QSO 340 Module 4 Project Schedule and Critical Path Assignment example

Reviewed by Portia Lambrick, MBA Project Management Southern New Hampshire University Full sample paper Free custom sample in 24 to 48h

This complete QSO 340 Module 4 assignment builds the schedule for the warehouse management system project planned in Project One at a composite regional food bank. It lists twelve activities with durations and dependencies, calculates early and late start and finish times with a forward and backward pass, identifies the critical path and the float on every other activity, and discovers that the schedule misses the November 15 go-live date by about a week. The paper compares crashing and fast-tracking as fixes and recommends one. The food bank is composite; the scheduling methods are standard.

What this page holds

The complete text of a QSO 340 Module 4 scheduling assignment: an activity list with dependencies, a critical path table with early and late times and float, the finding that the plan misses its deadline, and a comparison of crashing and fast-tracking with a recommended solution. Searches like "qso 340 module 4 assignment", "qso340 module 4 project schedule and critical path assignment" and "qso 340 module 4 example" land here.

The QSO 340 Module 4 example, in full

1

Finding the Critical Path: Scheduling a Food Bank's Warehouse System Project Against a Holiday Deadline

[Student Name]

Southern New Hampshire University

QSO 340: Project Management

Module Four Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe title names the method and the constraint that makes it matter, a deadline the project cannot move, which signals that the analysis leads to a decision.
2

Finding the Critical Path: Scheduling a Food Bank's Warehouse System Project Against a Holiday Deadline

The Deadline

The composite Tri-River food bank must bring its new warehouse management system live by November 15, the end of the project's 37th week, because holiday food drives make late November through early January the worst possible time to change how the warehouses work. The project plan in Project One listed the work in its work breakdown structure but did not yet show whether the deadline was realistic. The critical path method, first described for industrial projects in the late 1950s (Kelley & Walker, 1959), answers that question by finding the longest chain of dependent work (Kerzner, 2022).

Activities, Durations and Dependencies

The project team broke the work packages into twelve activities and estimated each duration in weeks, based on the vendor's implementation plan and the food bank's staff availability. Requirements and process mapping (A, 5 weeks) comes first. Vendor contracting and system design (B, 6 weeks) and data cleanup (E, 6 weeks) follow A. System configuration (C, 12 weeks) and hardware installation, including scanners and freezer wireless coverage (D, 8 weeks), follow B. Trial data migrations (F, 4 weeks) need both C and E. Warehouse user testing (G, 4 weeks) needs C and D. The pantry pilot (H, 6 weeks) needs F and G. Warehouse staff training (I, 3 weeks) follows G. Pantry training (J, 4 weeks) follows H. Final migration and cutover (K, 1 week) needs I and J, and go-live support and handoff (L, 2 weeks) follows K.

Forward and Backward Pass

The forward pass calculates each activity's earliest start and finish, working from the beginning; the backward pass calculates the latest start and finish that would not delay the project, working back from the end. Float, the difference between the late and early start, shows how much an activity can slip without delaying the project. Table 1 summarizes the results in weeks from the project start.

Table 1

Critical Path Calculations, Warehouse Management System Project

ActivityDurationEarly startEarly finishLate startLate finishFloat
A Requirements505050
B Contract and design65115110
C Configuration12112311230
D Hardware8111915234
E Data cleanup6511172312
F Trial migrations4232723270
G Warehouse testing4232723270
H Pantry pilot6273327330
I Warehouse training3273034377
J Pantry training4333733370
K Cutover1373837380
L Go-live support2384038400

Note. Composite estimates, in weeks from the project start. Zero float marks critical activities.

What this page is doingThe table shows every early and late time, so each float value can be checked. Showing both passes rather than only the critical path demonstrates the method, which is what the assignment grades.
3

The Critical Path and the Float

The zero-float activities make up the critical path: A, B, C, then F and G in parallel, H, J, K and L. Because F and G have the same duration and both lead into the pilot, the network has two critical branches through that stage, which makes it more fragile: a delay in either the migrations or the warehouse testing delays everything after it. Data cleanup has 12 weeks of float and can be scheduled whenever the inventory analyst has time. Hardware has 4 weeks of float, and warehouse training has 7.

The critical path ends with cutover at week 38, one week after the week 37 deadline. The plan as estimated puts go-live in the middle of the holiday blackout, which the charter forbids. Something must change before work begins, not after the project falls behind.

How Reliable Are the Estimates?

A critical path is only as good as the duration estimates behind it, and these are single-point estimates for work the food bank has never done. Configuration, at 12 weeks, carries the most uncertainty because it depends on how many of the food bank's practices fit the vendor's standard settings. The project team therefore also asked the vendor for optimistic and pessimistic figures: 10 weeks if the standard setup fits well and 16 weeks if significant changes are needed. Using the common three-point weighting of one optimistic, four most likely and one pessimistic estimate divided by six, the expected duration is about 12.3 weeks, slightly longer than the estimate used in Table 1. The pessimistic case would push cutover four weeks later, well into the holiday period. This does not change the recommendation below, but it shows why configuration progress should be the first item in every status meeting and why the contingency reserve should not be spent on anything else until configuration is complete.

Two Ways to Shorten the Schedule

The project needs to recover at least one week, and preferably two to leave a buffer. There are two standard options (Project Management Institute [PMI], 2021).

Crashing adds resources to a critical activity. The vendor offers a second configuration consultant for 24,000 dollars, which would shorten configuration from 12 to 10 weeks. That recovers two weeks, but it draws on 40 percent of the 60,000 dollar contingency reserve before the project has started, and adding a new person to configuration work can slow it at first while they learn the food bank's setup.

Fast-tracking overlaps activities that were planned in sequence. Pantry training could begin two weeks before the pilot ends, using the lessons from the first four weeks of the pilot, rather than waiting for all six weeks. That also recovers two weeks and costs almost nothing, but it adds risk: if the last weeks of the pilot reveal a problem with the ordering portal, the training materials would need to be revised and some pantries retrained.

Recommendation

The project should fast-track pantry training and keep the configuration consultant as a fallback. Overlapping two weeks of pantry training with the end of the pilot moves cutover to week 36, about a week ahead of the deadline, without spending contingency. The risk of rework is manageable because most portal problems appear in the first weeks of a pilot, and the training can be delivered first to the eight pilot pantries, who already know the system. If configuration runs late, the project manager can still crash it with the second consultant, which is why the contingency should remain untouched for now. The float on data cleanup and hardware should be protected rather than consumed early, and the two parallel critical branches, migrations and warehouse testing, should be reviewed weekly because either can push the whole schedule past the holiday.

References

Kelley, J. E., Jr., & Walker, M. R. (1959). Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference (pp. 160-173). Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318

Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). Wiley.

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

How this QSO 340 Module 4 example is structured

The assignment works through the critical path method in order. Activities and their dependencies are listed first, then the forward and backward passes are summarized in a single table. The critical path and float are interpreted, the deadline problem is identified, and two ways of compressing the schedule are compared on cost and risk before a recommendation.

Get QSO 340 Module 4 written to your instructions

Send your QSO 340 Module 4 assignment and rubric with the activity data you were given. A network schedule with the critical path, float and a compression recommendation comes back within 24 to 48 hours; your first one is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

QSO 340 Module 4 questions, answered

What does QSO 340 Module 4 usually cover?

Scheduling is the usual focus of this module: defining activities from the work breakdown structure, sequencing them with dependencies, estimating durations, building a network diagram and finding the critical path. Assignments may also ask how to shorten a schedule by crashing or fast-tracking.

What is the critical path?

The critical path is the longest sequence of dependent activities through the project network. It determines the shortest possible project duration, and activities on it have zero float, so any delay to them delays the whole project unless the schedule is changed.

What is the difference between crashing and fast-tracking?

Crashing shortens critical activities by adding resources, such as extra staff or overtime, which usually increases cost. Fast-tracking performs activities in parallel that were planned in sequence, which usually adds risk because later work starts before earlier work is complete.