QSO 680 Module 6 Critical Chain Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 680 Module 6 Critical Chain Assignment sample applies critical chain scheduling to a leveled project, cutting activity estimates to median durations, sizing project and feeding buffers, setting rules for managing those buffers and weighing the method's limits. SNHU QSO 680 (QSO-680) covers critical chain in Module 6 of its MS Project Management seminar. The project is the 18-day dry dock of the Meridian Isle, a ship of Coral Lantern Cruises, an invented Miami line, whose foremen had each quietly padded their estimates. Pooling that safety into shared buffers gives the yard a tighter target and the project manager an early warning when the ship is slipping.

CourseQSO 680 Seminar in Project Management
ModuleModule 6
Paper typegraduate assignment applying critical chain scheduling to a leveled project, cutting activity estimates to median durations, sizing project and feeding buffers, setting buffer management rules and weighing the method's limitations
LengthAbout 1,110 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Project Management
UpdatedOctober 2026

Free sample paper for QSO 680 Module 6

1

Buffers Instead of Padding: Critical Chain for the Meridian Isle Dry Dock

[Student Name]

Southern New Hampshire University

QSO 680: Seminar in Project Management

Critical Chain Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe estimates, buffers and rules for Coral Lantern Cruises in this QSO 680 assignment are invented.
2

Buffers Instead of Padding: Critical Chain for the Meridian Isle Dry Dock

Introduction

The leveled schedule for the Meridian Isle's dry dock undocks on day 18, and with prefabrication and a night shift the simulation gives about a 62 percent chance of meeting that date. Interviews with foremen while building the schedule revealed something the simulation could not: almost every estimate carried private safety, a day added here and there because past dry docks had punished anyone who ran late. Safety held privately in each activity tends to be used whether needed or not. This paper applies critical chain scheduling to pool that safety into shared buffers, sets a target inside the commitment and designs the rules for managing the buffers.

What this page is doingStates why critical chain is being applied.
3

The Critical Chain

After leveling, the longest chain of activities linked by logic or by shared resources runs through hull gauging, steel renewal on nights, lower hull blasting, coating, final coating cure and undocking, a chain of 17.0 days in the leveled schedule. Two other paths join it: the ballast water system installation, which must finish its hull penetrations before coating, and the pod overhaul, which must be reassembled before the dock is flooded. The cabin refits run separately and finish at sea if needed, so they are managed outside the chain.

What this page is doingIdentifies the resource-constrained chain.
4

Median Estimates

Each foreman on the chain was asked for a duration they would beat about half the time, recorded beside the original estimate.

Chain activities, original and median estimates in days

ActivityOriginal estimateMedian estimateSafety removed
Hull gauging and survey2.01.60.4
Steel renewal, nights5.04.01.0
Lower hull blasting3.02.60.4
Coating, three coats4.03.40.6
Coating cure2.02.00.0
Flooding and undocking1.01.00.0
Chain total17.014.62.4

The coating cure and undocking were not reduced, since chemistry and the tide do not respond to motivation.

What this page is doingRemoves individual safety.
5

Sizing the Buffers

Leach (1999) explains that critical chain removes the safety from individual estimates and aggregates it into buffers, and reports organizations finishing projects faster after adopting it. A common rule of thumb sets the project buffer at half the chain's median length, which here would be 7.3 days, far too large to be useful. Instead the buffer is sized by the square root of the sum of the squares of the safety removed from each activity, on the reasoning that independent overruns rarely all occur together. The squares of 0.4, 1.0, 0.4 and 0.6 sum to about 1.68, whose square root is about 1.3 days. Because steel renewal carries the largest uncertainty, dependent on hull gauging, the buffer was increased to 2.1 days after comparing it with the spread in the simulation. Feeding buffers of 0.8 days for the ballast water path and 1.0 day for the pod path were sized the same way.

The target undocking day is the chain's 14.6 days plus the 2.1-day buffer, day 16.7. The commitment to the cruise line remains day 18, so the plan carries 1.3 days of margin beyond the buffer for events no estimate captures, such as a hurricane watch.

What this page is doingChooses a method and explains it.
6

Buffer Management

Buffer use is reported every shift change as two numbers: the percentage of the chain completed and the percentage of the project buffer consumed. They are plotted on a fever chart with three zones. In the green zone, buffer use is lower than chain progress, and no action is needed. In the yellow zone, buffer use runs ahead of progress by up to a third, and the foreman and project manager plan a recovery, such as moving night welders to the delayed activity. In the red zone, buffer use runs ahead by more than a third, and the recovery is executed immediately, including the air-freight and overtime options approved in advance. Feeding buffers are tracked the same way.

What this page is doingGives early warning.
7

Rules on the Floor

Critical chain fails if the behavior stays the same. Three rules apply on the dock. First, chain crews work on one chain task at a time; welders on steel renewal are not pulled to other jobs until it is complete. Second, work is handed on as soon as it is done, like runners in a relay, rather than at the scheduled start of the next activity; the coating crew stands by when blasting is near completion. Third, nobody is judged on whether an individual activity met its median estimate, since half of them will not; only the buffer is judged. The superintendents agreed to the third rule only after the vice president of marine operations confirmed it in writing.

What this page is doingChanges the behavior the method needs.
8

Communicating Two Dates

A plan with two dates can confuse people unless the difference is explained. The cruise line's commercial team, its guests and the shipyard contract all use day 18, the commitment. The dock uses day 16.7, the target, together with the buffer status. Foremen were briefed that the target is not a deadline they will be punished for missing but the date the plan aims at if everyone works without padding, and that the buffer exists precisely because some activities will overrun. The daily report to Coral Lantern's vice president of marine operations shows chain progress, buffer used and the fever chart zone, not a list of activities late against their medians. If the project enters the red zone and the recovery fails to bring it back within two shifts, the commercial team is warned that day 18 is at risk while there is still time to plan guest communications.

What this page is doingExplains target and commitment.
9

Weighing the Method

The method has serious critics. Herroelen and Leus (2001) welcome its focus on resources and buffers but warn that the 50 percent buffer rule can be arbitrary, that the critical chain may change once the schedule is executed, and that the method's results depend heavily on how the initial schedule is built. Raz et al. (2003) argue that many critical chain ideas restate earlier practice and that claims for its benefits need more rigorous evidence. Both criticisms apply here. The buffers are sized by a method with explicit assumptions and checked against the simulation rather than set at half the chain. The chain will be re-identified if a feeding path's delay exceeds its buffer. And the cruise line's commitment remains day 18, so critical chain is used as a way of managing the work, not as a promise of a shorter dry dock.

What this page is doingEngages with its critics.
10

Conclusion

Critical chain removes 2.4 days of private safety from the Meridian Isle's chain, pools it into a 2.1-day project buffer and two feeding buffers, and sets a target of day 16.7 inside the day-18 commitment. The fever chart turns buffer use into an early warning, and three floor rules give the method a chance to work. The method's limits are acknowledged and handled rather than ignored.

What this page is doingSummarizes the plan.
11

References

Herroelen, W., & Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management, 19(5), 559-577. https://doi.org/10.1016/S0272-6963(01)00054-7

Leach, L. P. (1999). Critical chain project management improves project performance. Project Management Journal, 30(2), 39-51. https://doi.org/10.1177/875697289903000207

Raz, T., Barnes, R., & Dvir, D. (2003). A critical look at critical chain project management. Project Management Journal, 34(4), 24-32. https://doi.org/10.1177/875697280303400404

What the QSO 680 Module 6 instructions ask for

The Module 6 assignment in QSO 680 typically asks students to apply critical chain project management to a project or to evaluate it against traditional critical path methods. Expect to identify the critical chain after resources are considered, reduce activity estimates by removing individual safety, size a project buffer and feeding buffers, explain how buffers are monitored and describe the behaviors the method expects, such as avoiding multitasking and passing work on as soon as it is done. Strong papers explain the buffer sizing method and its assumptions, show the resulting target and commitment dates, design buffer management zones and actions, and engage honestly with criticisms of the method rather than presenting it as a cure. A table comparing the critical path and critical chain versions helps.

How this QSO 680 Module 6 critical chain assignment example is built

The assignment applies critical chain to the Meridian Isle's leveled 18-day dry dock at Coral Lantern Cruises, a fictional Miami line. The chain through hull gauging, steel renewal, blasting, coating and undocking is rebuilt from median estimates, shortening it from 17.0 to 14.6 days. A project buffer of about 2.1 days is sized by the square root of the sum of squared cuts, not the 50 percent rule, with feeding buffers of 0.8 and 1.0 days where ballast water and pod paths join. The target is day 16.7 inside the day-18 commitment, tracked by a green, yellow and red fever chart, with floor rules against multitasking. Criticisms are weighed. Leach, Herroelen and Leus and Raz, Barnes and Dvir are cited.

Where the QSO 680 Module 6 rubric puts the points

The QSO 680 critical chain rubric generally rewards a correctly identified resource-constrained chain, estimates reduced with a stated rationale, buffers sized by a named method with its assumptions, feeding buffers where paths join the chain, buffer management zones with actions, the behavioral rules the method depends on, a fair treatment of the method's criticisms and research to support each choice. Papers stand out when the buffer plan gives earlier warning than the old schedule did. They lose marks for halving estimates without explanation, for buffers that are just padding moved to the end, for ignoring feeding paths, for no monitoring rules or for presenting the method uncritically. Neat tables and APA references that match the citations earn the final marks.

QSO 680 Module 6 help: the mistakes that cost points

Start with a schedule that is already leveled, since the critical chain depends on resources as well as logic. For each chain activity, ask the foreman for a median estimate, one they would beat half the time, and record how much safety came out. Size the project buffer from those cuts with a stated method; the square root of the sum of squares is common and smaller than half the chain. Add feeding buffers where other paths join. Set zones for buffer use against chain progress and decide what happens in each. Write the floor rules people must follow. Then answer the critics: buffers can be arbitrary and the chain can move. Papers often cut every estimate in half and call it critical chain; the method only works if the behavior changes too.

Get QSO 680 Module 6 written to your instructions

Share the QSO 680 Module 6 instructions and your leveled schedule. A writer identifies the critical chain, converts estimates to median durations, sizes project and feeding buffers with a stated method, sets buffer management zones and floor rules, weighs the method's criticisms and supports the plan with critical chain research. The first QSO 680 assignment is free and comes back within two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 680 papers and related MS Project Management samples

QSO 680 Module 6 questions, answered

Where can I find a free QSO 680 Module 6 critical chain sample?

The complete QSO 680 Module 6 assignment is on this page: buffers and a fever chart for an invented cruise ship's dry dock.

What is critical chain project management?

A scheduling method that uses median activity estimates, accounts for resources and protects the finish with shared buffers instead of padding each task.

What is a project buffer?

Time placed at the end of the critical chain to absorb overruns on chain activities, sized from the safety removed from their estimates.

What is a feeding buffer?

A buffer placed where a noncritical path joins the critical chain, protecting the chain from delays on that path.

What is a fever chart in critical chain?

A chart plotting buffer consumed against chain completed, with zones signaling when to watch, plan action or act.