MGT 605 Module 1 Discussion Example

Reviewed by Portia Lambrick, MBA

This MGT 605 Module 1 Discussion sample asks why construction budgets fixed early in a project so often prove too low, and what that means for a contractor deciding whether to bid. SNHU MGT 605 (MGT-605) begins its MS in Management construction coursework with budgets, estimates and bids as three different numbers. The post introduces Kearsarge Building Company, a composite Concord general contractor, and a school district whose $23.4 million construction budget was set from a sketch two years before bidding. Research on cost underestimation in public works and on optimistic forecasting explains the gap, and it ends by asking classmates how a bidder ought to respond.

CourseMGT 605 Construction Budgeting, Estimating & Bidding
ModuleModule 1
Paper typegraduate discussion post on why owner budgets for construction projects come in low
LengthAbout 360 words, 3 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 605 Module 1

1

Module One Discussion

The District Has a Number, and It Is Probably Wrong

In this course I am tracking a composite firm close to work I know: Kearsarge Building Company, a general contractor in Concord, New Hampshire, with about $70 million in yearly volume and 110 people in the field. Kearsarge just received a prequalification notice from the Winnipesaukee Regional School District for a new 41,000-square-foot, two-story shop and lab wing at its career and technical center in Laconia, together with 12,000 square feet of renovation in the 1972 building next door. The notice lists a construction budget of $23.4 million. Voters approved the bond in March 2025, using a figure the architect prepared in 2024 from a single-page massing sketch.

What this page is doingA project I am watching.
2

Kearsarge's estimator ran a two-minute check. Its last five school projects, adjusted to 2026 prices, cost a median of about $452 per square foot for new construction, and shop space with welding exhaust and dust collection costs more. At $475 for the new wing, $205 for renovation and about $1.2 million for site work, the total lands near $23.1 million before any design contingency or price escalation; with both, it is about $26.6 million. The district's budget sits roughly 12 percent under that.

What this page is doingA quick test of the number.
3

None of this means the architect erred. Flyvbjerg et al. (2002) studied 258 transport projects in 20 nations and found costs above forecast in almost nine of ten, by 28 percent on average, with no sign of improvement across seventy years. Kahneman and Lovallo (1993) argued that planners take an inside view, picturing their own project's plan, and neglect the outside view of how similar projects turned out. Odeck (2004), looking at Norwegian road projects, found overruns were proportionally largest on the smaller ones, which is the size of most school work. A budget fixed before design, then held through two years of price increases, is set up to miss.

What this page is doingWhy early numbers miss.
4

Kearsarge has three choices: skip the pursuit, bid it honestly and accept that the district may reject every bid, or bid and help the district by pricing alternates it could cut. Which path would you take, and which single fact would decide it for you?

What this page is doingThe question for us.
5

References

Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279-295. https://doi.org/10.1080/01944360208976273

Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17-31. https://doi.org/10.1287/mnsc.39.1.17

Odeck, J. (2004). Cost overruns in road construction: What are their sizes and determinants? Transport Policy, 11(1), 43-53. https://doi.org/10.1016/S0967-070X(03)00017-9

What the MGT 605 Module 1 instructions ask for

This opening MGT 605 discussion tends to ask how budgets, estimates and bids differ, why owner budgets are often unreliable and how a contractor should respond to them. Many prompts also invite you to describe a project you know, whether from your own job or the news. A useful post keeps the three terms apart: the budget is what the owner can spend, the estimate is what the work should cost and the bid is the price a contractor offers. It then tests a real or composite budget with simple numbers and uses research to explain why early figures miss. Peers can only build on your claims when they can see the square footage, the unit cost and the date behind each one.

How this MGT 605 Module 1 discussion example is built

Kearsarge Building Company, the composite contractor in this post, employs 110 field workers out of Concord, New Hampshire, and self-performs concrete and carpentry. Its business developer has the prequalification notice for a 41,000-square-foot shop and lab wing plus 12,000 square feet of renovation at a career and technical center in Laconia. The district's published construction budget is $23.4 million, set in 2024 from an architect's sketch. A quick check using Kearsarge's own school data suggests something near $26 million. The post explains the gap with Flyvbjerg, Holm and Buhl's evidence that nine in ten public works projects cost more than forecast, Kahneman and Lovallo's inside view and Odeck's data on small projects overrunning.

Where the MGT 605 Module 1 rubric puts the points

Instructors grading this first discussion commonly look for clear definitions of budget, estimate and bid, a concrete example, research that explains rather than decorates and thoughtful replies to classmates. High-scoring posts show arithmetic a reader can check, link the gap to a cause that research supports and stay open about what the poster does not yet know. Points are lost when the three terms are used as synonyms, when the example has no numbers, when sources are named without saying what they found and when replies just agree. A short statement of the decision the contractor faces, rather than a general complaint about owners, also helps the post read as management analysis. Fair-minded treatment of the owner's position earns credit too.

MGT 605 Module 1 help: the mistakes that cost points

Pick a project where you can state the size, the type of building and the owner's budget. Run one quick test: multiply the floor area by a cost per square foot you can defend from recent similar work, then compare. If the numbers disagree, ask why; the answer is usually that the budget was set before the design was known, adjusted for inflation too little or built on the hopeful inside view of one project. Cite one study of cost forecasting and say plainly what it measured. Do not accuse the owner of bad faith; early budgets miss for structural reasons. End by asking peers how a contractor should act on the gap, since that is where the course is heading.

Get MGT 605 Module 1 written to your instructions

Paste in the MGT 605 Module 1 prompt and tell us about a project whose budget looks out of step with its scope. We separate the owner's budget from an estimate and a bid, test the number with a quick parametric check and explain the gap with research on cost underestimation. An opening post costs nothing and arrives within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 605 papers and related MS in Management samples

MGT 605 Module 1 questions, answered

Where can I find a free MGT 605 Module 1 Discussion sample?

The complete MGT 605 Module 1 post sits on this page, testing a school district's construction budget for a technical center against a contractor's quick square-foot check.

How is a construction budget different from an estimate?

A budget is the amount an owner has decided it can spend; an estimate is a forecast of what the specified work will cost, prepared from the design at hand.

Why do public construction budgets often prove too low?

Studies of large samples show most public works cost more than forecast, mainly because early figures rest on immature design, optimistic assumptions and too little allowance for price changes before construction.

What did Flyvbjerg's research find about public works costs?

In 258 transport projects across 20 nations, costs ran above forecast almost nine times in ten, by about 28 percent on average, with no improvement over seven decades.

Should a contractor bid when the owner's budget looks too low?

Often yes, but with care: the contractor should price honestly, look for alternates the owner can drop and expect that the owner may reject every bid and redesign.