Two Hundred Thirty Welders on Day Five: Leveling the Meridian Isle Dry Dock
[Student Name]
Southern New Hampshire University
QSO 680: Seminar in Project Management
Resource Scheduling Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Two Hundred Thirty Welders on Day Five: Leveling the Meridian Isle Dry Dock
Introduction
The Meridian Isle's dry-dock schedule was built in project software from the scope selected in Module 3, with logical links and durations for about 610 jobs rolled into about 90 summary activities. It shows undocking on day 18. But the schedule was built on time alone. When welders, dock cranes and blasting crews were assigned to the activities, the resource profiles showed demand far above what the shipyard can supply. This paper identifies the overallocations, levels the schedule, reports the effect on duration and changes the plan so the leveled schedule still undocks on day 18.
Resources and Limits
Key resources and limits
| Resource | Available | Notes |
|---|---|---|
| Welders, day shift | 140 | Shipyard's allocation to Meridian Isle |
| Welders, night shift | 0 in base plan | Subcontractor can supply up to 70 at a premium |
| Dock cranes | 2 | About 22 lifts each per day shift, shared by all trades |
| Hull blasting crews | 3 | Day shift only in base plan |
| Cabin contractor crews | 36 | Riding crew, not limited by yard |
Overallocations
Welder demand in the time-only schedule, day shift
| Day | Steel renewal | Ballast water piping | Pod foundations and other | Total demand | Available |
|---|---|---|---|---|---|
| 3 | 40 | 60 | 30 | 130 | 140 |
| 4 | 70 | 90 | 40 | 200 | 140 |
| 5 | 90 | 100 | 40 | 230 | 140 |
| 6 | 90 | 100 | 30 | 220 | 140 |
| 7 | 70 | 90 | 30 | 190 | 140 |
| 8 | 40 | 60 | 20 | 120 | 140 |
Welder demand exceeds supply on days 4 to 7, peaking at 230 on day 5. Crane demand shows a similar peak: on days 3 to 6 the plan calls for about 58 lifts a day against about 44 available, because steel plates, piping spools, pod parts and cabin materials all arrive at once. Blasting crews are within limits but sit on the critical hull path.
Leveling
Leveling delays activities until resources are free. The order in which competing activities get resources is set by a priority rule. Davis and Patterson (1975) compared eight heuristic rules with optimal solutions on a set of test problems and found that rules that serve the tightest-floated jobs first came out ahead on average, producing schedules only a little longer than optimal. Kolisch (1996) compared the two basic ways of building such schedules, adding activities one at a time in priority order or scheduling everything that can start at each point in time, and found that neither approach dominated across all problems.
Two rules were tried in the software. Minimum slack first, which delays activities with the most float, pushed undocking to day 19.5, because ballast water piping and steel renewal are both near-critical and compete for the same welders. Latest finish first gave day 19.8. The software also split several activities into fragments and delayed some cabin material lifts into night hours the yard does not staff, so its result was reviewed by hand with the shipyard's planner, who confirmed day 19.5 as realistic for the plan as built.
Changing the Plan
Leveling showed that the plan, not just the dates, had to change. Three changes target the constraints directly.
First, prefabrication. About 3,800 welding hours of ballast water piping can be built ashore as spools in the yard's fabrication shop during the four weeks before the ship arrives, then lifted aboard and joined. This removes most of the piping welders from days 4 to 7, though it adds crane lifts, so spools will be lifted at night when no other trade needs the cranes.
Second, a night shift. A subcontractor will supply 70 welders on nights from day 3 to day 9 for steel renewal, which, unlike piping, can proceed under lights without disturbing other trades. Because steel renewal quantities depend on hull gauging on day 2, the subcontract is priced per hour with a minimum of 40 welders.
Third, crane relief. Cabin materials, about a third of the planned lifts on days 3 to 6, will be loaded through a shell door on deck 4 using the yard's forklift and a temporary ramp, freeing crane time for steel and pod parts. Crane lifts are booked in one-hour slots by a coordinator at the dock.
Welder demand after the plan changes
| Day | Day shift demand | Day shift available | Night shift demand | Night shift available |
|---|---|---|---|---|
| 3 | 118 | 140 | 40 | 70 |
| 4 | 134 | 140 | 66 | 70 |
| 5 | 138 | 140 | 66 | 70 |
| 6 | 136 | 140 | 60 | 70 |
| 7 | 128 | 140 | 50 | 70 |
| 8 | 112 | 140 | 30 | 70 |
Effect on Duration and Critical Path
With the changes, the leveled schedule undocks on day 18, with crane demand within about 40 lifts a day. The critical path now runs through hull blasting, coating, the pod overhaul's reassembly and undocking. Leveling created resource links that do not appear in the logic: steel renewal on nights now determines when the coating crews can start on the lower hull, so a night-shift shortfall becomes a critical delay. Hegazy (1999) argues for treating resource allocation and leveling together rather than in separate steps, since fixing one can disturb the other; here the night shift solved the allocation problem but created a new dependency that the project manager will watch daily.
Confirming the Plan With the Shipyard
A leveled schedule is only credible if the people who supply the resources agree to it. The revised plan was reviewed line by line with the shipyard's planning manager, its welding superintendent and the night-shift subcontractor before it became the baseline. The review changed two things. The yard asked that spool lifts finish by 5 a.m. so that the cranes are inspected before the day shift, which moved four lifts to the evening before. The subcontractor asked for 48 hours' notice to raise its crew above 40, which ties its staffing to the hull gauging results on day 2, so the project manager will send that notice on the evening of day 2 whatever the gauging shows. Both changes were entered in the software and the schedule releveled; undocking stayed on day 18. The yard's planner now owns the daily crane booking sheet, and any day on which welder demand exceeds 135 is flagged at the evening coordination meeting.
Cost and Value
Cost of plan changes
| Change | Cost | Days recovered |
|---|---|---|
| Prefabricated ballast water spools | $180,000 extra shop labor and handling | about 0.8 |
| Night welders, days 3 to 9 | $370,000 | about 0.5 |
| Shell door loading and crane coordinator | $60,000 | about 0.2 |
| Total | $610,000 | about 1.5 |
Against the $1.6 million cost of each day late, the $610,000 is easily justified.
Conclusion
The Meridian Isle's time-only schedule assumed 230 welders where 140 exist. Leveling with a minimum-slack rule moved undocking to day 19.5. Prefabrication, a night shift and relief for the cranes bring the leveled schedule back to day 18 for about $610,000, while creating a new dependency on night steel work that must be managed daily.
References
Davis, E. W., & Patterson, J. H. (1975). A comparison of heuristic and optimum solutions in resource-constrained project scheduling. Management Science, 21(8), 944-955. https://doi.org/10.1287/mnsc.21.8.944
Hegazy, T. (1999). Optimization of resource allocation and leveling using genetic algorithms. Journal of Construction Engineering and Management, 125(3), 167-175. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(167)
Kolisch, R. (1996). Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research, 90(2), 320-333. https://doi.org/10.1016/0377-2217(95)00357-6
What the QSO 680 Module 5 instructions ask for
The QSO 680 Module 5 assignment usually asks students to analyze and level resources in a project schedule, often using project management software. Expect to assign resources to activities, produce resource histograms, identify overallocations, apply leveling, explain the priority rules used and report how leveling changes the project's duration and critical path. Strong papers recognize that a schedule built on time alone is a wish until resources are checked, compare at least two priority rules, review what the software did rather than accepting it, and, if leveling pushes the finish past a fixed date, change the plan with options such as shifts, subcontracting, prefabrication or resequencing, costed against the value of the time saved. They also note that leveling can create a new critical path made of resource links rather than logic.
How this QSO 680 Module 5 resource scheduling assignment example is built
The assignment levels resources for the Meridian Isle's 18-day dry dock at Coral Lantern Cruises, a fictional Miami line. The time-only schedule asks for up to 230 welders on days 4 to 7 against 140 per day shift, and more crane lifts than two cranes can make. Software leveling with a minimum-slack rule pushes undocking to day 19.5. The plan changes instead of the date: prefabricated piping spools remove about 3,800 welding hours, a night shift of 70 welders takes steel renewal and cabin materials load through a shell door. The leveled schedule meets day 18 with peaks of 138 welders by day and 66 by night, for about $610,000. Davis and Patterson, Kolisch and Hegazy are cited.
Where the QSO 680 Module 5 rubric puts the points
Grading in the QSO 680 resource assignment generally credits accurate resource assignments and histograms, clearly identified overallocations, leveling done with stated priority rules and reviewed by hand, the effect on duration and critical path reported, plan changes that address the constraint with costs and benefits, and research on resource-constrained scheduling. Papers stand out when the leveled schedule is credible to the people who supply the resources. They lose points for schedules that ignore resource limits, for accepting software leveling without review, for reporting a later date without trying to recover it or for recovery options with no cost. Histograms or tables, APA references and clear writing finish the grade.
QSO 680 Module 5 help: the mistakes that cost points
Assign your main resources to activities and print a histogram for each scarce one: people by skill, equipment, space. Mark where the demand exceeds what is available. Level with a rule, such as serving the jobs with the least float first, and see how far the finish moves; try a second rule and compare. Review what the software did, since it may split tasks or delay critical work oddly. If the leveled finish is too late, change the plan: add a shift, buy outside capacity, move work out of the constrained area or resequence. Price every fix and set it beside what a recovered day is worth to the owner. Papers often level and report a new date; good papers treat the new date as a problem to solve.
Get QSO 680 Module 5 written to your instructions
Share the QSO 680 Module 5 instructions and your schedule or software file. A writer builds resource profiles, identifies overallocations, levels them with priority rules and project software, reports the effect on duration, proposes plan changes such as shifts, prefabrication or resequencing and costs them, with support from scheduling research. Your first QSO 680 assignment costs nothing and is typically delivered in two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 680 papers and related MS Project Management samples
- QSO 680 Module 1 Discussion: Why a Dry Dock Is Complex
- QSO 680 Module 2 Program Assignment: Three Ships, One Fleet Program
- QSO 680 Module 3 Scope Selection Assignment: Choosing 610 of 812 Jobs
- QSO 680 Module 4 Discussion: A One-in-Three Chance of 18 Days
- QSO 680 Module 6 Critical Chain Assignment: Buffers Instead of Padding
- QSO 680 Module 7 Discussion: Two Ships, One Superintendent
- QSO 680 Module 8 Quantitative Risk Assignment: Steel, Paint and a Decision Tree
- QSO 680 Module 9 Final Project: The Advanced Project Plan
- QSO 680 Module 10 Discussion: What the Tools Were Worth
- ACC 691 Module 1 Discussion: Why Executives Misstate Results
- SPT 565 Module 8 International Event Assignment: Hosting a Liga MX Friendly
- MGT 701 Module 10 Final Project: Critical Issue Capstone Report
- ACC 646 Module 3 Milestone One: Predication and a Plan for the Hauling Vendor
QSO 680 Module 5 questions, answered
Where can I find a free QSO 680 Module 5 resource leveling sample?
The full QSO 680 Module 5 assignment is on this page: leveling welders and cranes in an invented cruise ship's dry dock.
What is resource leveling?
Adjusting a schedule so that demand for each resource stays within what is available, usually by delaying activities that have slack.
What is a resource-constrained schedule?
A schedule that respects limits on people, equipment or space as well as the logical order of activities.
Which priority rule works best for resource leveling?
Studies often find rules based on slack or latest finish times perform well, but no single rule is best for every project.
Why can leveling change the critical path?
Because delaying activities for resources creates new links between activities that share a resource, which can become critical.