MGT 605 Module 3 Discussion Example

Reviewed by Portia Lambrick, MBA

This MGT 605 Module 3 Discussion sample asks how rough order of magnitude, conceptual and definitive estimates differ, and how much contingency each stage of design deserves. SNHU MGT 605 (MGT-605) uses this point in the MS in Management construction sequence to move from square-foot pricing toward quantity takeoff. The post follows Kearsarge Building Company, a composite New Hampshire general contractor, as design development drawings for a career and technical center arrive and its estimate drops by $1.7 million after the owner trims scope. It argues for reference class forecasting when setting contingency and invites classmates to say when they would switch methods.

CourseMGT 605 Construction Budgeting, Estimating & Bidding
ModuleModule 3
Paper typegraduate discussion post on how estimate types and contingency change as design advances
LengthAbout 400 words, 3 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 605 Module 3

1

Module Three Discussion

Sixty Percent Drawings and a Smaller Number

Last module my composite firm, Kearsarge Building Company, priced the Laconia career and technical center at $26.6 million from schematic drawings. This week the Winnipesaukee Regional School District released sixty percent design development drawings, and two things changed. The district dropped a 2,200-square-foot shop mezzanine and cut the renovation of the 1972 building from 12,000 to 9,500 square feet. And the drawings now show foundation plans, steel framing and wall types, so Kearsarge can count things instead of scaling them.

What this page is doingThe drawings came in.
2

The new estimate is $24.9 million. About $1.6 million of the drop comes from the scope the district removed. Concrete, structural steel and masonry are now priced from measured quantities, and together they came in about $0.3 million under the square-foot allowance. Pulling the other way, the outline specification now calls for a larger dust collector and makeup air in the welding shop, which adds about $1.1 million. Mechanical and electrical work is still priced by the square foot, because those ventilation designs are not drawn yet. Contingency fell from ten percent to six, and escalation was recomputed for a shorter wait until construction. So this is a hybrid: part definitive, part conceptual.

What this page is doingWhat the new number is made of.
3

Cantarelli et al. (2010) sorted the explanations researchers give for overruns into technical, economic, psychological and political families. Only the first is solved by better drawings. Flyvbjerg (2006) argued that the way to correct for the other three is to set forecasts from the outcomes of a reference class of similar past projects, rather than from planners' confidence. Trost and Oberlender (2003) found that the maturity of the design behind an estimate was among the strongest predictors of its accuracy. Put together, contingency should shrink as design matures, but not to zero while a third of the cost is still priced by the square foot.

For Kearsarge, I would carry six percent on the measured trades and closer to twelve on the mechanical and electrical work, which blends to roughly the six percent now in the estimate only because the measured share is so large. If the mechanical drawings arrive late, I would rather show that higher figure to our leadership than discover it on bid day.

What this page is doingHow much contingency is honest?
4

At sixty percent drawings, with mechanical systems still undrawn, what contingency would you carry, and would you set it differently for the mechanical work than for the measured trades?

What this page is doingOver to you.
5

References

Cantarelli, C. C., Flyvbjerg, B., Molin, E. J. E., & van Wee, B. (2010). Cost overruns in large-scale transportation infrastructure projects: Explanations and their theoretical embeddedness. European Journal of Transport and Infrastructure Research, 10(1), 5-18. https://doi.org/10.18757/ejtir.2010.10.1.2864

Flyvbjerg, B. (2006). From Nobel prize to project management: Getting risks right. Project Management Journal, 37(3), 5-15. https://doi.org/10.1177/875697280603700302

Trost, S. M., & Oberlender, G. D. (2003). Predicting accuracy of early cost estimates using factor analysis and multivariate regression. Journal of Construction Engineering and Management, 129(2), 198-204. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:2(198)

What the MGT 605 Module 3 instructions ask for

The third MGT 605 discussion typically asks you to compare estimate types, such as rough order of magnitude, conceptual or budget and definitive or detailed estimates, and to explain how accuracy and contingency change as a project moves through design. Some prompts also ask when each type is used and by whom. A good post ties each type to the information available when it is prepared, explains what method fits that information and shows with numbers how a real or composite estimate changed between stages. It treats contingency as a measure of what is still unknown, not as padding, and uses research on forecast error to say how large it should be at each point in design.

How this MGT 605 Module 3 discussion example is built

In this sample, Kearsarge's schematic estimate of $26.6 million for the Laconia technical center is revisited when sixty percent design development drawings arrive. The school district has dropped a 2,200-square-foot shop mezzanine and narrowed the renovation to 9,500 square feet, so the new figure is $24.9 million. The estimator has now switched to quantity takeoff for concrete, steel and masonry but still prices mechanical systems by the square foot. The post argues that design contingency should fall from ten percent to about six, not to zero, and supports that with Flyvbjerg's case for reference class forecasting, Cantarelli and colleagues' four families of explanation for overruns and Trost and Oberlender on estimate accuracy.

Where the MGT 605 Module 3 rubric puts the points

Discussion posts on estimate types are generally graded on accurate definitions, a clear link between design stage and method, sensible treatment of contingency, use of research and replies that add to the conversation. The better posts show a real number changing between two stages and explain each part of the change. Credit drops when estimate types are defined from a glossary with no example, when contingency is treated as a fixed percentage regardless of design maturity, when sources are cited without their findings and when replies only praise. Readers also reward posts that admit which parts of the estimate are still rough, because mixed methods are normal on real projects. A brief sentence on who uses each estimate, owner or contractor, adds useful context.

MGT 605 Module 3 help: the mistakes that cost points

Describe one project at two design stages and give the estimate at each. Say what information the estimator had both times, and which method that information allowed. Explain the change in parts: scope removed, quantities now measured, prices updated. Then decide how much contingency belongs at the later stage and justify it with evidence about how similar estimates have performed, rather than a rule of thumb. Be honest that some systems are still priced roughly. Keep definitions short; the example carries the post. In replies, ask peers what their contingency would be at the same stage and why, because that comparison is where most of the learning in this discussion happens.

Get MGT 605 Module 3 written to your instructions

Share the MGT 605 Module 3 question and the design stage of the project you are discussing. We explain which estimate type fits that stage, how much contingency it should carry and why, citing studies of forecast error. A first discussion post is free, and a draft is usually ready in two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 605 papers and related MS in Management samples

MGT 605 Module 3 questions, answered

Where can I find a free MGT 605 Module 3 Discussion sample?

This page holds the whole MGT 605 Module 3 post, following a technical center estimate from schematic to design development drawings.

What is a rough order of magnitude estimate?

A very early estimate made from little more than the type and size of a project, used to decide whether the project is worth pursuing, with a wide range of possible error.

How does a definitive estimate differ from a conceptual one?

A definitive estimate is built from measured quantities and current prices on nearly complete drawings, while a conceptual estimate scales costs from similar past projects.

How much contingency should a construction estimate carry?

It should match what remains unknown: larger at schematic design, smaller once quantities can be measured, and set from how similar estimates have actually performed.

What is reference class forecasting?

A method that sets a forecast from the actual outcomes of a group of similar past projects, rather than from the planners' view of their own project.