QSO 420 Module 2 Budgeting Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 420 Module 2 Budgeting Assignment sample builds a project budget from the work breakdown structure into control accounts, with contingency, management reserve and a time-phased baseline. SNHU QSO 420 (QSO-420) assigns budgeting in Module 2, as its BS Operations Management cost and schedule course moves from ideas to numbers. The project is the Sauk Bend Park District's outdoor aquatic center, an invented $14.6 million Illinois project with a winter shutdown in the middle. The paper builds six control accounts, separates the contractor's contingency, the owner's contingency and the board's reserve and spreads the budget into a monthly S-curve.

CourseQSO 420 Integrated Cost and Schedule Control
ModuleModule 2
Paper typeundergraduate assignment building a project budget from the work breakdown structure into control accounts, with contingency, management reserve and a time-phased baseline
LengthAbout 1,020 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 420 Module 2

1

Six Control Accounts and Two Reserves: Budgeting the Sauk Bend Aquatic Center

[Student Name]

Southern New Hampshire University

QSO 420: Integrated Cost and Schedule Control

Budgeting Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe budget, accounts and reserves for the Sauk Bend Park District in this QSO 420 assignment are invented.
2

Six Control Accounts and Two Reserves: Budgeting the Sauk Bend Aquatic Center

Introduction

The Sauk Bend Park District's board approved $14.6 million for an outdoor aquatic center with a lazy river, two waterslides, a 50-meter competition pool and a bathhouse, to open on Memorial Day weekend 2028. A single total is not a budget that anyone can control. This assignment builds the budget from the work breakdown structure into control accounts, separates the reserves for known and unknown risks, spreads the construction budget over the schedule and sets the rules for using each reserve.

What this page is doingStates the budget's purpose.
3

From Work Breakdown Structure to Control Accounts

Globerson (1994) showed that the way a work breakdown structure is organized shapes how a project is understood and managed, because it determines how work is grouped, measured and assigned. The aquatic center's structure follows the physical parts of the facility, since each is built by different trades and has a different risk. The construction manager at risk built the guaranteed maximum price of $11.9 million bottom-up from its trade bids, and that price is divided into six control accounts, each with a responsible manager on the construction manager's staff.

Construction control accounts within the guaranteed maximum price

Control accountMain workBudget
1. Site work and utilitiesClearing, excavation, storm and sanitary lines, water service$1,650,000
2. Pools and mechanicalPool shells, piping, filtration, plaster, startup$4,200,000
3. Slides and lazy river featuresSlide towers and flumes, river current pumps, spray features$1,850,000
4. BathhouseBuilding, locker rooms, concessions, mechanical room$2,400,000
5. Electrical and lightingService, pool equipment power, site lighting$900,000
6. Landscaping, paving and fencingDeck, walks, parking, fence, plantings$900,000
Total construction$11,900,000

The construction manager's general conditions, fee and its own construction contingency of $450,000 are distributed across the accounts in proportion to their value, as the contract allows. The construction manager's contingency covers risks in its own work, such as trade coordination and estimating gaps, and is released only by the construction manager with notice to the district.

What this page is doingOrganizes the budget.
4

Owner Costs

Owner costs

ItemBudget
Design and construction administration$1,000,000
Furniture, fixtures and equipment, including lifeguard chairs and lockers$350,000
Testing, permits and health department review$150,000
Total owner costs$1,500,000

Most of the design fee was spent before construction, so the cost baseline that will be monitored during construction is chiefly the $11.9 million of construction work.

What this page is doingAdds the costs outside construction.
5

Owner Contingency

The owner contingency covers risks the district carries under the contract: unforeseen site conditions, design errors and changes the district itself requests. Touran (2003) proposed a probabilistic model in which contingency is set from the expected number and cost of changes, so that the owner can choose the probability of the contingency being sufficient rather than adopt a fixed percentage.

Identified owner risks

RiskProbabilityCost if it occursExpected cost
Rock or poor soil below the pool excavation35%$250,000$87,500
Design errors found during construction60%$180,000$108,000
Health department requires additional features25%$120,000$30,000
District-requested changes, such as added shade structures50%$150,000$75,000
Winter protection to hold the schedule30%$200,000$60,000
Total expected cost$360,500

The expected cost of these risks is about $360,000, but an expected value would be exceeded roughly half the time. Treating each risk as independent and simulating 100,000 combinations, the district would need about $580,000 to cover the identified risks with 85 percent confidence and about $700,000 for 95 percent. The board chose $700,000, because a fixed opening date leaves no time to stop and ask for more money mid-project. That is about 5.9 percent of construction, within the range Odeck (2004) found for overruns on smaller public projects, which tended to be proportionally larger than on big ones.

What this page is doingSizes the reserve for identified risks.
6

Management Reserve

A management reserve of $500,000 covers risks nobody has identified, such as a change in state pool regulations during construction or a contractor default. It is held by the park board outside the cost baseline and released only by board vote. Keeping it separate means that it cannot be used quietly to cover poor performance and that the cost baseline measures the work actually planned.

Total project budget

ComponentAmount
Construction, guaranteed maximum price$11,900,000
Owner costs$1,500,000
Owner contingency$700,000
Management reserve$500,000
Total$14,600,000
What this page is doingSets aside money for the unknown.
7

Time-Phased Baseline

The construction budget is spread over the 16 months of construction, from February 2027 to May 2028, following the schedule for each control account. Site work runs in months one to five; pool shells and piping in months four to ten, with plaster and startup in months fourteen and fifteen; the slides are engineered in months five to seven and installed in months thirteen to fifteen; the bathhouse runs from month four to month fifteen; electrical from month six to month fourteen; and landscaping in the last three months.

Cumulative planned value, construction

End of monthCalendar monthCumulative planned value
3April 2027$990,000
5June 2027$3,300,000
7August 2027$5,100,000
10November 2027$7,575,000
12January 2028$8,175,000
14March 2028$10,337,500
16May 2028$11,900,000

The curve rises steeply through the summer and fall of 2027, flattens from December to February, when concrete and plaster cannot be placed outdoors and only bathhouse and electrical work continue, and rises again in spring. That flat stretch matters for control: any pool work not finished by the end of November cannot simply be done in December.

What this page is doingSpreads the budget over the schedule.
8

Rules for Releasing Reserves

The construction manager may use its own contingency for its own risks and must report each use monthly. The district's project manager may approve owner contingency changes up to $50,000 each, the executive director up to $150,000 and the park board above that. Management reserve requires a board vote. Any use of owner contingency or reserve that changes a control account's budget goes through change control and updates the baseline, so that performance is always measured against the approved budget.

What this page is doingAssigns authority.
9

Conclusion

The aquatic center's $14.6 million is now a controllable budget: six construction control accounts with managers, owner costs, a $700,000 contingency sized from identified risks, a $500,000 reserve held by the board and a monthly baseline that shows the winter shutdown. The integrated baseline in Project One will add the schedule detail and the rules for measuring progress.

What this page is doingSummarizes the budget.
10

References

Globerson, S. (1994). Impact of various work-breakdown structures on project conceptualization. International Journal of Project Management, 12(3), 165-171. https://doi.org/10.1016/0263-7863(94)90032-9

Odeck, J. (2004). Cost overruns in road construction: What are their sizes and determinants? Transport Policy, 11(1), 43-53. https://doi.org/10.1016/S0967-070X(03)00017-9

Touran, A. (2003). Probabilistic model for cost contingency. Journal of Construction Engineering and Management, 129(3), 280-284. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:3(280)

What the QSO 420 Module 2 instructions ask for

The QSO 420 Module 2 assignment usually asks students to develop a project budget. Expect to estimate costs from the work breakdown structure, organize them into control accounts or cost accounts with responsible managers, determine contingency reserves for identified risks and a management reserve for unknown ones, time-phase the budget to create a cost baseline or S-curve and explain how reserves will be controlled. Strong assignments build the budget from the bottom up, keep contingency separate from management reserve and from the baseline, base contingency on an analysis of risks rather than a flat percentage alone, show how the time-phased baseline follows the schedule and state who may authorize the use of each reserve.

How this QSO 420 Module 2 budgeting assignment example is built

The assignment budgets the Sauk Bend Park District's outdoor aquatic center, a fictional $14.6 million project in Illinois. Inside the construction manager's $11.9 million guaranteed maximum price are six control accounts: site work and utilities, pools and mechanical systems, slides and lazy river features, the bathhouse, electrical and landscaping. Owner costs add $1.5 million. The owner's $700,000 contingency is sized from a probabilistic view of expected change orders, and a $500,000 management reserve is held by the board. The construction budget is spread monthly into an S-curve that flattens during the December to February concrete shutdown. Globerson on work breakdown structures, Touran on probabilistic contingency and Odeck on overruns support the method.

Where the QSO 420 Module 2 rubric puts the points

The QSO 420 budgeting assignment is commonly graded on a budget built from the work breakdown structure, sensible control accounts with owners, contingency sized from identified risks, a separate management reserve, a time-phased baseline that follows the schedule, clear rules for releasing reserves and correct use of research. The strongest assignments show where the budget's uncertainty lies and how each reserve relates to it. Credit drops when the budget is a single total, contingency is a flat percentage with no reasoning, reserves are mixed into the baseline, the S-curve ignores the schedule or no one is named to approve spending. Tables, clear writing and APA citations complete the grade.

QSO 420 Module 2 help: the mistakes that cost points

Start with the work breakdown structure and group its work packages into control accounts, each with one manager and a budget built from the packages below it. Add the costs that sit outside construction, such as design, equipment and permits. Then list the identified risks, estimate their likely cost and set the contingency from that analysis, considering how confident you want to be. Set a separate management reserve for risks nobody has identified, held by the sponsor or board. Spread each control account's budget over the months its work is scheduled and add them up to draw the S-curve. Finally, write down who may release each reserve and up to what amount. A common mistake is putting contingency inside each estimate; another is an S-curve that ignores seasonal stops.

Get QSO 420 Module 2 written to your instructions

Share the QSO 420 Module 2 instructions and describe your project. A writer builds the budget from the work breakdown structure into control accounts, sizes contingency from identified risks, sets a management reserve, time-phases the baseline into a monthly S-curve and explains who may release each reserve, citing research on estimating and contingency. Your first QSO 420 paper is free, sent in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 420 papers and related BS Operations Management samples

QSO 420 Module 2 questions, answered

Where can I find a free QSO 420 Module 2 Budgeting Assignment sample?

The complete QSO 420 Module 2 assignment is on this page: control accounts, reserves and an S-curve for an invented park district's aquatic center.

What is a control account?

A management control point where scope, budget, actual cost and schedule are integrated and compared to earned value, usually assigned to one responsible manager.

How does contingency differ from management reserve?

Contingency covers identified risks and is managed by the project; management reserve covers unidentified risks and is held outside the baseline by the sponsor or organization.

What is a cost baseline?

The approved, time-phased budget for the project's work, excluding management reserve, used to measure and monitor cost performance.

Why is a project budget shaped like an S-curve?

Because spending starts slowly during mobilization, accelerates during the main work and slows again during finishing, so cumulative cost rises in an S shape.