How Low Will Suncook Go? A Competitive Analysis of Three Rivals for the Laconia Technical Center Bid
[Student Name]
Southern New Hampshire University
MGT 605: Construction Budgeting, Estimating & Bidding
Competitive Analysis Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
How Low Will Suncook Go? A Competitive Analysis of Three Rivals for the Laconia Technical Center Bid
Introduction
Kearsarge Building Company will compete for the Laconia career school wing against firms it knows well. Its estimate of cost, including general conditions, bond, insurance and a two percent home office charge, stands at $24.68 million on the ninety percent drawings. The question is how much profit to add. Too little wastes margin if Kearsarge would have won anyway; too much hands the job to a rival. This paper identifies the competitors, turns their past bids into probabilities and recommends a markup.
The Competitors
Five firms besides Kearsarge were prequalified, but the district's planholder list shows that only three bought bid documents. Suncook Valley Construction of Manchester is the largest regional rival, with a strong school record and an open-shop workforce much like Kearsarge's. Contoocook Builders of Hillsborough is smaller and usually bids higher; it wins mainly when larger firms are busy. Piscataqua General Contractors of Portsmouth is the most unpredictable: it has won two school jobs with very low bids and lost others by wide margins. Suncook is believed to be lightly booked for 2027 after losing a hospital project, which suggests it will bid hungrily.
The Data
Kearsarge has kept its own estimates and the bid tabulations for every public job it has bid since 2016. On 34 of them at least one of these three firms also bid. For each, the rival's bid is divided by Kearsarge's estimated cost, which makes jobs of different sizes comparable.
Rival bids as a ratio of Kearsarge's estimated cost
| Rival | Bids observed | Mean ratio | Standard deviation | Lowest ratio seen |
|---|---|---|---|---|
| Suncook Valley Construction | 14 | 1.058 | 0.038 | 0.993 |
| Contoocook Builders | 11 | 1.074 | 0.049 | 1.002 |
| Piscataqua General Contractors | 9 | 1.046 | 0.061 | 0.951 |
Suncook bids about 5.8 percent above Kearsarge's cost on average, and fairly consistently. Piscataqua's average is the lowest and its spread the widest, so it is the rival most likely to undercut any given markup. A ratio below 1.0 means a rival bid below what Kearsarge believed the job would cost, which happened three times in 34 bids.
Friedman's Model
Friedman (1956) proposed treating each competitor's past bids, relative to one's own cost estimate, as a probability distribution. The chance of beating a rival at a given markup is the share of that distribution lying above one's own bid, and the chance of beating all known rivals is the product of the individual chances, on the assumption that they bid independently. Fitting a normal curve to each rival's ratios gives the results below. Expected profit is the markup times the cost times the probability of winning.
Win probability and expected profit at several markups (cost $24.68 million)
| Markup | Beat Suncook | Beat Contoocook | Beat Piscataqua | Win, Friedman | Expected profit, Friedman | Win, Gates | Expected profit, Gates |
|---|---|---|---|---|---|---|---|
| 2.0 percent | 0.84 | 0.86 | 0.67 | 0.48 | $239,000 | 0.54 | $267,000 |
| 3.0 percent | 0.77 | 0.82 | 0.60 | 0.38 | $280,000 | 0.46 | $339,000 |
| 3.5 percent | 0.73 | 0.79 | 0.57 | 0.33 | $283,000 | 0.42 | $361,000 |
| 4.0 percent | 0.68 | 0.76 | 0.54 | 0.28 | $275,000 | 0.38 | $373,000 |
| 4.5 percent | 0.63 | 0.72 | 0.51 | 0.23 | $258,000 | 0.34 | $378,000 |
| 5.0 percent | 0.58 | 0.69 | 0.47 | 0.19 | $235,000 | 0.31 | $376,000 |
| 6.0 percent | 0.48 | 0.61 | 0.41 | 0.12 | $178,000 | 0.24 | $356,000 |
Under Friedman's model, expected profit peaks at a 3.5 percent markup, with about a one-in-three chance of winning. The curve is flat between 3.0 and 4.0 percent, which means the choice within that band matters less than the choice of band.
Gates's Alternative
Gates (1967) questioned Friedman's multiplication, arguing that it understates the chance of winning when several bidders compete, and proposed a different formula: one divided by one plus the sum, across rivals, of the odds of losing to each. Applied to the same three distributions, Gates's formula gives higher win probabilities at every markup and moves the best expected profit to about 4.5 percent. The two models have been argued over for decades without a clear empirical winner. What matters here is that both put the answer between 3.5 and 4.5 percent, and both show expected profit falling off quickly above 5 percent.
The Winner's Curse
Capen et al. (1971), writing about sealed bids for offshore oil leases, observed that the company that wins is often the one that most overestimated the lease's value, so winners as a group earn less than they expected. In construction, the same logic applies to cost: if six honest estimators price the same drawings, the lowest estimate is more likely to be too low than the others. Kearsarge's estimates have themselves varied by about three percent from final cost on recent jobs. If Kearsarge wins at 3.5 percent, there is a real chance that part of the reason is an estimating miss, and a markup at the very bottom of the range leaves little room to absorb one.
What the Models Leave Out
The models assume each rival bids as it has in the past. Suncook's thin 2027 backlog argues that it may bid closer to cost than its history suggests, which would lower Kearsarge's chances at any markup. On the other side, Contoocook might not submit at all, which would raise them. The models also ignore Kearsarge's own backlog, which at 78 percent of capacity means the firm does not need this job at any price.
A Scenario Check
To see how much Suncook's backlog matters, the Friedman table was recomputed with Suncook's mean ratio lowered from 1.058 to 1.035, as if it shaved two points off its usual margin. The chance of winning at 3.5 percent then falls from 0.33 to about 0.22, and the best expected profit shifts toward 3.0 percent. A rival's hunger therefore pushes the answer down by about half a point, not more, because Piscataqua's wide spread already makes winning uncertain at any markup. That limited sensitivity is reassuring: the recommendation does not hinge on guessing one rival's mood correctly.
Recommendation
Kearsarge should bid with a markup between 3.5 and 4.0 percent, adding $864,000 to $987,000 to its cost. A point near 3.6 percent balances Friedman's optimum against Gates's higher figure, the risk that Suncook bids aggressively and the protection the firm needs against its own estimating error. The final number should be set at the bid-day review after subcontractor prices arrive, using the same table recomputed on the final cost.
Limitations
Nine to fourteen observations per rival are few, and normal curves fitted to them are rough. Past bids were on different building types and in different years, when market conditions and backlogs differed. The analysis also treats rivals as independent, though all three buy many of the same subcontractor numbers on bid day.
References
Capen, E. C., Clapp, R. V., & Campbell, W. M. (1971). Competitive bidding in high-risk situations. Journal of Petroleum Technology, 23(6), 641-653. https://doi.org/10.2118/2993-PA
Friedman, L. (1956). A competitive-bidding strategy. Operations Research, 4(1), 104-112. https://doi.org/10.1287/opre.4.1.104
Gates, M. (1967). Bidding strategies and probabilities. Journal of the Construction Division, 93(1), 75-110. https://doi.org/10.1061/JCCEAZ.0000192
What the MGT 605 Module 7 instructions ask for
This MGT 605 competitive analysis tends to ask you to identify the likely competitors on a bid, examine their strengths, weaknesses and pricing behavior and use that analysis to shape your bid strategy. Some versions point to probabilistic bidding models; others want a broader market and competitor review. A strong paper names the competitors and why they are likely to bid, uses whatever bid history is available as data rather than anecdote, explains the model chosen and its assumptions, shows the probability of winning and the expected profit at several markups and ends with a recommendation that also weighs factors the model leaves out. Honesty about thin data earns more credit than false precision.
How this MGT 605 Module 7 competitive analysis assignment example is built
The sample studies three rivals who bought plans for the Laconia bid. Kearsarge's files hold 34 public bids where one of them bid against Kearsarge; each rival bid is expressed as a ratio of Kearsarge's own cost estimate. Suncook averages 1.058 with a standard deviation of 0.038, Contoocook 1.074 with 0.049 and Piscataqua 1.046 with 0.061. Friedman's method, which multiplies the chances of beating each rival, gives a 33 percent chance of winning at a 3.5 percent markup and the highest expected profit, about $283,000. Gates's formula favors 4.5 percent. Citing Capen, Clapp and Campbell on the winner's curse, the paper recommends 3.5 to 4.0 percent on a $24.68 million cost.
Where the MGT 605 Module 7 rubric puts the points
Competitive analyses in this course are generally scored on identifying competitors, the quality of the data and analysis, the correct use of a bidding model, the link between analysis and bid strategy and APA writing. Top papers show the raw pattern before modeling it, explain each model's assumptions in plain words, present win probability and expected profit at several markups and test whether the answer changes under a second model. Points fall for competitor descriptions with no pricing evidence, for formulas applied without explaining what they assume, for a recommendation taken straight from the model and for ignoring the possibility that winning signals an estimating error. A short discussion of the bidders the data cannot describe adds realism.
MGT 605 Module 7 help: the mistakes that cost points
Start with the facts you have: who bought plans, who has bid against you before and what they bid. Express each past bid as a ratio of your own cost estimate on that job, which removes the effect of project size. Look at the averages and spreads before choosing a model. Friedman's approach treats each rival separately; Gates's formula is gentler when there are several bidders. Compute the probability of winning and the expected profit at five or six markups and show them in a table. Then step back: a model cannot see a rival's backlog or a mistake in your own estimate. Recommend a range, say which end you would choose and explain why in a sentence or two.
Get MGT 605 Module 7 written to your instructions
Post the MGT 605 Module 7 brief and whatever you know about the firms bidding against you. We turn past bid results into win probabilities, compare the Friedman and Gates models, check for the winner's curse and recommend a markup with the tradeoffs shown. A first competitive analysis is free, ready in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More MGT 605 papers and related MS in Management samples
- MGT 605 Module 1 Discussion: A Bond Number Set Too Early
- MGT 605 Module 2 Conceptual Estimate Assignment: A Square-Foot Estimate for a Shop Wing
- MGT 605 Module 3 Discussion: From Rough Order to Definitive
- MGT 605 Module 4 Pricing Assignment: Labor, Equipment and Materials for Concrete
- MGT 605 Module 5 Milestone One: The Project Budget at Design Development
- MGT 605 Module 6 Discussion: To Bid or Not, and at What Markup
- MGT 605 Module 8 Milestone Two: The Definitive Estimate and Bid Strategy
- MGT 605 Module 9 Discussion: Low Bid or Construction Manager at Risk
- MGT 605 Module 10 Final Project: The Complete Bid Proposal
- MBA 580 Module 2 Innovation Types Presentation: Incremental versus discontinuous at an automaker
- OL 640 Module 4 Discussion: Territories and Encroachment
- OL 670 Module 4 Discussion: A Founder Who Fit One Situation
- MKT 678 Module 5 Brand Architecture Assignment: Brand Architecture and an Acquired Brand
MGT 605 Module 7 questions, answered
Where can I find a free MGT 605 Module 7 Competitive Analysis Assignment sample?
This page shows a complete MGT 605 Module 7 competitive analysis that uses three rivals' bid histories to choose a markup for a school project.
What is the Friedman bidding model?
Friedman's 1956 model estimates the chance of beating each known competitor from its past bids and multiplies those chances to get the probability of winning at a given markup.
How does the Gates bidding model differ from Friedman's?
Gates proposed a different formula for combining the chances of beating several competitors, which gives higher win probabilities than Friedman's when many firms bid.
What is the winner's curse in construction bidding?
In sealed bidding, the winner is often the bidder whose estimate was furthest too low, so winning itself is evidence that the estimate may have missed costs.
How do you calculate expected profit on a bid?
Multiply the profit you would earn if you won at a given markup by the probability of winning at that markup, and compare the results across markups.