$24.9 Million on Sixty Percent Drawings: Kearsarge's Project Budget and Cost Plan for the Laconia Technical Center
[Student Name]
Southern New Hampshire University
MGT 605: Construction Budgeting, Estimating & Bidding
Milestone One: Project Budget
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
$24.9 Million on Sixty Percent Drawings: Kearsarge's Project Budget and Cost Plan for the Laconia Technical Center
Introduction
The Winnipesaukee Regional School District will put its Laconia technical school expansion out to bid in late spring 2026. The project is a new two-story wing of about 38,800 square feet for shops and labs, after the owner removed a 2,200-square-foot mezzanine, and 9,500 square feet of renovation in the 1972 classroom building. In February the district raised the construction budget to $25.9 million, moving money from its furniture and equipment allowance and its own contingency after Kearsarge and other prequalified firms warned that $23.4 million would not hold. This milestone sets Kearsarge's project budget at design development, before bid documents are final, and plans the work that will turn it into a bid.
Budget by Trade
The budget follows the twelve trade packages Kearsarge will buy or perform. The first six now rest on quantities measured from the sixty percent drawings; the last six still rest on square-foot pricing because the mechanical, electrical and interior designs are incomplete.
Direct cost by trade, March 2026 prices
| Trade package | Basis | Amount |
|---|---|---|
| Site, utilities and paving | Measured | $1,290,000 |
| Concrete, self-performed | Measured | $864,000 |
| Masonry | Measured | $1,640,000 |
| Structural steel and deck | Measured | $2,510,000 |
| Carpentry, doors and specialties | Measured | $1,030,000 |
| Roofing, walls and windows | Measured | $2,050,000 |
| Subtotal, measured trades | $9,384,000 | |
| Interior finishes | Per square foot | $2,250,000 |
| Casework and equipment rough-in | Per square foot | $860,000 |
| Fire protection | Per square foot | $495,000 |
| Plumbing and compressed air | Per square foot | $1,460,000 |
| HVAC, exhaust and dust collection | Per square foot | $3,700,000 |
| Electrical and low voltage | Per square foot | $2,903,000 |
| Subtotal, square-foot trades | $11,668,000 | |
| Total direct cost | $21,052,000 |
Mechanical, electrical and fire protection work is about 41 percent of direct cost, more than in a typical school, because of shop exhaust, compressed air and power for welding and machine tools.
General Conditions
The district's schedule allows sixteen months from a July 2026 start to substantial completion in October 2027, with the renovation done while students occupy the rest of the campus. Kearsarge's general conditions cover a full-time superintendent and assistant, a project manager at sixty percent, a project engineer, the field office, temporary power, heat and water, fencing, cleanup, dumpsters, safety staff and survey. At about $73,750 a month, sixteen months comes to $1,180,000.
Allowances
From direct cost to project budget
| Line | Basis | Amount |
|---|---|---|
| Direct cost plus general conditions | $22,232,000 | |
| Payment and performance bond, builder's risk, liability | 1.6 percent | $355,712 |
| Design contingency | 6 percent | $1,355,263 |
| Escalation to bid and buyout | 4 percent | $957,719 |
| Project budget | $24,900,694 |
The six percent contingency is not a reserve for mistakes. It covers what the sixty percent drawings still lack, mainly in the square-foot trades. Flyvbjerg (2006) argued that allowances should be set from how a reference class of similar projects actually turned out, rather than from the team's confidence in its own plan. Kearsarge's last six school estimates at design development moved by between minus 3 and plus 9 percent by bid day, a median of plus 5, which supports six percent overall, weighted toward the mechanical and electrical lines. Escalation of four percent covers price movement between March prices and the buyout of subcontracts after award; once subcontracts are signed, it falls away.
Cash Flow
Billings will follow the usual S-curve: slow during site work and foundations, fastest while steel, envelope and mechanical rough-in proceed at once and slow again during finishes and commissioning.
Forecast billings by quarter
| Quarter | Share of budget | Billings |
|---|---|---|
| July to September 2026 | 6 percent | $1,494,000 |
| October to December 2026 | 17 percent | $4,233,000 |
| January to March 2027 | 27 percent | $6,723,000 |
| April to June 2027 | 27 percent | $6,723,000 |
| July to September 2027 | 17 percent | $4,233,000 |
| October 2027 and closeout | 6 percent | $1,494,000 |
The district will retain five percent of each payment until substantial completion, so about $1.25 million of Kearsarge's earned revenue sits with the owner for most of 2027. Kearsarge pays most subcontractors with the same retainage withheld, but its own concrete crews and its general conditions are paid weekly, so the company must finance its share of the curve from its credit line in the first two quarters.
Risk and Delay Cost
Delay is the risk this budget feels most directly, because general conditions are a monthly cost. Chan and Kumaraswamy (1997), surveying clients, consultants and contractors in Hong Kong, found that poor site management, unforeseen ground conditions, slow decisions and client-initiated changes ranked among the main causes of time overruns. In a survey of large Saudi Arabian projects, Assaf and Al-Hejji (2006) reported that changes ordered by the owner during construction were the cause all three parties agreed on. Both point to risks present here: the renovation sits in an occupied school, and the district's committee meets monthly. Each month of delay that is not the owner's responsibility would cost Kearsarge about $74,000 in general conditions, before any liquidated damages the contract may impose. Ledge that the borings missed is the main ground risk and will be carried as a unit price.
Owner's Budget Check
The district's $25.9 million is a construction budget only; its architect, testing, furniture and project management costs sit in a separate soft-cost line of the bond. Kearsarge's budget must therefore be compared with the $25.9 million alone, after overhead and profit are added. At a two percent home office charge and a profit of three to four percent, a bid built on this budget would land between about $26.2 and $26.4 million, which is above the district's figure. The design contingency is the gap: if the remaining design comes in as the reference class suggests, much of the six percent will be consumed, and if it comes in better, the bid can fall below the budget. That is the clearest reason to buy the square-foot trades early and replace guesses with prices.
Buyout Plan
Kearsarge will issue twelve bid packages to subcontractors when the district releases the bid documents, with a target of at least three numbers per trade. Mechanical, electrical and fire protection will go first, since they are the least certain lines. Kearsarge's estimator will take off quantities for every trade so that subcontractor bids can be checked for scope gaps, and the concrete package will be repriced with updated ready-mix quotes. The design contingency will be replaced line by line by firm numbers, and any of it remaining at bid day becomes a small bid contingency or is removed.
Conclusion
At $24.9 million, Kearsarge's budget sits about $1 million under the district's revised construction budget of $25.9 million, which leaves room for overhead and profit in a competitive bid. The budget's weakest lines are the mechanical and electrical trades, and the buyout plan puts them first. Milestone Two will replace this budget with a definitive estimate and the bid strategy built on it.
References
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-357. https://doi.org/10.1016/j.ijproman.2005.11.010
Chan, D. W. M., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1), 55-63. https://doi.org/10.1016/S0263-7863(96)00039-7
Flyvbjerg, B. (2006). From Nobel prize to project management: Getting risks right. Project Management Journal, 37(3), 5-15. https://doi.org/10.1177/875697280603700302
What the MGT 605 Module 5 instructions ask for
MGT 605 Milestone One commonly asks you to introduce a construction project and present its budget, covering the major cost categories, the assumptions behind them, contingency and the factors that could change the figure. Some versions also ask for a cash flow forecast or a timeline. A strong milestone describes the project and its design stage, organizes costs by trade or division, separates direct work from general conditions, bond, insurance, contingency and escalation and explains each allowance. It shows when money will be spent, not only how much, and names the risks most likely to move the budget. The best milestones also connect the budget to the estimating work still to come, so the final project has a clear path.
How this MGT 605 Module 5 milestone one example is built
Kearsarge's milestone budgets the Laconia shop and lab wing at $24.90 million from sixty percent drawings. Six trade lines worth $9.38 million are priced from measured quantities and six worth $11.67 million by the square foot; general conditions of $1.18 million follow from a sixteen-month schedule. Bond and insurance add 1.6 percent, design contingency six percent and escalation four percent. A quarterly billing curve peaks at $6.72 million in each of the two middle quarters, and retainage holds about $1.25 million until the end. Using Chan and Kumaraswamy and Assaf and Al-Hejji, the paper prices a month of delay at roughly $74,000, and it uses Flyvbjerg to defend the contingency.
Where the MGT 605 Module 5 rubric puts the points
Milestone One budgets are usually assessed on the project description, the completeness and organization of the budget, the justification of assumptions, contingency and escalation, the treatment of timing and risk and APA writing. Top milestones give totals that reconcile, explain where each figure came from and say which numbers are firm and which are rough. Marks are lost for budgets that list only trade costs, for contingency with no basis, for escalation forgotten or folded into unit prices and for risks named in general terms with no cost attached. Instructors also look for a budget that clearly sets up the definitive estimate and bid in the later milestones. A cash flow view and a candid note on the weakest numbers both strengthen the paper.
MGT 605 Module 5 help: the mistakes that cost points
Describe the project in a paragraph: owner, size, use, location and design stage. Then build the budget from the bottom: trade costs first, then the costs of running the job, such as supervision and temporary facilities, which depend on how many months it lasts. Add bond and insurance, then design contingency sized to what the drawings still lack, then escalation to the midpoint of construction. Show when the money is spent, because owners and contractors both have to finance the curve, and remember that retainage delays cash. Put a dollar figure on the main risks, such as a month of delay. Close with what must be firmed up before bid day and who will do it.
Get MGT 605 Module 5 written to your instructions
Send us the MGT 605 Milestone One guidelines and the construction project you chose. We build the budget by trade, set general conditions from the schedule, size contingency and escalation, forecast cash flow and retainage and plan the buyout. Your first milestone is free, with a full draft in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More MGT 605 papers and related MS in Management samples
- MGT 605 Module 1 Discussion: A Bond Number Set Too Early
- MGT 605 Module 2 Conceptual Estimate Assignment: A Square-Foot Estimate for a Shop Wing
- MGT 605 Module 3 Discussion: From Rough Order to Definitive
- MGT 605 Module 4 Pricing Assignment: Labor, Equipment and Materials for Concrete
- MGT 605 Module 6 Discussion: To Bid or Not, and at What Markup
- MGT 605 Module 7 Competitive Analysis Assignment: Three Rivals and a Markup
- MGT 605 Module 8 Milestone Two: The Definitive Estimate and Bid Strategy
- MGT 605 Module 9 Discussion: Low Bid or Construction Manager at Risk
- MGT 605 Module 10 Final Project: The Complete Bid Proposal
- ACC 550 Module 5 Milestone Two: An Activity-Based Model for Retail and Bulk Channels
- HRM 630 Module 4 Process Analysis Assignment: Mapping and Counting Missed Appointments
- FIN 610 Module 8 Short-Term Financing Assignment: Revolver, Asset-Based Loan or Factoring
- MGT 510 Module 6 Discussion: The Sales Goal and the Member's Interest
MGT 605 Module 5 questions, answered
Where can I find a free MGT 605 Module 5 Milestone One sample?
You can read a full MGT 605 Module 5 Milestone One on this page: a contractor's project budget for a technical center wing, with a cash flow curve.
What goes into a construction project budget?
Trade or subcontract costs, general conditions for running the job, bond and insurance, design contingency, escalation and, for the contractor, overhead and profit added at bid time.
What are general conditions in construction?
The time-related costs of running a project, such as the superintendent, project manager, trailer, temporary utilities, cleanup and safety, usually budgeted per month.
Why does a construction budget need a cash flow forecast?
Spending follows an S-shaped curve and retainage holds back part of each payment, so both owner and contractor need to know when cash will be needed, not only how much.
What usually causes construction delays?
Surveys of owners, contractors and consultants point to slow decisions, design changes, poor site management and unforeseen ground conditions among the most frequent causes.