| Course | QSO 680 Seminar in Project Management |
|---|---|
| Module | Module 9 |
| Paper type | graduate final project presenting an advanced plan for a complex project built in project software, integrating scope selection, a resource-leveled schedule, critical chain buffers, simulation results, cost and contingency, quantified risk, program interfaces and a control approach |
| Length | About 1,300 words, 7 pages |
| Format | APA 7 student paper |
| School | Southern New Hampshire University |
| Program | MS Project Management |
| Updated | October 2026 |
Free sample paper for QSO 680 Module 9
The Advanced Project Plan for the Meridian Isle Dry Dock
[Student Name]
Southern New Hampshire University
QSO 680: Seminar in Project Management
Final Project
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
The Advanced Project Plan for the Meridian Isle Dry Dock
Introduction
On January 9, the Meridian Isle, a 2,380-passenger ship of Coral Lantern Cruises, enters a Gulf Coast shipyard for 18 days. Its first sailing after the yard, from Miami on day 20, is fully booked, so a single late day wipes out a cruise's ticket income, roughly $1.6 million, plus goodwill. This plan brings together the methods applied in this course into one plan for the dry dock: how the scope was chosen, how the schedule was built and leveled, how uncertainty was measured and protected against, how cost and contingency were set, how the main risk decision was made, how the dry dock fits the fleet program and how the work will be controlled.
Diagnosis of Complexity
The dry dock is complex in several distinct ways. It has many interdependent parts: about 610 jobs across hull, propulsion, ballast water and hotel work, sharing power, cranes, welders and spaces. It has uncertainty that resolves early: steel renewal quantities on day 2 and pod condition on day 4. It moves at extreme pace, and it involves three organizations with separate contracts. Pich et al. (2002) argue that the right management strategy depends on whether a project's information is adequate: where outcomes can be foreseen, planning and instruction work; where they cannot, the project needs learning and parallel trials. Most of the dry dock is foreseeable and is planned in detail; the two early uncertainties are handled by decision points and contingency, not by pretending they are known.
Scope
The 812 requests, worth about $71 million, were cut to the 186 jobs rules require plus some 424 others that won places by score per dollar while fitting both the money and the in-dock-only window. Seventy-four hotel jobs move to riding crews on the next three voyages, 128 are deferred, and a $2.6 million spa expansion is held as an option to be decided in July from bookings data. The scope fits $47.3 million of allocable budget and 18 days.
The Software Model
The schedule is built in project management software with about 4,000 lines rolled into about 90 summary activities by work stream. Resources are drawn from a shared pool used by all three ships in the fleet program, so that experts and contracted crews booked for the Meridian Isle are visible when the Palmetto Star is planned. The baseline is saved after leveling and again after buffers are inserted, and each shift's progress is entered at shift change by the project's planner.
Resource-Leveled Schedule
Built on logic alone, the schedule needed up to 230 welders a day against 140 available and more crane lifts than two cranes can make. Leveling with a minimum-slack rule pushed undocking to day 19.5. Three plan changes recovered the time for about $610,000: ballast water pipe spools built in the yard's shop before arrival, 70 night-shift welders from a subcontractor for steel renewal and cabin materials loaded through a shell door to relieve the cranes. After those changes, leveling holds undocking at day 18 and day-shift welders top out at 138.
Uncertainty and Buffers
Probability of undocking by day 18 at each planning stage
| Stage | Chance of day 18 | 80th percentile finish |
|---|---|---|
| Original logic-only plan | about 34% | about day 19.6 |
| After prefabrication and night shift | about 62% | about day 18.5 |
| With critical chain target and buffer management | target day 16.7; commitment day 18 | buffer covers most simulated overruns on the chain |
A Monte Carlo simulation of the original plan showed only a one-in-three chance of day 18, mostly because four parallel paths had to finish together. The plan changes raised the chance to about 62 percent. Critical chain scheduling then stripped the foremen's hidden cushions out of the chain of hull gauging, steel renewal, blasting, coating, cure and undocking, set a project buffer of 2.1 days sized from the removed safety and checked against the simulation, and added feeding buffers of 0.8 and 1.0 days where the ballast water and pod paths join. That puts the working target at day 16.7 while the promise to the cruise line stays at day 18.
Cost Baseline and Contingency
Cost baseline and reserves
| Item | Amount |
|---|---|
| Mandatory jobs | $21.4 million |
| Discretionary jobs selected | about $25.9 million |
| Allocable baseline | about $47.3 million |
| Contingency for growth work | $4.7 million |
| Dry-dock budget | $52.0 million |
The contingency was checked by simulating growth work, chiefly steel renewal above 70 tonnes, coating weather and pod damage. The 80th percentile of simulated growth cost is about $4.4 million and the 90th about $5.3 million, so the contingency covers the 80th percentile, and the fleet program's reserve stands behind the remainder.
Key Risk Decision
A decision tree compared three ways to install the required ballast water treatment system. Counting only lost revenue, loose components had the lowest expected cost; once refunds, future credits and lost bookings were added to lost revenue, the three options were within about $20,000 of each other, and the factory-tested skid was chosen because it reduces the chance of losing a day from about 30 to 8 percent. The extra $500,000 is in the discretionary allocation.
Program Interfaces
The dry dock shares people, suppliers and the shipyard with two later ships. Under program rules, a ship in service has first call on the propulsion superintendent, work inside a dry-dock window comes next and planning comes last; the superintendent's time is booked through the program manager, and a second engineer is shadowing the overhaul. The ballast water skid is the first of three in a bulk order. The berth window cannot slip, because the shipyard's next customer arrives two days after the Meridian Isle leaves.
Control Approach
Vanhoucke (2012) compared project control methods on simulated and real projects and found that top-down earned value monitoring worked best for projects with mainly serial activities, while bottom-up schedule risk analysis of individual activities was more useful for projects with many parallel paths. The dry dock is highly parallel, so schedule control centers on buffer tracking and the chain's activities, while earned value is used for cost, where it remains informative. A review of analytical monitoring and control models has pointed to the distance between the methods studied and the simple tools practitioners actually use (Hazır, 2015); the control routine here is therefore deliberately plain.
Control routine
| Measure | Frequency | Owner | Trigger for action |
|---|---|---|---|
| Project and feeding buffer used vs chain complete | Each shift change | Planner | Yellow zone: plan recovery; red zone: act |
| Welders and crane lifts booked vs available | Daily | Shipyard planner | Demand above 135 welders or 40 lifts |
| Cost growth vs contingency | Daily during days 1 to 5, then every two days | Project manager | Growth forecast above $4.4 million |
| Earned value for cost | Weekly | Cost engineer | Cost performance index below 0.95 |
| Decision point: hull gauging results | Day 2 | Project manager | Steel above 110 tonnes: request program reserve |
| Decision point: pod condition | Day 4 | Propulsion superintendent | Bearing damage: switch to spare bearing set |
Limits of the Plan
The methods depend on estimates from foremen and suppliers, and simulation results are only as good as those ranges. Critical chain depends on behavior, especially avoiding multitasking, which the shipyard's habits may resist. And no method removes the possibility of an event outside the model, such as a hurricane watch, which is why the 1.3 days between the target and the commitment are not allocated to any activity.
Conclusion
The Meridian Isle's plan combines methods because the dry dock's complexity has several sources. Scope was chosen against hard limits, the schedule was leveled against real welders and cranes, simulation showed where the date was fragile, buffers protect the finish, contingency is set from simulated growth, the main risk decision was made with numbers and the control routine fits a project of parallel paths. Together they turn an 18-day promise from a one-in-three chance into a date the yard and the cruise line can plan around.
References
Hazır, Ö. (2015). A review of analytical models, approaches and decision support tools in project monitoring and control. International Journal of Project Management, 33(4), 808-815. https://doi.org/10.1016/j.ijproman.2014.09.005
Pich, M. T., Loch, C. H., & De Meyer, A. (2002). On uncertainty, ambiguity, and complexity in project management. Management Science, 48(8), 1008-1023. https://doi.org/10.1287/mnsc.48.8.1008.163
Vanhoucke, M. (2012). Measuring the efficiency of project control using fictitious and empirical project data. International Journal of Project Management, 30(2), 252-263. https://doi.org/10.1016/j.ijproman.2011.05.006
What the QSO 680 Module 9 instructions ask for
For its capstone, QSO 680 wants a full plan for one complex undertaking, built with the advanced methods and with scheduling software. Expect to present the project's scope and how it was chosen, a schedule that accounts for resource limits, an analysis of schedule uncertainty, a cost baseline with reserves, a quantified risk analysis and the approach to monitoring and control, along with the software outputs that support them. Strong projects explain why each method was chosen for this project's particular complexity, show that the methods were combined rather than applied in isolation, keep every figure consistent from one section to the next, discuss the limits of the tools and set out a control approach suited to the project's structure. Screens from software should support the argument, not replace it.
How this QSO 680 Module 9 final project example is built
The project presents the advanced plan for the Meridian Isle's 18-day dry dock at Coral Lantern Cruises, a fictional Miami line. It summarizes the complexity diagnosis and a scope of about 610 jobs chosen from 812, a software model of about 4,000 lines in 90 summary activities with a fleet resource pool, the leveled schedule kept at day 18 by prefabrication, a night shift and crane relief, a critical chain with a 2.1-day buffer and a day-16.7 target, simulation results rising from 34 to 62 percent, a $47.3 million baseline with $4.7 million contingency at the 80th percentile and the factory-tested ballast water skid. Control pairs buffer tracking with earned value. Pich and colleagues, Vanhoucke and Hazır are cited.
Where the QSO 680 Module 9 rubric puts the points
Marks on the QSO 680 final project usually go to a clear diagnosis of complexity, a scope justified by selection methods, a resource-leveled schedule built in software, a probabilistic analysis interpreted correctly, buffers or reserves sized with stated methods, a cost baseline and contingency tied to risk analysis, quantified risk decisions, attention to program or multi-project interfaces, a control approach suited to the project and consistent figures throughout. Plans stand out when the methods visibly inform one another. They lose points for screenshots without explanation, for figures that change between sections, for methods applied without saying why, for ignoring resource limits or for control plans that track only cost. Consistent tables and accurate APA entries take the final points.
QSO 680 Module 9 help: the mistakes that cost points
Start with a short diagnosis: what makes your project complex and which methods answer each source. Then present the plan in the order decisions were made: scope selected within limits, schedule leveled against real resources, uncertainty simulated, buffers or reserves sized, cost baselined with contingency from the risk analysis, key risk decisions made with numbers. Make sure every figure, from the number of jobs to the contingency, is the same everywhere it appears. Describe the software model briefly and use its outputs as evidence. End with how you will control the project: what you will measure, how often and what triggers action. Final projects often present each milestone again; the best ones show how the methods depend on each other.
Get QSO 680 Module 9 written to your instructions
Share the QSO 680 capstone instructions, your project software file or data and any milestone feedback. A writer builds and explains an integrated advanced plan covering scope selection, resource-leveled scheduling, buffers, simulation, cost and contingency, quantified risk, program interfaces and control, keeps the figures consistent across sections and supports each method with research. Your first QSO 680 project is drafted free, usually in two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 680 papers and related MS Project Management samples
- QSO 680 Module 1 Discussion: Why a Dry Dock Is Complex
- QSO 680 Module 2 Program Assignment: Three Ships, One Fleet Program
- QSO 680 Module 3 Scope Selection Assignment: Choosing 610 of 812 Jobs
- QSO 680 Module 4 Discussion: A One-in-Three Chance of 18 Days
- QSO 680 Module 5 Resource Scheduling Assignment: Leveling Welders and Cranes
- QSO 680 Module 6 Critical Chain Assignment: Buffers Instead of Padding
- QSO 680 Module 7 Discussion: Two Ships, One Superintendent
- QSO 680 Module 8 Quantitative Risk Assignment: Steel, Paint and a Decision Tree
- QSO 680 Module 10 Discussion: What the Tools Were Worth
- MKT 668 Module 3 Milestone One: Service Blueprint and Customer Journey
- QSO 530 Module 8 Regression Assignment: What Moves Weekly Store Sales
- MGT 605 Module 1 Discussion: A Bond Number Set Too Early
- FIN 610 Module 2 Cash Budget Assignment: Twelve Months of Rappahannock's Cash
QSO 680 Module 9 questions, answered
Where can I find a free QSO 680 Module 9 Final Project sample?
The full QSO 680 Module 9 final project is on this page: an advanced plan for an invented cruise ship's 18-day dry dock.
What goes into an advanced project plan?
Scope selection, a resource-leveled schedule, probabilistic analysis, buffers or reserves, a cost baseline with contingency, quantified risks, interfaces and a control approach.
How should project software outputs be used in a final project?
As evidence for decisions, such as histograms showing overallocations or simulation curves, explained in the text rather than pasted alone.
Why combine several advanced scheduling methods?
Because each answers a different problem: leveling handles resources, simulation handles uncertainty and buffers protect the date.
How should a complex project be controlled?
With measures suited to its structure, such as buffer tracking for parallel paths and earned value for cost, plus decision points when key uncertainties resolve.