MGT 605 Module 8 Milestone Two Example

Reviewed by Portia Lambrick, MBA

This MGT 605 Module 8 Milestone Two sample presents a definitive estimate built from subcontractor bids and the strategy for turning it into a bid price. SNHU MGT 605 (MGT-605) uses Milestone Two to have MS in Management students move from a budget to a firm estimate and a pricing decision. Kearsarge Building Company, a composite New Hampshire general contractor, levels 38 trade bids for the Laconia technical center wing, adds general conditions, bond, insurance, contingency and home office overhead, sets a markup from its competitive analysis, prices three alternates and a unit price and plans how the final bid-day review will protect the number from an estimating miss.

CourseMGT 605 Construction Budgeting, Estimating & Bidding
ModuleModule 8
Paper typegraduate milestone presenting a definitive estimate, alternates and a bid strategy
LengthAbout 1,050 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 605 Module 8

1

Thirty-Eight Numbers to One Price: Kearsarge's Definitive Estimate and Bid Strategy for the Laconia Technical Center

[Student Name]

Southern New Hampshire University

MGT 605: Construction Budgeting, Estimating & Bidding

Milestone Two: Definitive Estimate and Bid Strategy

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingKearsarge Building Company, its subcontractors and every price are fictional and illustrative.
2

Thirty-Eight Numbers to One Price: Kearsarge's Definitive Estimate and Bid Strategy for the Laconia Technical Center

Introduction

Sealed bids for the Laconia project are due to the Winnipesaukee Regional School District at two o'clock on May 21, 2026. Milestone One set Kearsarge Building Company's budget at $24.90 million on sixty percent drawings. Since then the drawings have reached one hundred percent, and Kearsarge has received 38 subcontractor and supplier numbers across twelve trades. This milestone presents the definitive estimate that results, the markup chosen from the competitive analysis, the prices for three add alternates and a unit price and the plan for the final review on bid day.

What this page is doingExplains what changed since the budget.
3

Leveling the Trade Bids

Subcontractor bids rarely cover the same scope. For each trade, Kearsarge's estimator listed what each bidder included and excluded, then added the estimated cost of missing items before comparing. The mechanical trade shows why this matters. Three HVAC bids arrived at $3.88 million, $4.05 million and $4.41 million. The lowest excluded the welding shop's makeup air unit and its controls, worth about $300,000 by Kearsarge's takeoff, so its leveled price was $4.18 million, slightly above the second bid's $4.05 million, which in turn excluded the vehicle exhaust reels. Leveled, the two were within $5,000; Kearsarge carried $4.18 million and chose the second bidder for its complete scope.

What this page is doingShows how numbers were made comparable.
4

Definitive Estimate

From direct cost to bid

Trade packageBids receivedCarriedChange from budget
Site, utilities and paving4$1,338,000plus 3.7 percent
Concrete, self-performedSupplier quotes$864,000none
Masonry3$1,706,000plus 4.0 percent
Structural steel and deck3$2,622,000plus 4.5 percent
Carpentry, doors and specialties3$1,072,000plus 4.1 percent
Roofing, walls and windows4$2,131,000plus 4.0 percent
Interior finishes4$2,384,000plus 6.0 percent
Casework and equipment rough-in3$896,000plus 4.2 percent
Fire protection3$512,000plus 3.4 percent
Plumbing and compressed air3$1,530,000plus 4.8 percent
HVAC, exhaust and dust collection3$4,182,000plus 13.0 percent
Electrical and low voltage3$3,134,000plus 8.0 percent
Direct cost38 numbers in all$22,371,000plus 6.3 percent
LineBasisAmount
Direct costLeveled trade bids$22,371,000
General conditionsSixteen months$1,180,000
Bond, builder's risk and liability1.6 percent$376,816
Bid contingency1.5 percent$358,917
Cost before overhead$24,286,733
Home office overhead2.0 percent$485,735
Total cost$24,772,468
Markup3.6 percent$891,809
Base bid, rounded$25,664,000

Most trades rose about four percent from March prices, close to the escalation allowance. The two outliers are HVAC and electrical, whose square-foot allowances at design development underestimated the shop systems once they were drawn. The design contingency has been replaced by firm numbers, leaving a 1.5 percent bid contingency for coordination gaps between trades that no single bid covers.

What this page is doingBuilds the cost in layers.
5

Setting the Markup

The Module 7 analysis, rerun on the final cost, still puts expected profit highest between 3.5 and 4.0 percent. Two facts favor the lower end: Suncook Valley Construction, the steadiest rival, is lightly booked, and the base bid at 3.6 percent, $25,664,000, falls under the district's $25.9 million construction budget, which matters because a base bid over budget invites rejection of all bids. One fact argues against going lower: the winner's curse. Thaler (1988) reviewed evidence that winners of common-value auctions often lose money because the winning bid tends to come from the most optimistic estimate. In a classroom experiment by Bazerman and Samuelson (1983), students bid for jars of coins; their average estimate of the jar's value was below its true value, yet the winning bids were above it on average, so winners lost money. A markup below 3.5 percent would leave Kearsarge exposed to exactly that outcome.

What this page is doingLinks the price to the competitive analysis.
6

Scope Risks Still in the Number

Three gaps remain after leveling. The steel erector and the roofing contractor each assume the other provides the curb framing for rooftop exhaust fans, worth about $40,000. The electrical bids carry welding receptacles as shown, but the shop equipment list issued in an addendum adds four machines whose power needs are not yet confirmed. And the renovation abatement is priced from the district's survey, which sampled only accessible areas. The 1.5 percent bid contingency, about $359,000, is sized to cover these together with ordinary coordination items, and the estimator has listed each against it so that, if the contingency is spent, the reasons are already on record.

What this page is doingNames what the contingency must cover.
7

Alternates and Unit Price

Alternates and unit price

ItemDescriptionPrice
Add alternate 1Culinary lab fit-out with hoods and walk-in cooler$412,000
Add alternate 2Rooftop solar array on the shop wing, 140 kilowatts$588,000
Add alternate 3Renovation of the remaining 2,500 square feet of the 1972 building$596,000
Unit priceLedge removal, per cubic yard, beyond the first 50 included in the base bid$185

With all three alternates the bid would total $27.26 million, so the district will likely award the base bid and add alternates only as its budget allows. Each alternate carries the same 3.6 percent markup, so Kearsarge is indifferent to which the district chooses.

What this page is doingPrices what the bid form requires.
8

Bid-Day Plan

Laryea and Hughes (2008), who observed contractors' estimating and pricing meetings in the UK, found that allowances for risk were often negotiated down at the final review as managers searched for a winning price. Kearsarge will guard against that with three rules. First, late subcontractor numbers may replace carried figures only after the estimator confirms their scope against the leveling sheet; a number more than 15 percent under the others is presumed to be missing scope. Second, the markup may move only within 3.5 to 4.0 percent, and only the president may move it. Third, the bid contingency is not available for cutting. The bid form will be signed at 1:40 p.m. and delivered by the project manager in person.

What this page is doingDecides in advance how late changes are handled.
9

Conclusion

Kearsarge's definitive cost for the Laconia wing is $24.77 million with overhead. Before overhead it is $24.29 million, about 2.5 percent under the design development budget: trade prices rose 6.3 percent, led by the mechanical and electrical systems that were underestimated before they were drawn, but the contingency and escalation allowances that anticipated such increases have now given way to firm numbers. A base bid of $25,664,000 at a 3.6 percent markup sits under the owner's budget and near the profit-maximizing range of two bidding models, and the bid-day rules are meant to keep the risk allowance in the price when the pressure to win is highest.

What this page is doingSummarizes the estimate and strategy.
10

References

Bazerman, M. H., & Samuelson, W. F. (1983). I won the auction but don't want the prize. Journal of Conflict Resolution, 27(4), 618-634. https://doi.org/10.1177/0022002783027004003

Laryea, S., & Hughes, W. (2008). How contractors price risk in bids: Theory and practice. Construction Management and Economics, 26(9), 911-924. https://doi.org/10.1080/01446190802317718

Thaler, R. H. (1988). Anomalies: The winner's curse. Journal of Economic Perspectives, 2(1), 191-202. https://doi.org/10.1257/jep.2.1.191

What the MGT 605 Module 8 instructions ask for

Milestone Two in MGT 605 generally asks you to develop the detailed estimate for your project and explain the bid strategy built on it, including pricing for labor, materials and equipment, subcontractor costs, overhead, profit and the approach to competition. Expect to show how the earlier budget changed and why. A strong milestone presents a definitive estimate that reconciles with its parts, explains how subcontractor bids were compared for scope, separates contingency, overhead and profit, sets a markup with evidence from the competitive analysis and prices any alternates or unit prices the bid form requires. It also says how the firm will make last-minute decisions on bid day, because that is where good estimates are often spoiled.

How this MGT 605 Module 8 milestone two example is built

The sample builds Kearsarge's definitive estimate for the Laconia wing on bid documents. Thirty-eight subcontractor and supplier numbers across twelve trades are leveled for scope, giving direct cost of $22.37 million; mechanical bids came in 13 percent over the budget line. General conditions, bond and insurance, a 1.5 percent bid contingency and a two percent home office charge bring the cost to $24.77 million. A 3.6 percent markup from the Module 7 analysis sets the base bid at $25,664,000. Three add alternates and a ledge unit price are priced. The paper uses Thaler's review and Bazerman and Samuelson's coin-jar auctions on the winner's curse, and Laryea and Hughes on bid-day reviews.

Where the MGT 605 Module 8 rubric puts the points

Milestone Two rubrics usually weigh the completeness and accuracy of the estimate, the treatment of subcontractor pricing, the separation of contingency, overhead and profit, the bid strategy and its link to the competitive analysis and APA writing. Top milestones show totals a reader can rebuild, explain how scope gaps between bids were closed, compare the estimate with the earlier budget line by line and state the bid with its alternates in the owner's format. Points drop when the lowest number in each trade is used without leveling, when markup appears with no reasoning, when alternates are left unpriced and when the paper does not say how the bid-day review will be run. Clear tables and an honest note on the riskiest numbers add credit.

MGT 605 Module 8 help: the mistakes that cost points

Collect every subcontractor and supplier number you have and level them: list what each includes and excludes, add the cost of anything missing and only then compare. Carry the leveled low number for each trade, unless a bidder's scope or reliability is doubtful. Build the cost in layers: direct work, general conditions, bond and insurance, any bid contingency, home office overhead. Then add the markup your competitive analysis supports. Price every alternate and unit price the bid form asks for. Compare the result with your earlier budget and explain the differences. Finally, decide in advance who may change the number on bid day and by how much, and write that rule down.

Get MGT 605 Module 8 written to your instructions

Upload the MGT 605 Milestone Two guidelines with your estimate so far. We level the trade bids, build the cost to a firm total, set the markup from evidence, price the alternates and write the bid-day plan that keeps risk in the number. A first Milestone Two is free and lands in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 605 papers and related MS in Management samples

MGT 605 Module 8 questions, answered

Where can I find a free MGT 605 Module 8 Milestone Two sample?

The full MGT 605 Module 8 Milestone Two is posted here, building a definitive estimate and bid for a technical center wing from 38 subcontractor numbers.

What is a definitive construction estimate?

An estimate built from complete or nearly complete documents, using measured quantities and firm prices from subcontractors and suppliers, accurate enough to bid.

What does it mean to level subcontractor bids?

To compare trade bids on the same scope by listing what each includes and excludes and adding the cost of missing items, so the comparison is fair.

What are add alternates in a construction bid?

Separately priced pieces of work the owner may add to the base contract, letting the owner award as much scope as its budget allows.

How do contractors guard against the winner's curse?

By checking unusually low trade numbers for missing scope, keeping a modest contingency and avoiding a markup at the very bottom of the range the analysis supports.