MGT 605 Module 10 Final Project Example

Reviewed by Portia Lambrick, MBA

This MGT 605 Module 10 Final Project sample presents a complete construction bid proposal: the budget history, the definitive estimate, the price and the reasoning behind it. SNHU MGT 605 (MGT-605) closes its MS in Management construction course by asking for a budget, estimate and bid package a real owner could evaluate. Kearsarge Building Company, a composite New Hampshire general contractor, submits its proposal for a new shop and lab wing at a Laconia career and technical center. The paper traces four successive cost figures, states the base bid, alternates and unit price, sets out the schedule and exclusions and explains how competition and risk shaped the markup.

CourseMGT 605 Construction Budgeting, Estimating & Bidding
ModuleModule 10
Paper typegraduate final project presenting a complete construction budget, estimate and bid proposal
LengthAbout 1,160 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for MGT 605 Module 10

1

Base Bid $25,664,000: Kearsarge Building Company's Proposal and Estimating Report to the Winnipesaukee Regional School District

[Student Name]

Southern New Hampshire University

MGT 605: Construction Budgeting, Estimating & Bidding

Final Project: Bid Proposal

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingKearsarge Building Company, the Winnipesaukee Regional School District and every figure are fictional and illustrative.
2

Base Bid $25,664,000: Kearsarge Building Company's Proposal and Estimating Report to the Winnipesaukee Regional School District

Summary for the Building Committee

Kearsarge Building Company proposes to build the Lakes Region Career and Technical Center shop and lab wing and the renovation of the 1972 classroom building for a base bid of $25,664,000, within the district's construction budget of $25.9 million. We also offer three add alternates and a unit price for ledge. We will complete the work in sixteen months from a July 2026 start while keeping the existing school open and safe, and our price rests on firm subcontractor numbers for every trade and our own crews for concrete. This proposal explains how we arrived at the price, what it includes and what it assumes.

What this page is doingGives the owner the essentials first.
3

The Project as We Understand It

The new two-story wing, about 38,800 square feet, houses shops and labs for automotive technology, welding, building trades, culinary arts and health science. Its demanding systems are welding exhaust, a dust collection system for the wood shop, vehicle exhaust extraction, compressed air to every shop and heavy power for machine tools. The renovation covers 9,500 square feet of the 1972 building, where asbestos in old floor tile and pipe wrap comes out before lights, air systems and finishes are replaced. Site work relocates the bus loop, adds 90 parking spaces and brings new water and gas services. Students and staff will occupy the rest of the campus throughout construction.

What this page is doingShows the contractor read the documents.
4

How the Price Developed

Four cost figures, January to May 2026

Date and basisFigureWhat changed
March 2025 bond vote, architect's sketch$23.4 million construction budgetSet before design; held through two years of price increases
January 2026, schematic design$26.6 million point estimate, range $22.6 to $31.9 millionSquare-foot pricing from five adjusted past schools, 10 percent design contingency, 14 months of escalation
March 2026, sixty percent drawings$24.9 million project budgetMezzanine removed and renovation reduced; measured quantities for six trades; contingency cut to 6 percent
May 2026, bid documents$24.77 million total cost38 leveled trade numbers; mechanical and electrical bids above their allowances; 1.5 percent bid contingency; 2 percent home office overhead

The early estimate warned that the original budget would not hold, and the district responded by trimming scope and raising its construction budget to $25.9 million. Each later figure replaced a layer of assumption with evidence. Trost and Oberlender (2003) found that how far design had progressed was among the strongest predictors of an early estimate's accuracy; the narrowing from a range of more than $9 million in January to firm trade prices in May is that relationship at work.

What this page is doingTraces every figure from first to last.
5

Bid Form

Bid summary

AmountBid form line
$25,664,000Base bid, all work in the bid documents
$412,000Alternate 1: culinary arts kitchen, exhaust hoods and a walk-in cooler included
$588,000Alternate 2: solar panels on the shop roof, 140 kilowatts
$596,000Alternate 3: last 2,500 square feet of 1972 classrooms brought up to new standards
$185 per cubic yardLedge taken out after the 50 cubic yards already carried
$27,260,000Base bid plus every alternate
What this page is doingStates the price in the owner's format.
6

Cost Behind the Base Bid

Of the base bid, $22.37 million is trade work, $1.18 million is general conditions for sixteen months of supervision and site operations, about $0.38 million covers the payment and performance bond and insurance, $0.36 million is a bid contingency for coordination between trades and $0.49 million is home office overhead. The remaining $0.89 million, 3.6 percent of cost, is Kearsarge's profit. The largest single trade is HVAC, exhaust and dust collection at $4.18 million, followed by electrical at $3.13 million and structural steel at $2.62 million. Kearsarge's own concrete crews will place about 1,500 cubic yards, priced at $864,400.

What this page is doingLets the owner see the structure of the price.
7

Schedule

Site work and the bus loop relocation begin in July 2026, timed so the new loop opens before school starts. Foundations follow in a six-week stretch of fifty-hour weeks so that steel can rise in the fall and the building can be closed in before deep winter. Interior work and mechanical rough-in run through the winter and spring of 2027. The renovation is done in two phases during school vacations and evenings, with abatement in the summer of 2026. Commissioning of the shop exhaust and dust collection takes six weeks in August and September 2027, and substantial completion is set for October 2027.

What this page is doingShows how sixteen months will be used.
8

Clarifications and Exclusions

The price includes the first 50 cubic yards of ledge removal; additional ledge will be paid at the unit price. Shop machinery, kitchen equipment other than that in alternate 1, furniture and technology devices are furnished by the district; Kearsarge installs the utility connections shown on the drawings. Abatement is priced from the district's hazardous materials survey; materials not identified in the survey are excluded and would be handled by change order. The price assumes the district's builder's risk requirements as written and weekday site hours running from half past six in the morning until five in the afternoon, with evening work limited to the renovation phases listed above.

What this page is doingStates what the price assumes.
9

Internal Rationale: Markup and Risk

Kearsarge expected three rivals to bid. Treating each rival's past bids as a ratio of our own cost estimate, as Friedman (1956) proposed, expected profit was highest at markups between 3.5 and 4.0 percent, and a second model placed it slightly higher. We chose 3.6 percent because the steadiest rival is short of work, because a base bid above the district's budget would invite rejection of all bids and because a lower markup would leave little margin if our own estimate is the one that missed.

Two risks remain in the price. The first is labor productivity on the foundations, where the schedule demands long weeks; Hanna et al. (2005) showed that output per hour falls as overtime extends, and the estimate includes a ten percent productivity allowance and premium pay for that period. The second is coordination between trades, covered by the bid contingency. Laryea and Hughes (2008) found that contractors often trimmed risk allowances in the final pricing meeting under pressure to win. Our bid-day rules prevented that: the contingency was not available for cutting, and the markup could move only within the agreed range.

What this page is doingExplains the price to Kearsarge's leadership.
10

Lessons From the Estimate

Our design development budget underestimated the shop mechanical and electrical systems by about ten percent, because square-foot rates from ordinary schools do not capture welding exhaust and machine power. For future technical school bids, Kearsarge will build a separate rate for shop space from this project's final costs. We will also record each rival's bid on this project as a ratio of our cost, so the next competitive analysis has one more observation.

What this page is doingRecords what Kearsarge would do differently.
11

Conclusion

Kearsarge's base bid of $25,664,000 rests on firm prices for every trade, a schedule built around an occupied school and a markup chosen with evidence rather than habit. The district can award the base bid within its budget and add alternates as funds allow, with each priced on the same terms. We would welcome the chance to discuss any part of this proposal with the building committee.

What this page is doingCloses the proposal.
12

References

Friedman, L. (1956). A competitive-bidding strategy. Operations Research, 4(1), 104-112. https://doi.org/10.1287/opre.4.1.104

Hanna, A. S., Taylor, C. S., & Sullivan, K. T. (2005). Impact of extended overtime on construction labor productivity. Journal of Construction Engineering and Management, 131(6), 734-739. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:6(734)

Laryea, S., & Hughes, W. (2008). How contractors price risk in bids: Theory and practice. Construction Management and Economics, 26(9), 911-924. https://doi.org/10.1080/01446190802317718

Trost, S. M., & Oberlender, G. D. (2003). Predicting accuracy of early cost estimates using factor analysis and multivariate regression. Journal of Construction Engineering and Management, 129(2), 198-204. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:2(198)

What the MGT 605 Module 10 instructions ask for

The MGT 605 final project typically asks you to produce a complete budget, estimate and bid proposal for a construction project, building on your milestones and the feedback you received. Expect to present the project, its budget and estimate with their assumptions, pricing of labor, materials, equipment and subcontracts, the bid price with its components and the strategy behind it, including competitive analysis. A strong final reads as one document an owner and a contractor's leadership could both use: it reconciles every figure, explains how the numbers evolved, separates what goes to the owner from internal reasoning and states clarifications and exclusions clearly. Rework milestone text instead of copying it, because the final is read against the comments you were given.

How this MGT 605 Module 10 final project example is built

Kearsarge's final project is its proposal for the Laconia technical center. It opens with a summary for the district's building committee, then traces the cost from the district's $23.4 million budget through a $26.6 million schematic estimate and a $24.9 million design development budget to a $24.77 million definitive cost. The base bid is $25,664,000, with three add alternates and a $185 per cubic yard ledge price. A sixteen-month schedule protects the occupied school, and clarifications name what the price assumes. An internal section explains the 3.6 percent markup with Friedman's model and Laryea and Hughes, the estimate's accuracy with Trost and Oberlender and the overtime allowance with Hanna and colleagues.

Where the MGT 605 Module 10 rubric puts the points

Instructors marking this final tend to weigh how completely and accurately the paper presents the budget, the estimate, the bid price and its components, the bid strategy and competitive reasoning, the integration of earlier feedback and the quality of writing and APA style. Top papers reconcile every total, explain each change between estimates, show the bid in the owner's format with alternates and unit prices and justify the markup with evidence. Marks drop for figures that disagree between sections, for milestone text repeated without revision, for exclusions that are vague and for a markup with no rationale. Graders also reward a proposal whose owner-facing parts would make sense to a school board member without a construction background.

MGT 605 Module 10 help: the mistakes that cost points

Start from your corrected milestones and build one master table of figures; every number in the final should come from it. Write two kinds of content: what the owner sees, such as the summary, price, alternates, schedule and exclusions, and what your leadership needs, such as the markup reasoning and the risks still in the number. Explain how the estimate changed from the first figure to the last, because that history is the best evidence the price is sound. Make exclusions specific; an exclusion like 'unforeseen conditions' tells the owner nothing. Proofread the totals last. A final project that adds up and reads plainly usually outscores a longer one that does not.

Get MGT 605 Module 10 written to your instructions

Send your MGT 605 final project directions, both milestones and the comments your instructor left on them. We pull the budget, estimate and bid strategy into one proposal an owner could act on, with a clean cost history, priced alternates, a schedule and the reasoning behind the markup. A first final project draft is free and arrives in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 605 papers and related MS in Management samples

MGT 605 Module 10 questions, answered

Where can I find a free MGT 605 Module 10 Final Project sample?

A complete MGT 605 Module 10 final project is available on this page: a contractor's full bid proposal and estimating report for a school technical center.

What goes into a construction bid proposal?

The price in the owner's format with alternates and unit prices, a summary of the project as the contractor understands it, the schedule, qualifications and clear clarifications and exclusions.

Why should a bid proposal explain how the estimate changed?

Showing how each figure moved from the first budget to the final estimate gives the owner and the contractor's leadership confidence that the price rests on evidence.

What are clarifications and exclusions in a bid?

Statements of what the price assumes and what it leaves out, written specifically enough that owner and contractor will read them the same way.

How should the markup be justified in an MGT 605 final project?

With the competitive analysis behind it, the probability of winning and expected profit at several markups, and the judgment about risk that the models leave out.