MGT 600 Module 10 Final Project Example

Reviewed by Portia Lambrick, MBA

This MGT 600 Module 10 Final Project sample presents an integrated plan for allocating people, equipment and money to solve a complex, messy organizational problem. In SNHU MGT 600 (MGT-600), the Final Project has MBA students bring framing, resource assessment, decision analysis and resource planning together into one plan. For Wabash Crane and Rigging, a composite Indiana crane company with more heavy-lift work than it can staff, the plan frames the problem, summarizes the constraint, explains the chosen option, sets allocations by year and branch, adds goals, metrics and safeguards and gives a three-year outlook, risks and an execution plan.

CourseMGT 600 Resource Planning and Decision Making
ModuleModule 10
Paper typegraduate final project presenting an integrated resource plan for a complex problem
LengthAbout 1,060 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMBA
UpdatedOctober 2026

Free sample paper for MGT 600 Module 10

1

Build the Crews, Then the Fleet: An Integrated Resource Plan for Wabash Crane and Rigging

[Student Name]

Southern New Hampshire University

MGT 600: Resource Planning and Decision Making

Final Project: Integrated Resource Plan

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingWabash Crane and Rigging and every figure in this plan are composites built for this course.
2

Build the Crews, Then the Fleet: An Integrated Resource Plan for Wabash Crane and Rigging

Executive Summary

Wabash Crane and Rigging turned away $7.2 million of heavy-lift work last year while fourteen operator seats sat empty and one branch ran its cranes less than half the time. Its leaders spent months arguing over a $4.8 million crawler crane. This plan recommends building operator capacity first, renting heavy crawlers only for work under contract, replacing the oldest cranes, giving each branch a defined role and measuring branches on more than revenue. Over three years it should cut turned-away revenue below $2 million, raise utilization to 72 percent and keep the company's record of no fatal accidents, while preserving the option to buy a heavy crawler when contracts justify it.

What this page is doingThe decision in brief.
3

The Problem

Simon (1973) observed that most real problems lack a fixed list of alternatives and an agreed way to judge a solution, so part of the work is deciding what the problem is. Wabash's leaders each defined it differently: an equipment gap, a people gap, a location mismatch. The plan treats it as a capacity problem whose binding element is people, and it chooses among options against objectives the owners set before looking at options: profit, safety, cash risk, operator feasibility and client relationships.

What this page is doingWhy it resisted easy answers.
4

The Constraint

Barney (1991) argued that lasting advantage comes from resources that rivals cannot easily obtain or copy. At Wabash, cranes can be bought by any competitor with credit; experienced, certified operators cannot, and the company's average operator is 52 with 31 eligible to retire within five years. Its safety record and utility relationships, built over forty years, are also hard to copy and underused. The plan therefore spends first on people and puts the safety record to work in winning contracts.

What this page is doingWhat the assessment found.
5

The Choice

Buying the crawler scored lowest of six options because it failed on the two real constraints, operators and cash risk, and because it rested on a forecast of nine busy months. Kahneman and Lovallo (1993) showed that managers forecasting from the details of their own plans tend toward bold estimates; Wabash's own record bears that out, since its last two crawlers were forecast at 75 percent use and averaged 52. The hybrid option scored highest by combining operator development with contract-only rental, and it keeps the purchase open for when contracts make the forecast real.

What this page is doingWhy the hybrid won.
6

Personnel

The plan adds 78 operators over five years against a need of about 72: 26 experienced hires, 40 certified apprentices drawn from riggers and oilers and 12 veterans. A training yard at Fort Wayne opens in year two. Retention measures include predictable schedules, a heavy-lift premium, mentor stipends and phased retirement. Open seats should fall from fourteen to about two by the end of year three.

What this page is doingMaking operators.
7

Equipment and Capital

Year-one capital goes first to retiring the six oldest hydraulic cranes, about $3.1 million, then to crane telematics and shop tools at $1.2 million and the Fort Wayne training yard at $1.6 million. The remaining $3.1 million sits in a reserve for a heavy crawler and is released only on the purchase triggers fixed in Milestone Two, a long contract or a rental season past break-even. Expanding the Toledo yard waits until that branch's cranes are busy more than 60 percent of the time.

What this page is doingSpending in order.
8

Branch Roles

The heavy-lift team and any rented crawler base out of Indianapolis, nearest to most wind and data-center sites. Training and the central shop sit in Fort Wayne. South Bend sticks to steel erection and general building work. Toledo serves plants and its utility client with maintenance lifts and sends three of its least-used cranes to Indianapolis for each busy season.

What this page is doingA job for each yard.
9

Goals and Safeguards

Locke and Latham (2002) concluded from decades of studies that a hard, precise target lifts performance above a vague one, provided people accept it, get feedback and have the means to succeed. The plan's three-year goals are specific: open seats at four or fewer, turned-away revenue under $2 million, utilization at 72 percent, heavy-lift revenue of $5 million and weekly operator overtime under six hours. After the South Bend outrigger incident, safeguards are built in: on-time credit now requires a logged inspection, safety measures veto other bonus elements and every goal is reviewed against the others for conflicts.

What this page is doingPushing without breaking.
10

Measures

Branches are measured monthly on ten indicators: contribution per crane, revenue, utilization, mechanical downtime, on-time arrival with logged inspection, repeat clients, near misses reported, recordable incidents, apprentices mentored and operator overtime. Branch bonuses weight contribution, use, arrival, safety and operator development, and cranes lent to another branch count toward the lender's utilization. After a year, the company will test whether the operating measures actually predict contribution and drop any that do not.

What this page is doingThe branch scorecard.
11

Outlook

Three-year outlook

MeasureTodayYear 3 base caseYear 3 downside
Revenue$96 million$112 million$102 million
Turned-away revenue$7.2 millionUnder $2 million$4 million
Utilization66 percent72 percent68 percent
Open operator seats1428
Heavy-lift rental revenue$0$5 million$2 million

The downside assumes apprentice pass rates of 65 rather than 80 percent and a mild construction slowdown. Even then, the plan avoids a stranded crane, since heavy capability is rented, and keeps spending within cash flow.

What this page is doingBase case and downside.
12

Risks

A construction slowdown would cut demand; rental-first equipment and adjustable apprentice intake limit the damage. Apprentices may fail certification more often than expected; the plan admits extra trainees. A serious heavy-lift accident would wreck the reputation that wins the plan its contracts; only senior operators run heavy lifts, and lift engineers plan every one. Competitors may hire away newly certified operators; service commitments and the heavy-lift premium answer that.

What this page is doingWhat could go wrong.
13

Execution

Accountability follows the Milestone Two assignments: people and training sit with operations, money and rental agreements with finance, contracts and the buy decision with sales and each scorecard with its branch manager. The owners look at the scorecard every month, the goals every quarter and the purchase question at the close of each season.

What this page is doingOwners and reviews.
14

Conclusion

Wabash did not lack cranes or ambition; it lacked the people to run what it had and a way to decide among competing answers. This plan builds the crews first, buys heavy capability only when contracts justify it, gives every branch a clear role and measures what the plan needs, so the next decision about a big crane can rest on evidence rather than a forecast.

What this page is doingCapacity before capital.
15

References

Barney, J. (1991). Firm resources and sustained competitive advantage. Journal of Management, 17(1), 99-120. https://doi.org/10.1177/014920639101700108

Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17-31. https://doi.org/10.1287/mnsc.39.1.17

Locke, E. A., & Latham, G. P. (2002). Building a practically useful theory of goal setting and task motivation: A 35-year odyssey. American Psychologist, 57(9), 705-717. https://doi.org/10.1037/0003-066X.57.9.705

Simon, H. A. (1973). The structure of ill structured problems. Artificial Intelligence, 4(3-4), 181-201. https://doi.org/10.1016/0004-3702(73)90011-8

What the MGT 600 Module 10 instructions ask for

The final project in MGT 600 usually asks for a complete plan that addresses an ill-structured organizational problem, drawing together problem definition, resource assessment, analysis of alternatives and a resource plan covering personnel, budget, performance metrics and goals. A strong project reads as one argument, revises the milestones where feedback warranted it, shows allocations in numbers by period and unit, ties goals and measures to the chosen option, anticipates side effects and execution risks and gives leaders an outlook that shows what the plan should achieve and what it would cost if assumptions prove wrong. Some versions also ask for a short presentation or executive brief, so check every required part of the deliverable.

How this MGT 600 Module 10 final project example is built

The sample builds one plan for Wabash Crane and Rigging. It frames the problem as meeting heavy-lift demand without enough certified operators, summarizes the assessment that found people rather than cranes to be the constraint and explains why a hybrid option, developing operators first and renting a heavy crawler only for contracted work, beat buying a $4.8 million crane. Drawing on Simon on ill-structured problems, Barney on resources, Kahneman and Lovallo on bold forecasts and Locke and Latham on goals, it sets personnel, equipment, capital and branch allocations, goals with safety vetoes, a scorecard, a three-year outlook with a downside case, risks and an execution plan. Each section points back to the milestone evidence that supports it.

Where the MGT 600 Module 10 rubric puts the points

Final project rubrics usually weigh how well the problem is framed, the quality of the resource analysis, the justification of the chosen option, the completeness of the resource plan, goals and measures, the treatment of risks and execution and the use of research and APA style. The strongest projects hold together as one argument, show numbers by year and unit, include a downside case and build safeguards into goals. Marks drop when the milestones appear unrevised, when the outlook assumes everything goes right, when goals invite shortcuts and when no one owns the actions. Instructors also check that the outlook, budget and goals agree with each other and that milestone feedback visibly changed the plan.

MGT 600 Module 10 help: the mistakes that cost points

Imagine handing the plan to the owners on a Friday afternoon, with none of your earlier papers attached. Open with the problem and the decision in a short paragraph. Summarize the evidence briefly, then explain why the chosen option beat the others. Lay out allocations by year and unit in tables. Set goals and measures, and add safeguards where a goal could tempt shortcuts. Give an outlook with a base case and a downside case, since leaders need to know what happens if assumptions fail. End with risks, owners and the review schedule. Cut any paragraph that does not lead to a decision, an allocation or a measure.

Get MGT 600 Module 10 written to your instructions

Share the MGT 600 Final Project rubric along with your instructor's notes on Milestones One and Two. We combine your framing, assessment, decision and resource plan into one integrated document with allocations, goals, an outlook and an execution plan. Two days, and the first final project is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More MGT 600 papers and related MBA samples

MGT 600 Module 10 questions, answered

Where can I find a free MGT 600 Module 10 Final Project sample?

The full MGT 600 Final Project is here: an integrated resource plan for a crane company, from framing to outlook.

What is an integrated resource plan?

A single plan that frames a problem, assesses resources, chooses among alternatives and allocates people, equipment and money with goals, measures, risks and an execution schedule.

Why include a downside case in a resource plan?

Forecasts tend to be optimistic, so a downside case shows leaders what the plan would cost and deliver if key assumptions fall short.

How do you keep goals from causing harm?

Define goals so shortcuts do not count, give safety and ethics measures a veto, resolve conflicts among goals and review results for side effects.

What should an MGT 600 final project include?

A problem statement, resource assessment, analysis of alternatives, a resource plan for personnel, budget and equipment, goals and metrics, risks and an implementation timeline.