseEvidenceCost to date
Lost productivity from late and unsequenced panel deliveries and windDaily records of disrupted days and lost hours$71,000
Overtime premium to recover lost daysPayroll records, weeks 9 to 14$38,000
Lumber and sheathing price increases above estimateSupplier invoices against quotes$27,000
Rework of two misframed stair openingsNonconformance log$14,000
Total$150,000

Nearly three quarters of the variance comes from disrupted work and the overtime used to recover it. The material increase is outside the crew's control but partly recoverable under the contract's escalation clause. The rework is small but traceable to a drawing conflict the overlay review missed at the stair cores.

What this page is doingTies the indexes to field data.
8

Corrective Actions

First, enforce the panel supplier's delivery window and sequence, with the back-charge clause, which the productivity analysis suggests would recover about half the disruption losses, roughly $40,000 over the remaining ten weeks. Second, stop open-ended overtime; it is buying back days at a premium while tired crews lose efficiency, and replace it with a targeted Saturday shift on two floors where work is ready. Third, file a claim under the escalation clause for about $19,000 of the lumber increase. Fourth, add the stair cores to the overlay review before the fourth-floor panels are released. Together these actions could bring the forecast close to $3.12 to $3.16 million and recover about one of the 2.8 weeks of delay.

What this page is doingPrices the recovery.
9

Reporting to the Owner and Leadership

The earned value figures will go to two audiences in different forms. Merrymeeting's leadership will see the full table each month, including the three forecasts, because they need to know the range of outcomes and the cash the overrun will consume. The owner's representative, whose contract is a fixed price, will see the schedule measures and the recovery plan, since the finish date affects the owner's leasing, while the cost overrun remains Merrymeeting's risk. The project manager will also add the earned value line to the weekly dashboard so that foremen see cost and schedule moving with the productivity and quality measures they already track, rather than meeting the numbers once a month in a report.

What this page is doingExplains how the numbers will be used.
10

Limitations

Earned value depends on how progress is measured; counting panels set gives no credit for partly braced walls, which slightly understates progress at the end of each week. The cost-loaded schedule front-loaded panel setting, which makes the schedule variance look worse during setting and better during blocking.

What this page is doingNotes the weak points.
11

Conclusion

At week 14 the framing package is about 8 percent over cost for work done and about 2.8 weeks behind. The causes are measurable and mostly fixable. With supply discipline replacing overtime, Merrymeeting can limit the overrun to roughly $160,000 to $200,000 rather than the $270,000 the current trend implies.

What this page is doingSummarizes the status.
12

References

Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403

Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009

Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), 289-302. https://doi.org/10.1016/j.ijproman.2005.10.004

What the MGT 630 Module 7 instructions ask for

The cost and schedule control assignment in MGT 630 usually asks you to evaluate a project's or package's performance using earned value or similar methods, interpret the results and recommend corrective actions. You will likely compute planned value, earned value and actual cost, the resulting variances and indexes and forecasts at completion. A strong paper explains what each number means for this specific work rather than only reporting formulas, uses more than one forecasting method and says why they differ, traces variances back to causes in the field and connects corrective actions to their own cost. Linking the variance to productivity data from earlier modules makes the analysis far more convincing than the indexes alone.

How this MGT 630 Module 7 cost control assignment example is built

The sample examines Merrymeeting's framing and carpentry package at Cathance Landing, budgeted at $2.96 million over 24 weeks. At week 14, planned value is $1.85 million, earned value $1.64 million and actual cost $1.79 million, giving a cost variance of minus $150,000, a cost index of 0.916 and a schedule index of 0.886. Earned schedule is 12.55 weeks, implying a finish about 2.8 weeks late. Forecasts at completion run from $3.23 to $3.42 million. The variance is traced to late deliveries and wind, overtime, lumber prices and rework. Anbari's account of the method, Vandevoorde and Vanhoucke's duration forecasting comparison and Lipke and colleagues' statistical forecasting frame the conclusions.

Where the MGT 630 Module 7 rubric puts the points

Cost and schedule control papers are typically scored on correct calculations, interpretation, forecasting, the analysis of causes, the quality of corrective actions and writing. The best papers show inputs and results in tables, interpret each index in plain terms, compare forecasting methods, connect variances to measured causes and price each corrective action against the overrun it addresses. Marks fall for arithmetic errors, for indexes reported without meaning, for a single forecast presented as certain, for causes that are guessed rather than measured and for corrective actions that would cost more than they save. A note on the weakness of the schedule index late in a project, and why earned schedule helps, shows command of the method.

MGT 630 Module 7 help: the mistakes that cost points

Collect three numbers for each reporting period: the budgeted cost of work planned to date, the budgeted cost of work actually done and what that work actually cost. Compute variances and indexes, and say in words what each means. Forecast cost at completion in at least two ways, one assuming current cost efficiency continues and one that also reflects schedule pressure, and explain the gap. Use earned schedule for timing, since the ordinary schedule index drifts toward one near the end. Then explain the variance with field evidence, such as productivity losses, prices or rework. Recommend actions with their costs, and compare each cost with the overrun it is meant to prevent.

Get MGT 630 Module 7 written to your instructions

Give us the MGT 630 Module 7 instructions and your planned, earned and actual cost figures. We compute the variances and indexes, add earned schedule, forecast cost and finish with more than one method, trace the variance to causes and price the recovery. The first control report is free and ready in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 630 papers and related MS in Management samples

MGT 630 Module 7 questions, answered

Where can I find a free MGT 630 Module 7 Cost Control Assignment sample?

This page holds a complete MGT 630 Module 7 earned value analysis of a framing package at week 14 of a 24-week plan.

What do CPI and SPI mean in earned value?

The cost performance index is earned value divided by actual cost, and the schedule performance index is earned value divided by planned value; below 1.0 means over budget or behind schedule.

What is earned schedule?

The point in time at which the planned value equals the earned value achieved so far, which gives a schedule measure in time units rather than dollars.

How do you forecast cost at completion with earned value?

Common methods divide the budget at completion by the cost index, or add actual cost to remaining work divided by the product of the cost and schedule indexes.

Why does the schedule performance index become unreliable late in a project?

Because earned value approaches planned value as work nears completion, the dollar-based index drifts toward 1.0 even when the project is late.