QSO 328 Module 7 Project Two Example

Reviewed by Portia Lambrick, MBA

This QSO 328 Module 7 Project Two sample is a sustainable operations improvement plan with specific projects, costs, paybacks, environmental targets and an implementation schedule. SNHU QSO 328 (QSO-328) closes its BS Operations Management sustainable operations course with this plan in Module 7. The plant belongs to Cumberland Clay Tile, an invented Tennessee maker of porcelain and ceramic tile. Six projects, from kiln heat recovery and grinding fired scrap into new tile to a closed glaze water loop and returnable pallets, cost about $4.4 million, save about $2.2 million a year and cut the plant's own emissions by about 12 percent, landfilled waste by about 75 percent and fresh water by about 30 percent.

CourseQSO 328 Sustainable Operations
ModuleModule 7
Paper typeundergraduate sustainable operations improvement plan with projects, costs, paybacks, environmental targets and an implementation schedule
LengthAbout 1,140 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 328 Module 7

1

Less Gas, Less Landfill, Same Margins: A Sustainable Operations Plan for Cumberland Clay Tile

[Student Name]

Southern New Hampshire University

QSO 328: Sustainable Operations

Project Two: Sustainable Operations Improvement Plan

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingAll projects, costs, savings and targets for Cumberland Clay Tile in this QSO 328 plan are invented.
2

Less Gas, Less Landfill, Same Margins: A Sustainable Operations Plan for Cumberland Clay Tile

Introduction

Measured in 2025, the Lebanon plant emitted about 79,400 metric tons of carbon dioxide from its own fuel and electricity, withdrew 96 million gallons of fresh water and sent about 13,400 tons of fired scrap and glaze sludge to a landfill. Project One ranked five priorities: kiln and dryer energy, fired scrap, glaze water, packaging and supply chain partners. This plan turns those priorities into six projects, estimates their costs, savings and environmental effects, sets targets, addresses the barriers that have kept such projects unfunded and schedules the work. Corbett and Klassen (2006) argue that environmental gains in operations come from extending the boundaries of analysis to costs that are usually overlooked, and in the data of King and Lenox (2002) it was waste avoided, not waste treated, that paid; the plan is built on prevention first.

What this page is doingRestates the baseline and priorities.
3

Project 1: Kiln Waste Heat Recovery

A heat exchanger will duct exhaust from the two roller kilns to the tile dryers, replacing dryer gas burners for most of the year. Cost is about $2.1 million installed; the dryers would need roughly 12 percent less of the plant's gas, worth about $560,000, with a payback of about 3.8 years. Emissions fall by about 7,400 metric tons a year.

What this page is doingCaptures heat now lost up the stack.
4

Project 2: Grinding Fired Scrap Into New Tile

A grinding mill and classifier will crush fired scrap into a fine powder that can replace up to 8 percent of the clay and feldspar in tile bodies, after testing confirms color and strength. At an 8 percent blend, the bodies could absorb roughly 9,000 tons, most of what the kilns now reject each year. Cost is about $900,000. Savings are about $440,000 in avoided landfill fees, which are rising, and about $225,000 in purchased raw materials, a payback of about 1.4 years. A tile body with recycled content also earns credits with architects and supports the environmental product declaration. A separate effort will cut fired scrap at the source through kiln temperature control, targeting a scrap rate of 4.5 percent from 6 percent.

What this page is doingTurns the largest waste stream into raw material.
5

Project 3: Closed Glaze Water Loop

A filtration and settling system will treat glaze line wash water so it can be reused in glaze preparation, and the recovered glaze solids will be dried and blended back into darker glazes. Cost is about $650,000. Fresh water use falls by about 29 million gallons a year, about 30 percent, and glaze sludge sent to landfill falls by about 60 percent. Savings in water, sewer and landfill charges are about $190,000 a year, a payback of about 3.4 years.

What this page is doingReuses glaze wash water.
6

Project 4: Compressed Air and Motor Efficiency

A leak survey and repair program, controls that match compressor output to demand, variable speed drives on ball mill and spray dryer fans and LED lighting will cost about $380,000 and save about 5,200 megawatt-hours a year, roughly $440,000 at current rates, a payback under one year. Emissions fall by about 2,100 metric tons. Anderson and Newell (2004), studying industrial energy audits, found that firms adopted only about half of recommended projects and were far more likely to adopt those with short paybacks, so this quick-payback project is scheduled first to build confidence.

What this page is doingCuts electricity waste.
7

Project 5: Returnable Pallets

In a pilot with the home improvement chain's regional distribution center, tile will ship on durable returnable pallets that come back on Cumberland's trucks, replacing one-way wood pallets and some shrink wrap. Cost is about $300,000 for an initial pallet pool. Savings are about $150,000 a year, and the customer has asked for exactly this kind of collaboration.

What this page is doingWorks with the largest customer on packaging.
8

Project 6: Backhauls With the Carrier

The trucking carrier hauls outbound tile and, separately, inbound clay from Kentucky and North Carolina, and many trucks run empty one way. A shared schedule matching outbound deliveries with inbound clay pickups will cut empty miles by an estimated 15 percent, saving about $180,000 a year in freight and about 1,500 metric tons of supply chain emissions, for roughly $40,000 in scheduling software and carrier setup.

What this page is doingCuts empty truck miles.
9

Combined Results

Summary of the six projects (invented estimates)

ProjectInvestmentAnnual savingsPaybackMain environmental effect
Kiln heat recovery$2.1 million$560,0003.8 years-7,400 t CO2
Grinding fired scrap$0.9 million$665,0001.4 years-9,000 t landfill waste
Closed glaze water loop$0.65 million$190,0003.4 years-29 million gallons water
Compressed air and motors$0.38 million$440,0000.9 years-2,100 t CO2
Returnable pallets$0.30 million$150,0002.0 yearsLess wood and wrap
Carrier backhauls$0.04 million$180,0000.2 years-1,500 t CO2 in supply chain
TotalAbout $4.4 millionAbout $2.2 millionAbout 2 years

Together the projects cut emissions from the plant's own operations by about 9,500 metric tons, about 12 to 13 percent of the baseline, with further supply chain reductions; landfilled waste by about 9,000 tons of fired scrap and 1,100 tons of sludge, about 75 percent; and fresh water withdrawals by about 30 percent. Per thousand square feet, own-operations emissions fall from about 4.2 tons to about 3.7.

What this page is doingAdds up the projects.
10

Getting the Projects Funded

Jaffe and Stavins (1994) explained that the gap between profitable efficiency investments and those actually made arises partly from market failures, such as poor information, and partly from real hidden costs and uncertainty that firms rationally weigh. At Cumberland the main barrier is internal: a two-year payback rule that rejects heat recovery despite its positive net present value. The plan asks leadership to evaluate efficiency and waste projects on net present value at the 9 percent cost of capital, with a gas price sensitivity test, and to fund the quick-payback projects first so their savings help finance the larger ones. The gas utility's efficiency financing program, which allows savings to repay a loan through the utility bill, will be pursued for heat recovery.

What this page is doingAddresses the approval barrier.
11

Targets and Governance

By the end of 2028, against the 2025 baseline: own-operations carbon dioxide per thousand square feet down 12 percent; landfilled waste down 70 percent; fresh water per thousand square feet down 30 percent; fired scrap rate below 4.5 percent; recycled content of at least 8 percent in porcelain bodies. The environmental coordinator will report progress quarterly to the plant manager and annually to the board, using the baseline method from Module 2.

What this page is doingSets measurable goals and responsibility.
12

Implementation Schedule

Compressed air and motor work and carrier backhauls start in the first quarter of 2026. Scrap grinding trials run in the first half of 2026, with the mill installed by the third quarter. The glaze water loop is installed during the summer maintenance shutdown. Heat recovery is installed during the 2027 shutdown, after financing. The pallet pilot begins in mid-2026.

What this page is doingSequences the projects.
13

Risks

Recycled scrap could affect tile color or strength if not carefully controlled, so the blend rises in steps after testing. Gas prices could fall, stretching heat recovery's payback, though it remains positive in the sensitivity test. The pallet pilot depends on the customer's distribution center returning pallets reliably.

What this page is doingNotes what could go wrong.
14

References

Anderson, S. T., & Newell, R. G. (2004). Information programs for technology adoption: The case of energy-efficiency audits. Resource and Energy Economics, 26(1), 27-50. https://doi.org/10.1016/j.reseneeco.2003.07.001

Corbett, C. J., & Klassen, R. D. (2006). Extending the horizons: Environmental excellence as key to improving operations. Manufacturing & Service Operations Management, 8(1), 5-22. https://doi.org/10.1287/msom.1060.0095

Jaffe, A. B., & Stavins, R. N. (1994). The energy-efficiency gap: What does it mean? Energy Policy, 22(10), 804-810. https://doi.org/10.1016/0301-4215(94)90138-4

King, A., & Lenox, M. (2002). Exploring the locus of profitable pollution reduction. Management Science, 48(2), 289-299. https://doi.org/10.1287/mnsc.48.2.289.258

What the QSO 328 Module 7 instructions ask for

QSO 328 ends with a plan that improves the environmental and economic sustainability of the operation assessed in Project One. Expect to propose specific projects tied to the priorities identified earlier, estimate their costs, savings and environmental effects, set measurable targets against the baseline, address barriers to implementation and lay out a schedule and governance for tracking progress. Strong plans favor prevention at the source, quantify both financial and environmental results, show payback or net present value for each project, address why good projects often go unfunded and include supply chain actions as well as plant changes. The plan should be realistic for the organization's size and finances.

How this QSO 328 Module 7 project two example is built

The plan sets out six projects for Cumberland Clay Tile, a fictional tile plant with a 2025 baseline of about 79,400 metric tons of carbon dioxide from its own operations, 96 million gallons of fresh water and 13,400 tons of landfilled waste. Kiln heat recovery, grinding fired scrap into new tile bodies, a closed glaze water loop, a compressed air and motor efficiency program, returnable pallets with the largest customer and a backhaul agreement with the trucking carrier cost about $4.4 million and save about $2.2 million a year. The plan cuts own-operations emissions about 12 percent, landfilled waste about 75 percent and fresh water about 30 percent. Jaffe and Stavins, Anderson and Newell, Corbett and Klassen and King and Lenox inform the design and funding approach.

Where the QSO 328 Module 7 rubric puts the points

For QSO 328 Project Two, instructors evaluate how well projects address the priorities from the assessment, the soundness of cost, savings and payback estimates, the clarity of environmental targets against the baseline, the preference for prevention over end-of-pipe control, attention to implementation barriers and funding, inclusion of supply chain actions and a realistic schedule with governance. Plans that score highest show the arithmetic, report both financial and environmental results for each project and explain how they will get approved. Credit drops when projects are vague, savings lack assumptions, targets are not tied to the baseline or the plan ignores why such projects stall. Tables and APA citations complete the rubric.

QSO 328 Module 7 help: the mistakes that cost points

Turn each priority from your assessment into one or more projects with a defined scope. For each, estimate the investment, annual savings, payback and environmental effect in physical units, stating the assumptions. Add the projects up and set targets against your baseline, both in totals and per unit of output. Then think about approval: research on the energy efficiency gap explains why firms skip projects that would pay, so address payback rules, financing and the disruption of installation directly. Include actions with suppliers and customers where they matter. Sequence projects so quick paybacks fund later ones. A common mistake is a plan that lists technologies without numbers; another is targets that cannot be measured with the baseline you built. End with governance: who reports what and how often.

Get QSO 328 Module 7 written to your instructions

Send us the Module 7 directions for QSO 328 along with your assessment and baseline figures. A writer turns the priorities into specific projects, estimates each one's cost, savings, payback and environmental effect, sets targets against the baseline, explains how to get stalled projects funded and schedules the work. Your first QSO 328 Project Two is free, typically within two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 328 papers and related BS Operations Management samples

QSO 328 Module 7 questions, answered

Where can I find a free QSO 328 Module 7 Project Two sample?

The full QSO 328 Project Two is on this page: a sustainable operations plan for an invented tile plant with six projects, paybacks and targets.

What goes in a sustainable operations improvement plan?

Specific projects tied to the largest impacts, with costs, savings, paybacks and environmental effects, targets against a baseline, funding and implementation plans and governance.

What is the energy efficiency gap?

The difference between the energy efficiency investments that would pay off and those firms actually make, explained by factors such as hidden costs, uncertainty, capital limits and decision rules.

Why favor pollution prevention over pollution control?

Prevention removes waste and emissions at the source and often saves materials and energy, while control treats them afterward at added cost.

How should sustainability targets be set?

Against a measured baseline, in physical units and per unit of output, with a target year and an owner responsible for tracking progress.