Module Ten Discussion
Day 17.6, and What Earned Its Keep
The Meridian Isle undocked at 2:40 p.m. on day 17, about 17.6 days after arrival and inside our 18-day commitment. We used 72 percent of the project buffer. Hull gauging found 96 tonnes of steel to renew against 70 expected, which used much of the contingency; total spending was about $50.9 million against the $52 million budget. The first sailing left Miami on time, and the factory-tested ballast water skid commissioned on day 15 without a delay.
I judge each method by one question: did it change a decision? Simulation did, more than anything else. The one-in-three chance it showed in October led directly to prefabricated piping and a night welding shift, without which the extra steel would probably have cost us a day. Leveling did too, by exposing that the original plan needed 230 welders on day 5. The decision tree ended a three-week argument about the ballast water system in one meeting. Besner and Hobbs (2006) surveyed project practitioners and found that tools differ widely in how much value people see in them and that some less-used tools had high potential if adopted more widely; simulation was such a tool for us.
Critical chain worked only partly. The buffer and fever chart gave early warning on day 3, when steel renewal ran into the yellow zone, but foremen still moved welders between jobs when a supervisor asked, and the rule against judging individual activities was not believed by everyone. Earned value added little on a dry dock of parallel paths; buffer tracking told us more each shift. White and Fortune (2002) surveyed practitioners and found that a handful of tools, such as bar charts and critical path software, dominated actual use, and that many reported drawbacks with the tools they used. Zwikael (2009) found that the knowledge areas carry very unequal weight during planning; our experience suggests that resources and risk deserved more weight than they usually get.
For the Palmetto Star, I will run the simulation earlier, keep leveling and decision trees, keep buffers but invest more in the floor rules and drop weekly earned value in favor of buffer tracking for the schedule.
Which method from this course would you actually use again, and what would stop you?
References
Besner, C., & Hobbs, B. (2006). The perceived value and potential contribution of project management practices to project success. Project Management Journal, 37(3), 37-48. https://doi.org/10.1177/875697280603700305
White, D., & Fortune, J. (2002). Current practice in project management: An empirical study. International Journal of Project Management, 20(1), 1-11. https://doi.org/10.1016/S0263-7863(00)00029-6
Zwikael, O. (2009). The relative importance of the PMBOK Guide's nine knowledge areas during project planning. Project Management Journal, 40(4), 94-103. https://doi.org/10.1002/pmj.20116
What the QSO 680 Module 10 instructions ask for
QSO 680's closing thread has students take stock of the advanced methods covered in the course and how they apply to the student's work. Expect to evaluate which tools and techniques would help most on complex projects, which are hard to apply in practice and what barriers stand in the way, sometimes with reference to a project of your own. Strong posts judge methods by results, by whether they changed a decision or prevented a problem, rather than by how sophisticated they sound. They are honest about methods that did not work as intended and explain why, often because behavior or data did not cooperate. They also connect personal experience to research on what practitioners actually use and value. Replies should ask which method a classmate would genuinely use again and what would stop them.
How this QSO 680 Module 10 discussion example is built
The post reports that the Meridian Isle's dry dock at Coral Lantern Cruises, a fictional Miami line, undocked on day 17.6 with 72 percent of its buffer used, 96 tonnes of steel against 70 expected and spending of about $50.9 million against $52 million. Simulation is judged most valuable for changing the plan before arrival, leveling for exposing the welder shortage and the decision tree for settling the ballast water argument. Critical chain's floor rules were only partly followed, and earned value added little on parallel paths. The writer links this to research on which tools practitioners value and use and says what to keep for the next ship. Besner and Hobbs, White and Fortune and Zwikael are cited.
Where the QSO 680 Module 10 rubric puts the points
Credit in the final QSO 680 thread typically goes to an honest account of results, a method-by-method judgment based on decisions changed or problems prevented, candid treatment of methods that underperformed with reasons, connections to research on practitioner use of tools and a concrete statement of what will be kept or changed. Posts do well when the reflection would help a classmate choose tools. They lose credit for praising every method equally, for describing tools rather than evaluating them, for reflections with no project behind them or for skipping the research. Replies that ask what would stop a classmate from using a method again earn the most. APA citations finish the grade.
QSO 680 Module 10 help: the mistakes that cost points
Choose a project you know, finished or under way. List the methods you used or could have used, and for each ask one question: did it change a decision or prevent a problem? Be specific about when and how. Be just as specific about methods that did not help and why: bad data, people who would not change habits, a tool that did not fit the project's structure. Then compare your experience with research on which tools practitioners value and use. Finish with what you will do differently on the next project. Posts often list course topics with a sentence of praise each; a useful reflection ranks the methods and explains the ranking.
Get QSO 680 Module 10 written to your instructions
Paste the QSO 680 Module 10 prompt and describe a project and the methods you used. A writer judges each method by whether it changed a decision, explains what worked and what did not and why, connects the reflection to research on how practitioners value project tools and states what you would keep next time, then asks the class something worth answering. No charge applies to the first QSO 680 post, typically ready in two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 680 papers and related MS Project Management samples
- QSO 680 Module 1 Discussion: Why a Dry Dock Is Complex
- QSO 680 Module 2 Program Assignment: Three Ships, One Fleet Program
- QSO 680 Module 3 Scope Selection Assignment: Choosing 610 of 812 Jobs
- QSO 680 Module 4 Discussion: A One-in-Three Chance of 18 Days
- QSO 680 Module 5 Resource Scheduling Assignment: Leveling Welders and Cranes
- QSO 680 Module 6 Critical Chain Assignment: Buffers Instead of Padding
- QSO 680 Module 7 Discussion: Two Ships, One Superintendent
- QSO 680 Module 8 Quantitative Risk Assignment: Steel, Paint and a Decision Tree
- QSO 680 Module 9 Final Project: The Advanced Project Plan
- OL 665 Module 2 Discussion: Judging Nonprofit Effectiveness
- MGT 605 Module 8 Milestone Two: The Definitive Estimate and Bid Strategy
- MKT 635 Module 4 Discussion: Ad Position and Bidding in Paid Search
- OL 663 Module 1 Discussion: Why Change Efforts Stall
QSO 680 Module 10 questions, answered
Where can I find a free QSO 680 Module 10 Discussion sample?
The complete QSO 680 Module 10 post is on this page: an invented cruise ship dry dock and which advanced tools earned their keep.
Which advanced project management tools are most useful?
It depends on the project's structure, but tools that change decisions early, such as simulation and resource leveling, often add the most value.
Why do practitioners use only a few project management tools?
Because many tools need data, time or skills that projects lack, and their benefits are not always visible to decision makers.
Does critical chain always work?
No. It depends on behavior such as avoiding multitasking and passing work on quickly, which organizations often find hard to change.
How should a project manager judge a tool's value?
By whether it changed a decision, prevented a problem or gave earlier warning, not by its sophistication.