Free sample paper for MGT 630 Module 7
CPI 0.92, SPI 0.89: Earned Value Control of the Framing Package at Cathance Landing
[Student Name]
Southern New Hampshire University
MGT 630: Construction Quality Management and Productivity
Cost Control Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
CPI 0.92, SPI 0.89: Earned Value Control of the Framing Package at Cathance Landing
Introduction
Merrymeeting Builders self-performs framing, sheathing, blocking and rough carpentry at Cathance Landing, its current Topsham job. The package is budgeted at $2.96 million over 24 weeks, and with fourteen weeks gone, Merrymeeting's project manager wants two answers: is the package on track, and what will finishing it cost? The analysis below runs the package through earned value, adds an earned schedule measure, forecasts the final cost and duration, traces the variance to causes measured in the field and recommends corrective actions with their costs.
The Data
Planned value comes from the cost-loaded schedule set at the start of the package. Earned value is the budget of work actually completed, measured weekly by panels set, floors sheathed and blocking installed against the estimate's quantities. Actual cost comes from payroll, equipment rental and material invoices posted to the package. In the tables, PV, EV and AC stand for planned value, earned value and actual cost, BAC for the $2.96 million budget at completion and CPI and SPI for the cost and schedule performance indexes.
Cumulative values, weeks 10 to 14
| Week | Planned value | Earned value | Actual cost |
|---|---|---|---|
| 10 | $1,090,000 | $1,005,000 | $1,071,000 |
| 11 | $1,320,000 | $1,170,000 | $1,262,000 |
| 12 | $1,560,000 | $1,330,000 | $1,446,000 |
| 13 | $1,705,000 | $1,490,000 | $1,622,000 |
| 14 | $1,850,000 | $1,640,000 | $1,790,000 |
Performance at Week 14
Earned value measures at week 14
| Measure | Formula | Result | Meaning |
|---|---|---|---|
| Cost variance | EV less AC | Minus $150,000 | The work done cost $150,000 more than budgeted |
| Schedule variance | EV less PV | Minus $210,000 | $210,000 of planned work is not yet done |
| Cost performance index | EV over AC | 0.916 | Each dollar spent earns about 92 cents of budgeted work |
| Schedule performance index | EV over PV | 0.886 | Work is being completed at about 89 percent of the planned rate |
Both indexes have worsened steadily since week 10, when the cost index was 0.938 and the schedule index 0.922, so the problem is not a single bad week.
Earned Schedule
Anbari (2003) described how earned value integrates scope, cost and time and set out extensions that make the method easier to apply and read. One limitation of the dollar-based schedule index is that it drifts toward 1.0 as work nears completion, whatever the delay. Earned schedule avoids this by reading the planned curve backward: at what week did the plan expect today's earned value? Earned value of $1.64 million falls between the planned values of weeks 12 and 13, so earned schedule is 12 plus the fraction (1,640,000 minus 1,560,000) divided by (1,705,000 minus 1,560,000), or 12.55 weeks. The time-based index is 12.55 divided by 14, or 0.897, and at that rate the 24-week package would take about 26.8 weeks, finishing roughly 2.8 weeks late. Vandevoorde and Vanhoucke (2006) compared duration forecasting methods based on earned value and found that the earned schedule method gave the most reliable forecasts, which is why it is used here.
Forecasts at Completion
Cost forecasts at completion
| Method | Formula | Forecast | Overrun |
|---|---|---|---|
| Budget rate for remaining work | AC plus BAC less EV | $3,110,000 | $150,000 |
| Current cost efficiency continues | BAC over CPI | $3,230,700 | $270,700 |
| Cost and schedule pressure combined | AC plus (BAC less EV) over (CPI times SPI) | $3,415,200 | $455,200 |
The first forecast assumes the problems stop today, which nothing in the data supports. The second assumes they continue at the current rate. The third assumes that schedule pressure will also add cost, through overtime or extra crews, and is the pessimistic case. Lipke et al. (2009) showed that statistical analysis of performance indexes can produce reliable forecasts of final cost and duration, and that forecasts made this way stabilize well before a project ends. With 14 weeks of steady decline, the second forecast, about $3.23 million, is the most defensible point estimate, with the third as the warning case. Holding the package to its $2.96 million budget would demand a cost index of 1.128 on everything left to build, far better than anything achieved so far, so the budget will not be met without changes.
Causes of the Cost Variance
Sources of the $150,000 cost variance
| Cause | Evidence | Cost to date |
|---|---|---|
| Lost productivity from late and unsequenced panel deliveries and wind | Daily records of disrupted days and lost hours | $71,000 |
| Overtime premium to recover lost days | Payroll records, weeks 9 to 14 | $38,000 |
| Lumber and sheathing price increases above estimate | Supplier invoices against quotes | $27,000 |
| Rework of two misframed stair openings | Nonconformance log | $14,000 |
| Total | $150,000 |
Nearly three quarters of the variance comes from disrupted work and the overtime used to recover it. The material increase is outside the crew's control but partly recoverable under the contract's escalation clause. The rework is small but traceable to a drawing conflict the overlay review missed at the stair cores.
Corrective Actions
First, enforce the panel supplier's delivery window and sequence, with the back-charge clause, which the productivity analysis suggests would recover about half the disruption losses, roughly $40,000 over the remaining ten weeks. Second, stop open-ended overtime; it is buying back days at a premium while tired crews lose efficiency, and replace it with a targeted Saturday shift on two floors where work is ready. Third, file a claim under the escalation clause for about $19,000 of the lumber increase. Fourth, add the stair cores to the overlay review before the fourth-floor panels are released. Together these actions could bring the forecast close to $3.12 to $3.16 million and recover about one of the 2.8 weeks of delay.
Reporting to the Owner and Leadership
The earned value figures will go to two audiences in different forms. Merrymeeting's leadership will see the full table each month, including the three forecasts, because they need to know the range of outcomes and the cash the overrun will consume. The owner's representative, whose contract is a fixed price, will see the schedule measures and the recovery plan, since the finish date affects the owner's leasing, while the cost overrun remains Merrymeeting's risk. The project manager will also add the earned value line to the weekly dashboard so that foremen see cost and schedule moving with the productivity and quality measures they already track, rather than meeting the numbers once a month in a report.
Limitations
Earned value depends on how progress is measured; counting panels set gives no credit for partly braced walls, which slightly understates progress at the end of each week. The cost-loaded schedule front-loaded panel setting, which makes the schedule variance look worse during setting and better during blocking.
Conclusion
At week 14 the framing package is about 8 percent over cost for work done and about 2.8 weeks behind. The causes are measurable and mostly fixable. With supply discipline replacing overtime, Merrymeeting can limit the overrun to roughly $160,000 to $200,000 rather than the $270,000 the current trend implies.
References
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009
Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), 289-302. https://doi.org/10.1016/j.ijproman.2005.10.004
What the MGT 630 Module 7 instructions ask for
The cost and schedule control assignment in MGT 630 usually asks you to evaluate a project's or package's performance using earned value or similar methods, interpret the results and recommend corrective actions. You will likely compute planned value, earned value and actual cost, the resulting variances and indexes and forecasts at completion. A strong paper explains what each number means for this specific work rather than only reporting formulas, uses more than one forecasting method and says why they differ, traces variances back to causes in the field and connects corrective actions to their own cost. Linking the variance to productivity data from earlier modules makes the analysis far more convincing than the indexes alone.
How this MGT 630 Module 7 cost control assignment example is built
The sample examines Merrymeeting's framing and carpentry package at Cathance Landing, budgeted at $2.96 million over 24 weeks. At week 14, planned value is $1.85 million, earned value $1.64 million and actual cost $1.79 million, giving a cost variance of minus $150,000, a cost index of 0.916 and a schedule index of 0.886. Earned schedule is 12.55 weeks, implying a finish about 2.8 weeks late. Forecasts at completion run from $3.23 to $3.42 million. The variance is traced to late deliveries and wind, overtime, lumber prices and rework. Anbari's account of the method, Vandevoorde and Vanhoucke's duration forecasting comparison and Lipke and colleagues' statistical forecasting frame the conclusions.
Where the MGT 630 Module 7 rubric puts the points
Cost and schedule control papers are typically scored on correct calculations, interpretation, forecasting, the analysis of causes, the quality of corrective actions and writing. The best papers show inputs and results in tables, interpret each index in plain terms, compare forecasting methods, connect variances to measured causes and price each corrective action against the overrun it addresses. Marks fall for arithmetic errors, for indexes reported without meaning, for a single forecast presented as certain, for causes that are guessed rather than measured and for corrective actions that would cost more than they save. A note on the weakness of the schedule index late in a project, and why earned schedule helps, shows command of the method.
MGT 630 Module 7 help: the mistakes that cost points
Collect three numbers for each reporting period: the budgeted cost of work planned to date, the budgeted cost of work actually done and what that work actually cost. Compute variances and indexes, and say in words what each means. Forecast cost at completion in at least two ways, one assuming current cost efficiency continues and one that also reflects schedule pressure, and explain the gap. Use earned schedule for timing, since the ordinary schedule index drifts toward one near the end. Then explain the variance with field evidence, such as productivity losses, prices or rework. Recommend actions with their costs, and compare each cost with the overrun it is meant to prevent.
Get MGT 630 Module 7 written to your instructions
Give us the MGT 630 Module 7 instructions and your planned, earned and actual cost figures. We compute the variances and indexes, add earned schedule, forecast cost and finish with more than one method, trace the variance to causes and price the recovery. The first control report is free and ready in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More MGT 630 papers and related MS in Management samples
- MGT 630 Module 1 Discussion: Fast Framing, Leaking Windows
- MGT 630 Module 2 Rework Cost Analysis Assignment: What Rework Cost at Pejepscot Commons
- MGT 630 Module 3 Discussion: What Counts as Productivity on a Framing Crew
- MGT 630 Module 4 Productivity Analysis Assignment: Ten Weeks of Panel Setting Data
- MGT 630 Module 5 Milestone One: A Quality Management Plan for Cathance Landing
- MGT 630 Module 6 Discussion: Percent Plan Complete on the Framing Floors
- MGT 630 Module 8 Milestone Two: The Productivity and Equipment Plan
- MGT 630 Module 9 Discussion: Do Safe Sites Build Better Buildings
- MGT 630 Module 10 Final Project: The Integrated Quality and Productivity Report
- MBA 540 Module 8 Final Project Strategic Planning Proposal: Strategic proposal to enter Mexico
- SPT 501 Module 1 Discussion: What Makes a Question Researchable
- MKT 678 Module 5 Brand Architecture Assignment: Brand Architecture and an Acquired Brand
- MKT 665 Module 7 Discussion: Customers' Stories and Brand Communities
MGT 630 Module 7 questions, answered
Where can I find a free MGT 630 Module 7 Cost Control Assignment sample?
This page holds a complete MGT 630 Module 7 earned value analysis of a framing package at week 14 of a 24-week plan.
What do CPI and SPI mean in earned value?
The cost performance index is earned value divided by actual cost, and the schedule performance index is earned value divided by planned value; below 1.0 means over budget or behind schedule.
What is earned schedule?
The point in time at which the planned value equals the earned value achieved so far, which gives a schedule measure in time units rather than dollars.
How do you forecast cost at completion with earned value?
Common methods divide the budget at completion by the cost index, or add actual cost to remaining work divided by the product of the cost and schedule indexes.
Why does the schedule performance index become unreliable late in a project?
Because earned value approaches planned value as work nears completion, the dollar-based index drifts toward 1.0 even when the project is late.