MGT 605 Module 9 Discussion Example

Reviewed by Portia Lambrick, MBA

This MGT 605 Module 9 Discussion sample compares two ways of buying construction: design-bid-build with an award to the low bidder, and a construction manager at risk hired early who later guarantees a maximum price. SNHU MGT 605 (MGT-605) asks MS in Management students near the end of the course how procurement method shapes estimating and bidding. Kearsarge Building Company, a composite New Hampshire general contractor, answers a school district's question about the second phase of its technical center. The post weighs what low bidding did well and badly on phase one, applies research on procurement contracts and competition and asks classmates which method they would pick.

CourseMGT 605 Construction Budgeting, Estimating & Bidding
ModuleModule 9
Paper typegraduate discussion post comparing low-bid procurement with construction manager at risk
LengthAbout 380 words, 3 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 605 Module 9

1

Module Nine Discussion

Phase Two Should Not Be Bought Like Phase One

At the Laconia prebid meeting, the district's facilities director asked every bidder for advice in writing: phase two of the career and technical center, a 30,000-square-foot gymnasium and commons built while the school is open, is two years away. Should the district buy it the way it bought phase one, by public bid to the lowest responsible bidder, or hire a construction manager at risk during design?

What this page is doingThe district asked a fair question.
2

Phase one produced real price competition. Four firms bought documents, and each had every reason to sharpen its number. But low bidding also meant no contractor saw the design until it was done. Kearsarge's budget at design development missed the shop ventilation by more than ten percent because those systems had not yet been drawn, and every bidder carried that uncertainty into its price. We also had no way to suggest cheaper ways to meet the shop requirements, such as a central dust collector shared by two shops, because the design was fixed before any builder looked at it. Phase two has a different profile: the gym's long-span roof, a phased opening around the occupied school and a tight window between graduation and the fall term.

What this page is doingWhat low bidding did well and badly.
3

Bajari and Tadelis (2001) modeled the choice between fixed-price and cost-plus contracts and argued that fixed prices give the strongest incentive to control cost but become expensive when designs change after award, because every change must be renegotiated. Bajari et al. (2009), studying private building contracts in Northern California, found that owners were more likely to negotiate than to auction when projects were complex and the pool of capable bidders was small. Drew and Skitmore (1997) found that contractors bid most competitively within a particular range of contract sizes, so the number of serious bidders depends on the job's size as well as the market. Phase two is complex, phased and mid-sized for our region, which points to fewer serious bidders and more value in early contractor input.

What this page is doingWhat the research suggests.
4

I would recommend a construction manager at risk selected on qualifications and fee, with open-book subcontractor bidding. The district gives up some competition on the general contractor's fee but gains cost advice while the gym is still on paper. Would you recommend the same, or would you trust low bidding with a more complete design?

What this page is doingMy answer, and a question.
5

References

Bajari, P., McMillan, R., & Tadelis, S. (2009). Auctions versus negotiations in procurement: An empirical analysis. Journal of Law, Economics, and Organization, 25(2), 372-399. https://doi.org/10.1093/jleo/ewn002

Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. RAND Journal of Economics, 32(3), 387-407. https://doi.org/10.2307/2696361

Drew, D., & Skitmore, M. (1997). The effect of contract type and size on competitiveness in bidding. Construction Management and Economics, 15(5), 469-489. https://doi.org/10.1080/014461997372836

What the MGT 605 Module 9 instructions ask for

The Module 9 discussion in MGT 605 usually asks you to compare project delivery or procurement methods, such as design-bid-build with competitive bidding, construction manager at risk and design-build, and to explain how each affects budgeting, estimating and the bid. Some prompts ask which you would recommend for a specific project. A strong post compares the methods on concrete features of a real or composite project, such as design completeness, complexity, schedule and the number of capable bidders, and uses research on contracts and competition. It acknowledges what each method gives up and avoids presenting any one as always better, since the evidence points to fit between method and project.

How this MGT 605 Module 9 discussion example is built

In this sample, the Winnipesaukee Regional School District asks bidders whether phase two of its Laconia technical center, a 30,000-square-foot gymnasium and commons to be built while the school operates, should be bought by low bid or through a construction manager at risk. Kearsarge's post notes that low bidding on phase one produced keen prices but forced bidders to price shop ventilation before it was designed. Using Bajari and Tadelis on fixed-price versus cost-plus contracts, Bajari, McMillan and Tadelis's California evidence that complex projects are more often negotiated and Drew and Skitmore on competitive size ranges, it recommends a construction manager at risk for phase two and asks peers whether they agree.

Where the MGT 605 Module 9 rubric puts the points

When instructors mark a delivery-method post, they check whether each method is described correctly, whether it is tested against one specific project, whether the research is explained and whether replies push a classmate's thinking. The posts that do best compare methods on the project's own features, show what each method does to the owner's budget certainty and to the contractor's estimating risk and admit the costs of the recommended method. Posts lose credit when methods are described in general terms with no project, when one method is called best without conditions, when research is cited without explaining its finding and when replies simply restate the post. Including what the owner would have to do differently under the recommended method, such as selecting a contractor on qualifications, shows practical understanding.

MGT 605 Module 9 help: the mistakes that cost points

Choose a project and list the features that matter for procurement: how complete the design is when a price is needed, how complex or uncertain the work is, how tight the schedule is and how many capable firms would compete. Then explain what low bidding and a construction manager at risk each do with those features. Use research on contract types and competition, not only trade association brochures. Recommend a method for your project, and name what the owner gives up by choosing it, such as some price competition on the general contractor's fee. Keep the post brief, and in replies test a classmate's recommendation against one feature of their project they may have missed.

Get MGT 605 Module 9 written to your instructions

Drop in the MGT 605 Module 9 prompt and the owner or project you have in mind. We compare low bid, construction manager at risk and negotiated routes on that project's complexity, timing and competition, cite procurement research and end with a question for peers. A first post is free, typically back in two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 605 papers and related MS in Management samples

MGT 605 Module 9 questions, answered

Where can I find a free MGT 605 Module 9 Discussion sample?

This page has the full MGT 605 Module 9 post comparing low bid with a construction manager at risk for the second phase of a school project.

What is construction manager at risk?

A delivery method in which the owner hires a contractor during design to advise on cost and schedule, and the contractor later commits to a guaranteed maximum price and builds the project.

What are the drawbacks of low-bid procurement?

It needs complete design before pricing, gives the owner no contractor input during design and can reward bidders who miss scope, which leads to change orders and disputes.

When do owners negotiate construction contracts instead of bidding them?

Evidence from private building contracts suggests negotiation is more common when projects are complex, designs incomplete and capable bidders few.

Does construction manager at risk cost more than low bid?

The contractor's fee may be slightly higher without head-to-head price competition, but owners often accept that for earlier cost advice and fewer surprises on complex work.