MGT 605 Module 4 Pricing Assignment Example

Reviewed by Portia Lambrick, MBA

This MGT 605 Module 4 Pricing Assignment sample prices labor, equipment and materials for one trade a general contractor performs with its own crews. SNHU MGT 605 (MGT-605) has MS in Management students build prices from quantities, productivity rates and current costs rather than from lump sums. Kearsarge Building Company, a composite New Hampshire general contractor, prices the concrete for a new career and technical center wing: footings, frost walls and two kinds of slab. The paper computes labor hours from unit rates, burdens the wage, prices ready-mix and rebar, decides whether to rent or use its own equipment and allows for overtime the schedule will demand.

CourseMGT 605 Construction Budgeting, Estimating & Bidding
ModuleModule 4
Paper typegraduate assignment pricing labor, equipment and materials for a self-performed trade
LengthAbout 1,080 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 605 Module 4

1

Hours, Yards and a Rented Telehandler: Pricing Kearsarge's Self-Performed Concrete for the Laconia Wing

[Student Name]

Southern New Hampshire University

MGT 605: Construction Budgeting, Estimating & Bidding

Pricing Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingKearsarge Building Company and every quantity, wage and price are fictional and illustrative.
2

Hours, Yards and a Rented Telehandler: Pricing Kearsarge's Self-Performed Concrete for the Laconia Wing

Introduction

Kearsarge Building Company self-performs concrete and rough carpentry and subcontracts the other trades. On the Laconia shop wing the district is bidding, the concrete package is Kearsarge's own risk: if its crews take longer or its material costs rise, no subcontractor absorbs the difference. This paper prices that package from the sixty percent design development drawings. It sets out the quantities, prices labor from productivity rates and a burdened wage, prices materials and equipment and adjusts for the overtime the foundation schedule will require.

What this page is doingSets out the scope and purpose.
3

Scope and Quantities

The new wing sits on spread and continuous footings with four-foot frost walls. The ground floor is a slab on grade, six inches on average because the automotive and welding bays are thickened to eight; the second floor is a concrete slab on composite metal deck. A small slab infill is needed where the renovation removes old floor trenches. Quantities were taken off from the foundation and framing plans.

Concrete quantities

ElementQuantityUnit
Spread and continuous footings410cubic yards
Frost walls380cubic yards
Frost wall forms (contact area)11,400square feet
Slab on grade, new and infill22,900square feet (424 cubic yards)
Slab on metal deck20,500square feet (285 cubic yards)
Total concrete1,499cubic yards
What this page is doingLists the work before any price.
4

Labor Hours

Kearsarge's job cost records from its last eight concrete packages give the productivity rates below. They are averages for crews of six to eight working in normal conditions.

Labor hours by activity

ActivityQuantityLabor hours per unitHours
Footings, form, place and strip410 cubic yards2.4984
Frost walls, forming11,400 square feet of contact area0.121,368
Frost walls, placing380 cubic yards0.9342
Slab on grade, place and finish22,900 square feet0.028641
Slab on deck, place and finish20,500 square feet0.032656
Total3,991
What this page is doingTurns quantities into hours.
5

Wage and Burden

The crew mixes carpenters, laborers and cement masons. Their blended base wage on Kearsarge's open-shop payroll is $36.20 an hour; the project has no federal funding, so federal prevailing wage rules do not apply. Burden adds 41 percent: employer payroll taxes about 9 percent, workers' compensation for concrete work about 12 percent and health, retirement and paid leave about 20 percent. The burdened rate is $51.04, and 3,991 hours cost $203,701.

What this page is doingBuilds the hourly cost.
6

Materials

Two local ready-mix suppliers quoted 4,000-psi concrete; the lower quote, $198 per cubic yard, holds until December 2026 with a fuel surcharge clause. With five percent waste, 1,499 cubic yards cost $311,642. Reinforcing steel, about 68 tons, is priced at $1,650 a ton furnished and $780 a ton to place by a rebar installer, or $165,240. Form ply, ties and accessories cost about $3.10 per square foot of contact area, or $35,340. Vapor barrier, under-slab insulation, curing compound and joint filler add $48,000.

Material cost

ItemBasisCost
Ready-mix concrete1,499 cubic yards plus 5 percent at $198$311,642
Reinforcing, furnished and placed68 tons at $2,430$165,240
Forming materials11,400 square feet at $3.10$35,340
Slab materialsAllowance from supplier lists$48,000
Total$560,222
What this page is doingPrices what the crews install.
7

Equipment

A concrete pump is needed for nine pour days at $2,400 a day, or $21,600. The crews also need a telehandler for about three months. Kearsarge owns two, and its owning cost, covering depreciation, interest, insurance and maintenance, is about $3,950 a month, well below the $5,800 monthly rental rate. Both owned machines, however, are committed to a hospital job in Concord through the fall, and moving one would delay that work. The estimate therefore carries a rental at $17,400, and notes that if the hospital job finishes early, $5,550 could be saved. Winter protection, because footings will be poured in March, adds heaters, blankets and enclosures at $38,000.

What this page is doingDecides between owning and renting.
8

Job Conditions

Standard rates assume normal hours. The district's schedule requires the foundations to be complete in six weeks so steel erection can begin in May, which means fifty-hour weeks for the footing and wall crews. Hanna et al. (2005), modeling projects from specialty contractors, found that the productivity lost to overtime rises with both the hours worked each week and the number of weeks the schedule lasts. An earlier review by Thomas (1992) reached a similar conclusion: scheduled overtime lowers output per hour, and the loss compounds as fatigue builds. For a six-week stretch at fifty hours, this estimate assumes ten percent lower productivity on the 2,694 foundation hours, adding $13,750, plus premium pay at half the base wage on the overtime fifth of those hours, adding $9,752.

Thomas and Horman (2006) argued that crews perform best when the work in front of them is steady and matched to the crew's size, and that interruptions explain more poor productivity than effort does. The foundation schedule should therefore keep forms, rebar and inspections ahead of the crews so that the long weeks are not also broken weeks, which would compound the loss.

What this page is doingAdjusts the standard rates.
9

Summary

Self-performed concrete package

CategoryCost
Labor (3,991 hours at $51.04)$203,701
Materials$560,222
Pump and telehandler$39,000
Winter protection$38,000
Overtime productivity loss$13,750
Overtime premium$9,752
Total$864,425
What this page is doingGives the package total.
10

Checking the Rates

Company averages can hide drift, so the hours were checked two ways. First, the cost per cubic yard for labor, about $136, sits between the $121 and $149 that Kearsarge recorded on its two most recent school foundations, which had simpler walls and milder weather respectively. Second, the slab rates were compared with the finishing foreman's own count of how many square feet his crew finishes in a good day; his figure implies about 0.03 hours per square foot, close to the rates used. The wall forming rate is the least certain, because the frost walls step down twice along the north side to follow grade, which slows form setting. A five percent cushion on those 1,368 hours, about $3,500, would be reasonable if the superintendent agrees after walking the site.

What this page is doingTests the hours against a second source.
11

Risks to the Price

The largest exposures are labor hours, which carry no subcontractor's guarantee, and the ready-mix fuel surcharge. A ten percent miss on labor hours costs about $20,000. Rock in the excavation, not shown in the borings, would change the footing work entirely and should be excluded or priced as a unit rate in the bid.

What this page is doingNames what could move it.
12

Conclusion

Kearsarge can carry $864,400 for its own concrete with confidence in the material and equipment prices, most of which are quotes, and with moderate confidence in labor. Keeping the foundation work well supplied during the fifty-hour weeks is the best protection the superintendent has for that labor figure.

What this page is doingStates the result and its basis.
13

References

Hanna, A. S., Taylor, C. S., & Sullivan, K. T. (2005). Impact of extended overtime on construction labor productivity. Journal of Construction Engineering and Management, 131(6), 734-739. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:6(734)

Thomas, H. R. (1992). Effects of scheduled overtime on labor productivity. Journal of Construction Engineering and Management, 118(1), 60-76. https://doi.org/10.1061/(ASCE)0733-9364(1992)118:1(60)

Thomas, H. R., & Horman, M. J. (2006). Fundamental principles of workforce management. Journal of Construction Engineering and Management, 132(1), 97-104. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:1(97)

What the MGT 605 Module 4 instructions ask for

The pricing assignment in MGT 605 normally asks you to develop the cost of a defined scope of work by pricing its labor, equipment and materials separately. You may be given quantities or asked to take them off from drawings, and you are expected to apply productivity rates, wage rates with burden, equipment costs and current material prices. A strong paper explains where each rate comes from, shows the arithmetic in tables that add up, separates the wage from the burden that sits on top of it and makes the choice between owned and rented equipment explicit. It also asks what conditions on this particular job, such as weather or schedule pressure, could make the standard rates wrong.

How this MGT 605 Module 4 pricing assignment example is built

In the sample, Kearsarge prices its own concrete crews' work on the 41,000-square-foot Laconia shop wing. About 1,500 cubic yards of footings, frost walls, slab on grade and slab on deck need 3,991 labor hours at unit rates from Kearsarge's job records. A blended base wage of $36.20 carries 41 percent burden for $51.04 an hour, so labor costs $203,701. Ready-mix, reinforcing, forms and slab materials add $560,222 and equipment and winter protection $77,000. Six weeks of fifty-hour foundation work cost another $23,502 in premium time and lost productivity, using Hanna and colleagues and Thomas on overtime and Thomas and Horman on crew planning. The total is $864,425.

Where the MGT 605 Module 4 rubric puts the points

Grading for this pricing assignment usually covers the completeness of the scope, the quality and sources of productivity and price data, correct arithmetic, the treatment of labor burden, equipment and job conditions and APA writing. The strongest papers price every element of the scope, show quantities times rates in tables a reader can recompute and adjust standard rates for the specific job with evidence. Instructors deduct for lump sums with no breakdown, for wages used without burden, for equipment priced at purchase cost rather than per period of use and for arithmetic errors in totals. A short note on which prices are firm quotes and which are budget figures shows estimating judgment. Discussing what could push labor hours up is a further mark of quality.

MGT 605 Module 4 help: the mistakes that cost points

List the scope as quantities with units before pricing anything. Then price labor as hours, not dollars: multiply each quantity by a productivity rate, add up the hours and only then multiply by a burdened rate. Burden should include payroll taxes, workers' compensation, health and retirement benefits and paid time off. For materials, add waste and say whether the price is a quote. For equipment, compare the cost of owning per month with renting, and remember that owned equipment committed to another job is not free. Finally, look for conditions that change productivity, such as cold weather or long weeks. Show a total that a reader can check from your tables alone.

Get MGT 605 Module 4 written to your instructions

Upload the MGT 605 Module 4 instructions and the scope you need priced. We take off quantities, apply productivity rates, burden the labor, price materials and equipment and allow for schedule pressure, with every line traceable. A first pricing paper is free, and the line-by-line draft follows in roughly forty-eight hours. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 605 papers and related MS in Management samples

MGT 605 Module 4 questions, answered

Where can I find a free MGT 605 Module 4 Pricing Assignment sample?

A full MGT 605 Module 4 pricing paper appears on this page, building the labor, equipment and material cost of self-performed concrete for a school wing.

How do you price labor in a construction estimate?

Multiply each quantity by a productivity rate to get hours, total the hours and multiply by a wage rate that includes payroll taxes, insurance and benefits.

What is labor burden in construction?

The cost an employer pays on top of the base wage, including payroll taxes, workers' compensation insurance, health and retirement benefits and paid time off.

Does overtime reduce construction productivity?

Studies of construction crews report that sustained scheduled overtime lowers output per hour, and the loss grows as long weeks continue.

Should a contractor rent or own construction equipment?

Owning is cheaper for equipment used most months of the year; renting suits short or irregular needs, or when owned machines are committed to other jobs.