Six Control Accounts and Two Reserves: Budgeting the Sauk Bend Aquatic Center
[Student Name]
Southern New Hampshire University
QSO 420: Integrated Cost and Schedule Control
Budgeting Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Six Control Accounts and Two Reserves: Budgeting the Sauk Bend Aquatic Center
Introduction
The Sauk Bend Park District's board approved $14.6 million for an outdoor aquatic center with a lazy river, two waterslides, a 50-meter competition pool and a bathhouse, to open on Memorial Day weekend 2028. A single total is not a budget that anyone can control. This assignment builds the budget from the work breakdown structure into control accounts, separates the reserves for known and unknown risks, spreads the construction budget over the schedule and sets the rules for using each reserve.
From Work Breakdown Structure to Control Accounts
Globerson (1994) showed that the way a work breakdown structure is organized shapes how a project is understood and managed, because it determines how work is grouped, measured and assigned. The aquatic center's structure follows the physical parts of the facility, since each is built by different trades and has a different risk. The construction manager at risk built the guaranteed maximum price of $11.9 million bottom-up from its trade bids, and that price is divided into six control accounts, each with a responsible manager on the construction manager's staff.
Construction control accounts within the guaranteed maximum price
| Control account | Main work | Budget |
|---|---|---|
| 1. Site work and utilities | Clearing, excavation, storm and sanitary lines, water service | $1,650,000 |
| 2. Pools and mechanical | Pool shells, piping, filtration, plaster, startup | $4,200,000 |
| 3. Slides and lazy river features | Slide towers and flumes, river current pumps, spray features | $1,850,000 |
| 4. Bathhouse | Building, locker rooms, concessions, mechanical room | $2,400,000 |
| 5. Electrical and lighting | Service, pool equipment power, site lighting | $900,000 |
| 6. Landscaping, paving and fencing | Deck, walks, parking, fence, plantings | $900,000 |
| Total construction | $11,900,000 |
The construction manager's general conditions, fee and its own construction contingency of $450,000 are distributed across the accounts in proportion to their value, as the contract allows. The construction manager's contingency covers risks in its own work, such as trade coordination and estimating gaps, and is released only by the construction manager with notice to the district.
Owner Costs
Owner costs
| Item | Budget |
|---|---|
| Design and construction administration | $1,000,000 |
| Furniture, fixtures and equipment, including lifeguard chairs and lockers | $350,000 |
| Testing, permits and health department review | $150,000 |
| Total owner costs | $1,500,000 |
Most of the design fee was spent before construction, so the cost baseline that will be monitored during construction is chiefly the $11.9 million of construction work.
Owner Contingency
The owner contingency covers risks the district carries under the contract: unforeseen site conditions, design errors and changes the district itself requests. Touran (2003) proposed a probabilistic model in which contingency is set from the expected number and cost of changes, so that the owner can choose the probability of the contingency being sufficient rather than adopt a fixed percentage.
Identified owner risks
| Risk | Probability | Cost if it occurs | Expected cost |
|---|---|---|---|
| Rock or poor soil below the pool excavation | 35% | $250,000 | $87,500 |
| Design errors found during construction | 60% | $180,000 | $108,000 |
| Health department requires additional features | 25% | $120,000 | $30,000 |
| District-requested changes, such as added shade structures | 50% | $150,000 | $75,000 |
| Winter protection to hold the schedule | 30% | $200,000 | $60,000 |
| Total expected cost | $360,500 |
The expected cost of these risks is about $360,000, but an expected value would be exceeded roughly half the time. Treating each risk as independent and simulating 100,000 combinations, the district would need about $580,000 to cover the identified risks with 85 percent confidence and about $700,000 for 95 percent. The board chose $700,000, because a fixed opening date leaves no time to stop and ask for more money mid-project. That is about 5.9 percent of construction, within the range Odeck (2004) found for overruns on smaller public projects, which tended to be proportionally larger than on big ones.
Management Reserve
A management reserve of $500,000 covers risks nobody has identified, such as a change in state pool regulations during construction or a contractor default. It is held by the park board outside the cost baseline and released only by board vote. Keeping it separate means that it cannot be used quietly to cover poor performance and that the cost baseline measures the work actually planned.
Total project budget
| Component | Amount |
|---|---|
| Construction, guaranteed maximum price | $11,900,000 |
| Owner costs | $1,500,000 |
| Owner contingency | $700,000 |
| Management reserve | $500,000 |
| Total | $14,600,000 |
Time-Phased Baseline
The construction budget is spread over the 16 months of construction, from February 2027 to May 2028, following the schedule for each control account. Site work runs in months one to five; pool shells and piping in months four to ten, with plaster and startup in months fourteen and fifteen; the slides are engineered in months five to seven and installed in months thirteen to fifteen; the bathhouse runs from month four to month fifteen; electrical from month six to month fourteen; and landscaping in the last three months.
Cumulative planned value, construction
| End of month | Calendar month | Cumulative planned value |
|---|---|---|
| 3 | April 2027 | $990,000 |
| 5 | June 2027 | $3,300,000 |
| 7 | August 2027 | $5,100,000 |
| 10 | November 2027 | $7,575,000 |
| 12 | January 2028 | $8,175,000 |
| 14 | March 2028 | $10,337,500 |
| 16 | May 2028 | $11,900,000 |
The curve rises steeply through the summer and fall of 2027, flattens from December to February, when concrete and plaster cannot be placed outdoors and only bathhouse and electrical work continue, and rises again in spring. That flat stretch matters for control: any pool work not finished by the end of November cannot simply be done in December.
Rules for Releasing Reserves
The construction manager may use its own contingency for its own risks and must report each use monthly. The district's project manager may approve owner contingency changes up to $50,000 each, the executive director up to $150,000 and the park board above that. Management reserve requires a board vote. Any use of owner contingency or reserve that changes a control account's budget goes through change control and updates the baseline, so that performance is always measured against the approved budget.
Conclusion
The aquatic center's $14.6 million is now a controllable budget: six construction control accounts with managers, owner costs, a $700,000 contingency sized from identified risks, a $500,000 reserve held by the board and a monthly baseline that shows the winter shutdown. The integrated baseline in Project One will add the schedule detail and the rules for measuring progress.
References
Globerson, S. (1994). Impact of various work-breakdown structures on project conceptualization. International Journal of Project Management, 12(3), 165-171. https://doi.org/10.1016/0263-7863(94)90032-9
Odeck, J. (2004). Cost overruns in road construction: What are their sizes and determinants? Transport Policy, 11(1), 43-53. https://doi.org/10.1016/S0967-070X(03)00017-9
Touran, A. (2003). Probabilistic model for cost contingency. Journal of Construction Engineering and Management, 129(3), 280-284. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:3(280)
What the QSO 420 Module 2 instructions ask for
The QSO 420 Module 2 assignment usually asks students to develop a project budget. Expect to estimate costs from the work breakdown structure, organize them into control accounts or cost accounts with responsible managers, determine contingency reserves for identified risks and a management reserve for unknown ones, time-phase the budget to create a cost baseline or S-curve and explain how reserves will be controlled. Strong assignments build the budget from the bottom up, keep contingency separate from management reserve and from the baseline, base contingency on an analysis of risks rather than a flat percentage alone, show how the time-phased baseline follows the schedule and state who may authorize the use of each reserve.
How this QSO 420 Module 2 budgeting assignment example is built
The assignment budgets the Sauk Bend Park District's outdoor aquatic center, a fictional $14.6 million project in Illinois. Inside the construction manager's $11.9 million guaranteed maximum price are six control accounts: site work and utilities, pools and mechanical systems, slides and lazy river features, the bathhouse, electrical and landscaping. Owner costs add $1.5 million. The owner's $700,000 contingency is sized from a probabilistic view of expected change orders, and a $500,000 management reserve is held by the board. The construction budget is spread monthly into an S-curve that flattens during the December to February concrete shutdown. Globerson on work breakdown structures, Touran on probabilistic contingency and Odeck on overruns support the method.
Where the QSO 420 Module 2 rubric puts the points
The QSO 420 budgeting assignment is commonly graded on a budget built from the work breakdown structure, sensible control accounts with owners, contingency sized from identified risks, a separate management reserve, a time-phased baseline that follows the schedule, clear rules for releasing reserves and correct use of research. The strongest assignments show where the budget's uncertainty lies and how each reserve relates to it. Credit drops when the budget is a single total, contingency is a flat percentage with no reasoning, reserves are mixed into the baseline, the S-curve ignores the schedule or no one is named to approve spending. Tables, clear writing and APA citations complete the grade.
QSO 420 Module 2 help: the mistakes that cost points
Start with the work breakdown structure and group its work packages into control accounts, each with one manager and a budget built from the packages below it. Add the costs that sit outside construction, such as design, equipment and permits. Then list the identified risks, estimate their likely cost and set the contingency from that analysis, considering how confident you want to be. Set a separate management reserve for risks nobody has identified, held by the sponsor or board. Spread each control account's budget over the months its work is scheduled and add them up to draw the S-curve. Finally, write down who may release each reserve and up to what amount. A common mistake is putting contingency inside each estimate; another is an S-curve that ignores seasonal stops.
Get QSO 420 Module 2 written to your instructions
Share the QSO 420 Module 2 instructions and describe your project. A writer builds the budget from the work breakdown structure into control accounts, sizes contingency from identified risks, sets a management reserve, time-phases the baseline into a monthly S-curve and explains who may release each reserve, citing research on estimating and contingency. Your first QSO 420 paper is free, sent in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 420 papers and related BS Operations Management samples
- QSO 420 Module 1 Discussion: Why Cost and Schedule Must Be Controlled Together
- QSO 420 Module 3 Project One: The Integrated Baseline
- QSO 420 Module 4 Discussion: How to Measure Progress on a Pool
- QSO 420 Module 5 Variance Analysis Assignment: Month Seven, Five Control Accounts
- QSO 420 Module 6 Discussion: When SPI Stops Telling the Truth
- QSO 420 Module 7 Project Two: The Forecast and Recovery Plan
- QSO 420 Module 8 Discussion: The Board Wants a New Baseline
- ACC 318 Module 8 Earnings per Share Assignment: Basic and Diluted EPS With Convertibles and Options
- INT 433 Module 1 Discussion: Standardize or Adapt a Jar of Peanut Butter?
- HRM 300 Module 1 Discussion: Experience Is More Than Engagement
- ACC 315 Module 6 Discussion: A Fake Bank Change Request and IT Controls
QSO 420 Module 2 questions, answered
Where can I find a free QSO 420 Module 2 Budgeting Assignment sample?
The complete QSO 420 Module 2 assignment is on this page: control accounts, reserves and an S-curve for an invented park district's aquatic center.
What is a control account?
A management control point where scope, budget, actual cost and schedule are integrated and compared to earned value, usually assigned to one responsible manager.
How does contingency differ from management reserve?
Contingency covers identified risks and is managed by the project; management reserve covers unidentified risks and is held outside the baseline by the sponsor or organization.
What is a cost baseline?
The approved, time-phased budget for the project's work, excluding management reserve, used to measure and monitor cost performance.
Why is a project budget shaped like an S-curve?
Because spending starts slowly during mobilization, accelerates during the main work and slows again during finishing, so cumulative cost rises in an S shape.