MGT 605 Module 2 Conceptual Estimate Assignment Example

Reviewed by Portia Lambrick, MBA

This MGT 605 Module 2 Conceptual Estimate Assignment sample shows how a contractor prices a building from schematic drawings, before quantities exist. SNHU MGT 605 (MGT-605) asks MS in Management students to build an early estimate and explain how far it can be trusted. Kearsarge Building Company, a composite New Hampshire general contractor, prices a new shop and lab wing, a renovation and site work for a regional career and technical center in Laconia. The paper derives a cost per square foot from adjusted past projects, adds design contingency and escalation, states an accuracy range and compares the result with the school district's published construction budget.

CourseMGT 605 Construction Budgeting, Estimating & Bidding
ModuleModule 2
Paper typegraduate assignment preparing a conceptual cost estimate from schematic design
LengthAbout 1,110 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 605 Module 2

1

Five Past Schools and One Sketch: A Conceptual Estimate for the Lakes Region Career and Technical Center

[Student Name]

Southern New Hampshire University

MGT 605: Construction Budgeting, Estimating & Bidding

Conceptual Estimate Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingKearsarge Building Company, the school district and all cost data are fictional and illustrative.
2

Five Past Schools and One Sketch: A Conceptual Estimate for the Lakes Region Career and Technical Center

Introduction

In January 2026, the Winnipesaukee Regional School District issued a prequalification notice for the Lakes Region Career and Technical Center in Laconia, New Hampshire. The project adds a two-story, 41,000-square-foot wing of shops and labs for automotive, welding, building trades, culinary and health science programs, renovates 12,000 square feet of a 1972 classroom building and reworks parking and utilities. The district has published a construction budget of $23.4 million. Kearsarge Building Company, a Concord general contractor, must decide whether to pursue the work. This paper prepares the conceptual estimate that decision needs, using the schematic design issued with the notice, and states how far the figure can be trusted.

What this page is doingStates the purpose and the design stage.
3

Method

At the schematic stage there are floor plans, a building section and a one-page outline of systems, but no wall types, structural sizes or equipment schedules. Quantities cannot yet be measured, so the estimate uses a square-foot method built on Kearsarge's own completed projects. Kim et al. (2004) compared regression, neural network and case-based reasoning models on 530 residential buildings in Korea and found the neural network most accurate, while case-based reasoning, which retrieves similar past projects, was easier to update and explain. Kearsarge's database holds too few projects for a neural network, so it uses the simpler idea behind case-based reasoning: find the most similar past buildings and adjust them.

What this page is doingNames the method and why it fits.
4

Comparable Projects

Five school projects completed between 2019 and 2024 are close enough in type and size to serve. Each cost was moved to January 2026 with a building cost index and to Concord with a location factor.

Comparable school projects, adjusted

Project (completed)New area (sq ft)Cost at completion per sq ftTime factor to 2026Location factorAdjusted per sq ft
Regional high school addition (2019)38,500$3191.391.02$452
Middle school science wing (2021)22,000$3561.261.00$449
Technical school shop building (2022)29,400$3911.170.99$453
Elementary school replacement (2023)61,000$3811.101.03$432
Community college lab building (2024)33,800$4471.050.98$460
Median$452

The adjusted values fall within about $28 of each other, which suggests the sample is consistent. The technical school shop building is the closest match, and its adjusted cost, $453, sits almost exactly at the median.

What this page is doingShows the data and the adjustments.
5

Project Adjustments

The Laconia wing will carry more mechanical work than a typical school. Welding booths need local exhaust, the building trades shop needs a dust collection system, the automotive bay needs vehicle exhaust extraction and compressed air reaches every shop. Kearsarge's technical school project spent about 22 percent of its cost on mechanical systems, against roughly 17 percent for the general classroom buildings. A five percent premium on the median, rounding to $475 per square foot, reflects that difference.

The renovation is priced separately. Selective demolition, asbestos abatement in floor tile and pipe insulation, new lighting and ventilation and new finishes in an occupied campus cost far less per square foot than new construction but carry more uncertainty. Kearsarge's two recent school renovations, adjusted, ran $188 and $221; this estimate uses $205. Site work, including a relocated bus loop, 90 parking spaces, stormwater treatment and new water and gas services, is priced from a quick takeoff at $1.18 million.

What this page is doingExplains what makes this building different.
6

Estimate Summary

Conceptual estimate, January 2026 prices unless noted

ComponentBasisAmount
New shop and lab wing41,000 sq ft at $475$19,475,000
Renovation of 1972 building12,000 sq ft at $205$2,460,000
Site work and utilitiesQuick takeoff$1,180,000
Subtotal, current prices$23,115,000
Design contingency10 percent of subtotal$2,311,500
Subtotal with contingency$25,426,500
Escalation to construction midpoint4 percent a year for 14 months$1,190,000
Point estimate$26,616,500

Design contingency covers what the schematic drawings do not yet show, such as the final structural system and the full extent of abatement. Escalation is a separate allowance for price changes between January 2026 and the expected midpoint of construction in March 2027; at four percent a year over fourteen months the factor is 1.047.

What this page is doingPresents the figure with every allowance visible.
7

Accuracy

A schematic estimate should be read as a range. Trost and Oberlender (2003), working with estimates from the process industry, found that accuracy depended above all on the quality of the design basis behind the estimate, the experience of the estimating team and the time allowed to prepare it. Here the design basis is thin, the team is experienced and the time was two days. Applying a range of 15 percent under to 20 percent over, typical at this stage of design, gives $22.6 million to $31.9 million.

Akintoye (2000) surveyed contractors and grouped what drives estimating practice into factors such as project complexity, the technology involved, the quality of project information, contract terms, duration and market conditions. Three of those push risk upward here: shop systems are complex, the information is early and the regional market for mechanical and electrical subcontractors is busy. That is why the range leans high.

What this page is doingGives a range and the reasons for it.
8

Comparison With the Budget

The district's $23.4 million budget sits near the bottom of the range, about 12 percent below the point estimate. If the estimate is right, bids will probably exceed the budget unless the district reduces scope, finds more money or both. There is perhaps a one in five chance, judging by where the budget falls in the range, that competitive bids land under it as drawn.

What this page is doingTies the estimate to the decision.
9

Sensitivity

Three inputs drive most of the uncertainty. Every $25 change in the new-wing rate moves the point estimate by about $1.2 million once contingency and escalation are applied, so the shop premium matters more than any other single judgment. Raising escalation from four to six percent a year adds roughly $0.6 million, and lowering it to two percent removes about the same. Doubling the renovation allowance for abatement, if the survey finds asbestos in plaster as well as floor tile, adds about $0.4 million. Even if all three break in the district's favor, the estimate stays above $24 million, which is the main reason this paper doubts that the budget will hold without changes to scope.

What this page is doingShows which assumption moves the total most.
10

Limitations

Five comparable projects is a small sample. The estimate cannot price the abatement accurately until the district's hazardous materials survey is released, and it treats shop equipment as furnished by the owner, which the notice implies but does not state. A detailed estimate at design development will replace this one.

What this page is doingSays what the estimate cannot do.
11

Conclusion

Kearsarge should pursue the prequalification, because the project suits its self-performed concrete and its school experience, but it should expect the district to cut scope or add alternates before bidding. Sharing the range, not the point figure, with its own leadership will keep everyone honest about how little the drawings yet show.

What this page is doingStates what Kearsarge should do with it.
12

References

Akintoye, A. (2000). Analysis of factors influencing project cost estimating practice. Construction Management and Economics, 18(1), 77-89. https://doi.org/10.1080/014461900370979

Kim, G.-H., An, S.-H., & Kang, K.-I. (2004). Comparison of construction cost estimating models based on regression analysis, neural networks, and case-based reasoning. Building and Environment, 39(10), 1235-1242. https://doi.org/10.1016/j.buildenv.2004.02.013

Trost, S. M., & Oberlender, G. D. (2003). Predicting accuracy of early cost estimates using factor analysis and multivariate regression. Journal of Construction Engineering and Management, 129(2), 198-204. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:2(198)

What the MGT 605 Module 2 instructions ask for

The MGT 605 conceptual estimate generally asks for an early cost estimate for a defined project using square-foot, unit or parametric methods, along with an explanation of the assumptions and the likely accuracy. Expect to choose comparable projects or published cost data, adjust them for time and location, separate new work from renovation and site work and add contingency and escalation. The strongest papers show every adjustment in a table, justify the cost per square foot rather than borrowing it, treat contingency and escalation as separate allowances and finish with a range, not a single number. Comparing the result with the owner's budget, and saying what the comparison means, ties the estimate to a decision.

How this MGT 605 Module 2 conceptual estimate assignment example is built

Kearsarge's estimator prices the Laconia project from the schematic design issued with the prequalification notice. Five past school projects, adjusted to 2026 prices and a Concord location, give a median of $452 per square foot; shop ventilation, compressed air and dust collection add five percent, so the new wing carries $475. Renovation of the 1972 building is priced at $205 per square foot and site work at $1.18 million. A ten percent design contingency and fourteen months of escalation at four percent a year bring the point estimate to $26.62 million, with a range of $22.6 to $31.9 million. The paper uses Kim, An and Kang, Trost and Oberlender and Akintoye to explain the method and its limits.

Where the MGT 605 Module 2 rubric puts the points

Conceptual estimates get marked mostly on the method chosen, the quality of the cost data, the handling of adjustments, contingency and escalation, the accuracy statement and APA writing. Top papers explain why each comparable project belongs, show how prices were moved to the estimate date and location, keep design contingency apart from escalation and give a range that matches the maturity of the design. Points slip when a single national cost figure is used with no adjustment, when contingency is hidden inside unit rates, when the range is missing and when the paper never compares the estimate with the budget. Clear tables with totals that add up, and sources used to defend method rather than to fill space, also matter.

MGT 605 Module 2 help: the mistakes that cost points

Begin with three to six comparable buildings of the same type, and write down what each cost, when and where. Move each cost to today with a price index and to your city with a location factor, then take the median. Adjust for what makes your building different, such as heavy mechanical systems. Price renovation and site work separately, because they behave differently from new floor area. Add design contingency for what the drawings do not yet show and escalation for price changes until the midpoint of construction. Finish with a range. Early estimates are judged by whether they are honest about their uncertainty, so do not present a schematic figure to the dollar.

Get MGT 605 Module 2 written to your instructions

Send the MGT 605 Module 2 directions with the building type, floor area and location you are pricing. We assemble adjusted unit costs from comparable projects, add contingency and escalation the way estimators do and state a defensible accuracy range. Your first conceptual estimate is on us and returns in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 605 papers and related MS in Management samples

MGT 605 Module 2 questions, answered

Where can I find a free MGT 605 Module 2 Conceptual Estimate Assignment sample?

A full MGT 605 Module 2 conceptual estimate is published here, pricing a shop and lab wing, a renovation and site work for a career and technical center.

How do you prepare a square-foot conceptual estimate?

Collect costs of similar buildings, adjust them to the estimate date and location, take a representative cost per square foot, multiply by floor area and add contingency and escalation.

What is the difference between contingency and escalation?

Design contingency covers scope the drawings do not yet show; escalation covers expected price increases between the estimate date and the time the work is bought and built.

How accurate is a conceptual construction estimate?

At the schematic stage a range of about 15 percent under to 20 percent over is common, which is why early figures should be stated as ranges.

Which cost estimating model is most accurate?

In a Korean study of 530 residential buildings, a neural network model beat regression and case-based reasoning on accuracy, though case-based reasoning was easier to update and explain.