Choosing 610 of 812: Scope Selection for the Meridian Isle Dry Dock
[Student Name]
Southern New Hampshire University
QSO 680: Seminar in Project Management
Scope Selection Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Choosing 610 of 812: Scope Selection for the Meridian Isle Dry Dock
Introduction
When Coral Lantern Cruises asked its departments what the Meridian Isle needs in its January dry dock, the requests totaled 812 jobs worth about $71 million. The budget is $52 million, of which $4.7 million is held as contingency for growth work, such as extra steel renewal found once the hull is measured, leaving about $47.3 million to allocate. The dock time is 18 days, and some work can only be done while the ship is out of the water. This paper explains how the jobs were screened, scored and selected, what happened to the jobs that did not make the list and how one large discretionary item was treated as an option.
The Approach
Archer and Ghasemzadeh (1999) proposed a staged framework for portfolio selection in which candidates are first screened against basic requirements, then analyzed individually, then selected together subject to resource limits and finally adjusted by managers' judgment. The dry-dock selection follows those stages. Cooper et al. (1999) surveyed companies about their portfolio practices and found that those relying mainly on financial models had among the weakest portfolios, while those using strategic criteria and scoring models did better; for that reason the scoring here combines revenue with safety, guest experience and fit with the fleet program.
Screening Mandatory Work
Of the 812 requests, 186 are mandatory: items required for the five-year renewal survey by the classification society, installation of the ballast water treatment system required before the ship's compliance date, lifeboat and davit load tests, fire safety system renewals and hull coating where the existing coating has failed. These cost $21.4 million and enter the scope without scoring, leaving about $25.9 million for 626 discretionary jobs whose requested cost totals about $49.6 million.
Scoring the Discretionary Work
The four division heads who own the outcomes, ship operations, hotel, pricing and money, settled the criteria and weights in one meeting.
Examples of scored jobs
| Criterion | Weight | What a high score means | |
|---|---|---|---|
| Safety and reliability | 30% | Reduces risk of failure, injury or off-hire | |
| Revenue | 25% | Adds or protects revenue, such as sellable cabins | |
| Guest experience | 20% | Visible improvement guests notice and rate | |
| Cost of deferral | 15% | Cost or risk rises sharply if postponed | |
| Fit with fleet program | 10% | Supports the common cabin design or fleet standards | |
| Job | Cost | Weighted score | In dock only? |
| Refit 214 balcony cabins to fleet design | $9.8 million | 4.1 | No |
| Overhaul port and starboard stabilizers | $1.4 million | 4.0 | Yes |
| Replace galley refrigeration plant | $1.9 million | 3.8 | No |
| Spa expansion into former shop space | $2.6 million | 3.1 | No |
| Atrium carpet and lighting | $0.7 million | 2.6 | No |
| New exterior signage | $0.3 million | 1.8 | No |
Each requesting department gave its own jobs between one and five points under each heading, and those ratings were then reviewed by the project manager and a marine superintendent to keep scores consistent.
Selecting Within the Limits
Selection followed two limits. The first is money: about $25.9 million for discretionary work. The second is dock time: jobs that can only be done in dock, such as stabilizers and underwater fittings, must fit within 18 days alongside mandatory work, while hotel jobs can, in principle, be done by riding crews during later voyages. Jobs were added in order of score per dollar, with dock-only jobs considered first because their opportunity disappears when the ship floats. When a job would exceed either limit, the next job that fit was taken.
The result is about 610 jobs in the dry-dock scope: all 186 mandatory jobs and about 424 discretionary ones. Seventy-four hotel jobs that scored well but did not fit the dock schedule, such as carpet and some public-room lighting, were moved to riding crews who will work during the next three voyages at lower intensity. One hundred twenty-eight jobs were deferred to the next dry dock, including exterior signage and several low-scoring cosmetic items.
Sensitivity
The selection is stable under moderate changes. Raising the revenue weight to 35 percent and lowering safety to 20 percent moves six jobs in and six out, all near the cutoff, and does not change any job costing more than $500,000. Raising safety to 40 percent adds two reliability jobs and moves the atrium carpet to the riding crew list.
The Spa as an Option
The spa expansion scores in the middle at 3.1 and would fit the budget only by displacing several higher-scoring jobs. Revenue management believes it could earn about $700,000 a year, but that estimate depends on whether guests on the newly refit ship book spa treatments at higher rates, which is unknown. Because the spa can be built by riding crews at sea or in the next dry dock, deciding now gives up the chance to learn. Huchzermeier and Loch (2001) analyzed the value of managerial flexibility in projects and showed that it depends on the kind of uncertainty involved, so that more uncertainty does not always make an option more valuable. Here the uncertainty, spa demand on this ship, can be resolved by six months of bookings data at little cost, which makes waiting attractive: if demand is strong, the spa can be built at sea next autumn for about 8 percent more than in dock; if weak, the $2.6 million is saved. The board approved holding the spa as an option and reviewing it in July.
Communicating the Result
Each department received its own list showing every job it requested and where it landed: in the dry dock, moved to riding crews, deferred or held as an option, with its score and the reason. That transparency matters for the next dry dock, because departments that see their requests judged by a consistent method are more likely to score honestly next time instead of inflating every request to the top. The hotel operations team accepted the riding crew plan once it saw that the moved jobs kept their place in a dated schedule rather than disappearing. Two departments appealed individual scores, and one appeal, for a galley ventilation fan that the marine team had underscored on safety, succeeded and moved the job into the dock scope in place of a lower-scoring cosmetic item.
Conclusion
The Meridian Isle's dry-dock scope was built in stages: 186 mandatory jobs first, then about 424 discretionary jobs chosen by a weighted score within the money and dock-time limits. Seventy-four jobs move to riding crews at sea, 128 wait for the next dry dock, and the spa expansion is kept as an option rather than a commitment. The result fits $47.3 million and 18 days, and the departments can see why each of their requests landed where it did.
References
Archer, N. P., & Ghasemzadeh, F. (1999). An integrated framework for project portfolio selection. International Journal of Project Management, 17(4), 207-216. https://doi.org/10.1016/S0263-7863(98)00032-5
Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (1999). New product portfolio management: Practices and performance. Journal of Product Innovation Management, 16(4), 333-351. https://doi.org/10.1111/1540-5885.1640333
Huchzermeier, A., & Loch, C. H. (2001). Project management under risk: Using the real options approach to evaluate flexibility in R&D. Management Science, 47(1), 85-101. https://doi.org/10.1287/mnsc.47.1.85.10661
What the QSO 680 Module 3 instructions ask for
The Module 3 assignment in QSO 680 generally asks students to apply project selection or portfolio methods, either to choose among projects or to decide what a complex project should include. Expect to explain selection criteria, build a scoring or financial model, account for constraints such as budget, capacity and time, and recommend a selection. Strong papers separate mandatory items from discretionary ones before scoring, set weights with the stakeholders who own the outcomes, use more than one criterion so that financial measures do not crowd out safety or strategy, select within real constraints rather than ranking alone, check how sensitive the choice is to the weights and recognize options, such as deferring or doing work another way, that keep value without spending now.
How this QSO 680 Module 3 scope selection assignment example is built
The assignment selects work for the Meridian Isle's 18-day dry dock at Coral Lantern Cruises, a fictional Miami line, from 812 requested jobs worth about $71 million against a $52 million budget with $4.7 million in contingency. It screens out 186 mandatory jobs costing $21.4 million, scores the other 626 on safety and reliability, revenue, guest experience, cost of deferral and program fit, then selects within the budget and the limit of jobs only possible in dock. About 610 jobs remain, 74 hotel jobs move to riding crews at sea and 128 are deferred. The option to defer a $2.6 million spa expansion is valued. Cooper and colleagues, Archer and Ghasemzadeh and Huchzermeier and Loch are cited.
Where the QSO 680 Module 3 rubric puts the points
The QSO 680 selection rubric usually credits a clear separation of mandatory and discretionary work, criteria and weights with a stated source, a scoring or financial method applied consistently, selection within explicit constraints, a sensitivity check, attention to alternatives such as deferral or different execution, and research on portfolio and selection methods. Papers stand out when the constraints, not just the scores, shape the result. They lose marks for ranking items without any limit, for relying on a single financial measure, for weights with no basis or for treating deferred work as rejected. A selection table a department head could follow, plus correct APA entries, takes the last points.
QSO 680 Module 3 help: the mistakes that cost points
List every candidate and mark which ones are mandatory, by law, safety, contract or regulator; those go in first. For the rest, choose four to six criteria with the people who own the results, weight them and score each item. Then apply the real constraints, such as budget, time, crews or space, and select the best-scoring set that fits, not just the top of the list. Change the weights and see if the selection holds. Look for items that keep their value if done later or another way and treat those as options rather than losses. Report what was selected, what was moved and what was declined. Papers often rank and stop; selection only happens when the ranking meets a limit.
Get QSO 680 Module 3 written to your instructions
Share the QSO 680 Module 3 instructions and your list of candidate projects or work items. A writer screens out mandatory items, builds a weighted scoring model with the people affected, selects within budget and capacity limits, tests how the result changes with the weights, values the option to defer and draws on portfolio research. A first QSO 680 assignment costs nothing and is normally back within two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 680 papers and related MS Project Management samples
- QSO 680 Module 1 Discussion: Why a Dry Dock Is Complex
- QSO 680 Module 2 Program Assignment: Three Ships, One Fleet Program
- QSO 680 Module 4 Discussion: A One-in-Three Chance of 18 Days
- QSO 680 Module 5 Resource Scheduling Assignment: Leveling Welders and Cranes
- QSO 680 Module 6 Critical Chain Assignment: Buffers Instead of Padding
- BMB 655 Module 10 Final Project: A Three-Year Financial Plan
- OL 635 Module 9 Final Project: Consulting Report
- ACC 693 Module 2 Data Analytics Assignment: Testing Three Years of Payables
- BMB 670 Module 3 Milestone One: A Founder Hands Over the Keys
QSO 680 Module 3 questions, answered
Where can I find a free QSO 680 Module 3 scope selection sample?
The complete QSO 680 Module 3 assignment is on this page: choosing 610 of 812 jobs for an invented cruise ship's dry dock.
What is project portfolio selection?
Choosing which projects or work items to fund from a larger set, using criteria such as value, risk and strategic fit within limits on resources.
What is a weighted scoring model?
A method that scores each option on several criteria, multiplies each score by the criterion's weight and adds the results to compare options.
Why separate mandatory items before scoring?
Because legally or contractually required work must be done regardless of score, and mixing it with discretionary work distorts the ranking.
What is the option value of deferring a project?
The value of waiting to decide until more information is available, which can exceed the cost of delay when the outcome is uncertain.