QSO 420 Module 5 Variance Analysis Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 420 Module 5 Variance Analysis Assignment sample analyzes earned value by control account, applies variance thresholds and writes variance analysis reports with causes, impacts and corrective actions. SNHU QSO 420 (QSO-420) assigns variance analysis in Module 5, the point in its BS Operations Management cost and schedule course where earned value meets real causes. The project is the Sauk Bend Park District's outdoor aquatic center, an invented Illinois project at the end of August 2027, its seventh month. The paper shows that the overall indexes hide four separate problems with different causes and owners and writes the reports that send each one to the person who can fix it.

CourseQSO 420 Integrated Cost and Schedule Control
ModuleModule 5
Paper typeundergraduate assignment analyzing earned value by control account, applying variance thresholds and writing variance analysis reports with causes, impacts and corrective actions
LengthAbout 1,070 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 420 Module 5

1

Four Problems Behind One CPI: Variance Analysis at Month Seven of the Sauk Bend Aquatic Center

[Student Name]

Southern New Hampshire University

QSO 420: Integrated Cost and Schedule Control

Variance Analysis Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe earned value data, variances and causes for the Sauk Bend Park District in this QSO 420 assignment are invented.
2

Four Problems Behind One CPI: Variance Analysis at Month Seven of the Sauk Bend Aquatic Center

Introduction

This assignment analyzes earned value for the district's aquatic center at the close of August 2027, seven months into a 16-month build. Both the schedule and the budget are slipping, but the overall indexes do not say why or what to do. Kwak and Anbari (2012) note that agencies using earned value well push analysis down to the level where managers can act, rather than reporting project totals. The analysis therefore goes control account by control account, applies the variance thresholds set in the baseline and writes the variance reports that the thresholds require.

What this page is doingSets the date and the reason for going below the totals.
3

Project Totals

Project totals at month seven, construction

MeasureValue
Planned value$5,100,000
Earned value$4,620,000
Actual cost$4,980,000
Schedule varianceminus $480,000, minus 9.4%
Cost varianceminus $360,000, minus 7.8%
Schedule performance index0.91
Cost performance index0.93

The project has finished about nine-tenths of its planned work to date and paid about $1.08 for every dollar of work earned. Anbari (2003) cautions that indexes summarize performance but do not explain it, and Lipke et al. (2009) note that indexes early in a project are unstable and should be read with caution. At month seven, the totals are a signal to look further, not a forecast.

What this page is doingReports the overall position.
4

Control Account Analysis

Earned value by control account, thousands of dollars

Control accountPVEVACSVCVSPICPIReport required
1. Site work1,6501,6501,7900minus 1401.000.92Yes, cost over $100,000
2. Pools and mechanical2,1001,7201,840minus 380minus 1200.820.93Yes, both, critical path
3. Slides and features350300300minus 5000.861.00Yes, schedule over 10%
4. Bathhouse800750830minus 50minus 800.940.90Yes, cost over 10%
5. Electrical2002002200minus 201.000.91No, exactly 10%
Total5,1004,6204,980minus 480minus 3600.910.93

Landscaping has not started. Four accounts need variance reports, each with a different cause. Electrical's cost variance is exactly 10 percent of earned value and $20,000, so it does not exceed either threshold, but it will be watched.

What this page is doingBreaks the totals down.
5

Variance Report: Site Work

Cause. During excavation for the deep end of the competition pool, the contractor hit limestone about four feet higher than the geotechnical borings showed. Removing about 2,300 cubic yards of rock by hammering added about $140,000. The borings were taken 60 feet apart and missed the ledge.

Effect. The account is complete, so this is a one-time variance. It did not delay the critical path, because the contractor added a second hammer and finished excavation on time.

Responsibility and action. Under the contract, differing site conditions are the district's risk. The construction manager has submitted a change order for $140,000, which the district's project manager should forward to the executive director for approval from owner contingency, since it exceeds the project manager's $50,000 limit. Once approved, the account's budget rises to $1.79 million through change control and the cost variance closes, because the work was not in the original scope. Owner of action: district project manager, by September 15.

What this page is doingExplains the rock.
6

Variance Report: Pools and Mechanical

Cause. The structural engineer rejected the rebar shop drawings for the competition pool twice, for bar spacing at the wall-to-floor joint, costing about three weeks. Rebar for the main pool is therefore not complete and accepted, and its 20 percent milestone has not been earned. The crews were partly idle and then remobilized, and some bars already bent had to be refabricated, adding about $120,000.

Effect. The schedule variance of $380,000, 18 percent, is on the critical path. At the current pace the shells would finish about three weeks late, in the third week of December, inside the winter shutdown. Unless the time is recovered, shell work would stop until March, pushing plaster and startup past the opening. The cost variance appears to be continuing at a modest rate, since idle time and refabrication may not be over.

Responsibility and action. Shop drawing quality is the construction manager's responsibility, so the cost falls within its guaranteed maximum price and its own contingency, not the district's. The district's interest is the date. The construction manager should submit by September 10 a recovery schedule showing how the shells will be complete by November 30, for example with a second shotcrete crew and Saturday work at its own cost. Owner of action: construction manager's project executive.

What this page is doingExplains the critical delay.
7

Variance Report: Slides and Features

Cause. Two weeks of heavy rain in July saturated the soil at the slide tower foundations, and inspection of the footings was postponed. Shop drawings for the slides were approved on time.

Effect. The $50,000 schedule variance is 14 percent of planned value, over the percent threshold but small in dollars. The slides have about four weeks of float, and the foundations need to be finished only before the towers arrive in February, so the opening date is not at risk.

Action. Finish foundations by September 30. No cost action is needed. Owner: construction manager's site superintendent.

What this page is doingExplains a small schedule slip.
8

Variance Report: Bathhouse

Cause. The masonry trade's price, bid after the guaranteed maximum price was set, came in about $90,000 over the line in the construction manager's estimate, and the first month of block work used more labor than planned on the curved shower walls.

Effect. The $80,000 cost variance is 10.7 percent of earned value. If masonry productivity does not improve, the account could finish about $150,000 over. The bathhouse has about six weeks of float, so the small schedule variance does not threaten the opening.

Responsibility and action. The overrun falls within the guaranteed maximum price, as a buyout loss the construction manager carries. The construction manager should report by September 20 whether savings in other buyouts offset it and how the curved walls will be sequenced. Owner of action: construction manager's project manager for the bathhouse.

What this page is doingExplains the masonry overrun.
9

Conclusion

The project's SPI of 0.91 and CPI of 0.93 combine four separate stories: a one-time rock overrun that belongs to the district and should be moved into the baseline through a change order; a critical schedule problem on the pools that threatens the opening and must be recovered by November 30; a minor weather delay on the slides with float to absorb it; and a buyout overrun on the bathhouse that the construction manager carries. Only the second threatens the project's purpose, and the analysis makes it the first item for the September progress meeting.

What this page is doingSummarizes what the totals hid.
10

References

Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403

Kwak, Y. H., & Anbari, F. T. (2012). History, practices, and future of earned value management in government: Perspectives from NASA. Project Management Journal, 43(1), 77-90. https://doi.org/10.1002/pmj.20272

Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009

What the QSO 420 Module 5 instructions ask for

The QSO 420 Module 5 assignment usually asks students to analyze earned value data for a project at a status date. Expect to calculate schedule and cost variances and performance indexes for the project and for each control account or work package, compare them with variance thresholds, explain the causes of significant variances, assess their effects on the final cost and completion date, propose corrective actions and assign responsibility, often in the form of variance analysis reports. Strong assignments analyze below the project total, where causes become visible, separate one-time from continuing causes, distinguish who bears each variance under the contract, link schedule variances to the critical path and propose actions specific enough to be checked next month.

How this QSO 420 Module 5 variance analysis assignment example is built

The assignment analyzes month seven of the Sauk Bend Park District's aquatic center, a fictional Illinois project. Overall planned value is $5.10 million, earned value $4.62 million and actual cost $4.98 million, an SPI of 0.91 and CPI of 0.93. Four control accounts break the thresholds. Site work is $140,000 over because of unforeseen rock, which belongs in a change order against owner contingency. The pools are $380,000 behind after two rejected rebar submittals and $120,000 over, under the construction manager's risk. The slides are slightly behind on tower foundations, and the bathhouse is over on masonry. Electrical sits at exactly 10 percent and needs no report. Kwak and Anbari, Anbari and Lipke and colleagues support the method.

Where the QSO 420 Module 5 rubric puts the points

The QSO 420 variance analysis assignment is commonly marked on correct variances and indexes by control account, correct application of thresholds, causes explained rather than restated, effects on final cost and the critical path assessed, corrective actions that are specific and owned, attention to who bears each variance and clear reporting. The strongest assignments show how the project total hides different problems in different accounts. Credit drops when analysis stays at the total, variances are described as numbers without causes, all variances are treated as continuing, schedule variance is not linked to the critical path or actions have no owners. Tables, clear writing and APA citations complete the grade.

QSO 420 Module 5 help: the mistakes that cost points

Start with the totals, then go down to each control account and calculate its schedule and cost variances and indexes. Compare each with the thresholds, in percent and in dollars, and mark the accounts that need a report. For each, find the cause from field records, not from the numbers, and ask whether it will continue or was one-time. Say what it does to the final cost and whether it touches the critical path. Decide who bears it under the contract and propose a corrective action with an owner and a date. A common mistake is explaining a variance by restating it; another is averaging accounts with opposite problems into one comfortable index.

Get QSO 420 Module 5 written to your instructions

Share the QSO 420 Module 5 instructions and your earned value data. A writer calculates variances and indexes by control account, applies the thresholds, writes variance analysis reports with causes, effects on cost and schedule, corrective actions and owners and explains who bears each variance under the contract, citing earned value research. Your first QSO 420 paper is free, finished within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 420 papers and related BS Operations Management samples

QSO 420 Module 5 questions, answered

Where can I find a free QSO 420 Module 5 Variance Analysis Assignment sample?

The complete QSO 420 Module 5 assignment is on this page: earned value variance analysis by control account for an invented aquatic center.

What is a variance analysis report?

A report by a control account manager explaining a variance beyond threshold: its cause, its effect on cost and schedule, the corrective action and who will take it.

Why analyze variances by control account?

Because totals can combine accounts with different or opposite problems, hiding the specific causes that managers need to act on.

How do one-time and continuing variances differ?

A one-time variance results from an event that will not recur, such as unexpected rock; a continuing one reflects ongoing performance, such as a slow crew, and affects forecasts differently.

How does a schedule variance relate to the critical path?

A schedule variance on critical path work threatens the completion date directly, while one on work with float may be absorbed without delaying the project.