QSO 420 Module 7 Project Two Example

Reviewed by Portia Lambrick, MBA

This QSO 420 Module 7 Project Two sample forecasts final cost and completion with earned value and earned schedule, evaluates recovery options and processes changes through change control. SNHU QSO 420 (QSO-420) assigns this forecast and corrective action report in Module 7 of its BS Operations Management course on cost and schedule control. The project is the Sauk Bend Park District's aquatic center, an invented Illinois project whose pool shells are unfinished as the winter concrete shutdown begins. The report chooses the forecast that fits the causes, prices three ways to save the Memorial Day opening and decides which changes enter the baseline.

CourseQSO 420 Integrated Cost and Schedule Control
ModuleModule 7
Paper typeundergraduate project forecasting final cost and completion with earned value and earned schedule, evaluating recovery options and processing changes through change control
LengthAbout 1,170 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 420 Module 7

1

Five Weeks of Shells and a Winter in the Way: Forecast and Recovery Plan for the Sauk Bend Aquatic Center

[Student Name]

Southern New Hampshire University

QSO 420: Integrated Cost and Schedule Control

Project Two: Forecast and Recovery Plan

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe forecasts, options and costs for the Sauk Bend Park District in this QSO 420 project are invented.
2

Five Weeks of Shells and a Winter in the Way: Forecast and Recovery Plan for the Sauk Bend Aquatic Center

Introduction

This report takes stock of the Sauk Bend aquatic center on November 30, 2027, ten months into a 16-month build. The pool shells, which carry the critical path, are not finished, and outdoor concrete work stops for the winter on December 1. The report updates performance, forecasts the final cost and opening date, compares three ways to recover the pool schedule, processes pending changes and recommends a course of action to the park board.

What this page is doingSets the date and what the board must decide.
3

Performance at Month Ten

The $140,000 rock change order recommended at month seven was approved from owner contingency, raising the site work budget to $1.79 million and the construction budget at completion to $12.04 million.

Earned value at month ten, construction

MeasureValue
Budget at completion$12,040,000
Planned value$7,715,000
Earned value$7,010,000
Actual cost$7,380,000
Schedule varianceminus $705,000
Cost varianceminus $370,000
SPI0.91
CPI0.95
Earned schedule9.15 months
Schedule variance in timeminus 0.85 months

The cost variance comes from the pools, $200,000 over after continued rework on rebar and slow shotcrete production, the bathhouse, $130,000 over on masonry, and electrical, $40,000 over. All three are performance problems inside the construction manager's guaranteed maximum price, and all are continuing. The schedule variance is concentrated in the pools: about $615,000 of shell and piping work, roughly five weeks, remains.

What this page is doingUpdates the earned value picture.
4

Forecasting the Final Cost

Estimates at completion

MethodAssumptionEstimate
Actual cost plus remaining budgetPast overruns were one-time$12,410,000
Budget divided by CPICurrent cost efficiency continues$12,675,000
Remaining work divided by CPI times SPISchedule pressure will also raise cost$13,208,000

Lipke et al. (2009) show that forecasts from performance indexes become more reliable as a project advances and that statistical confidence limits can be placed around them; at 58 percent complete, the CPI has had time to settle. The variance analysis found that the remaining overruns reflect continuing performance, not one-time events, so the forecast that assumes the current CPI continues, about $12.68 million, is the most realistic. The third forecast would apply if the recovery effort itself added inefficiency, which the recovery plan below is designed to avoid.

Finishing within the $12.04 million budget would take a to-complete index of 1.08, meaning the rest of the job would have to be done 8 percent more efficiently than planned, against a current performance 5 percent worse. The budget will not be met. Under the guaranteed maximum price, however, the overrun above $12.04 million falls first on the construction manager's own contingency of $450,000 and beyond that on the construction manager itself, so the district's cost exposure is limited to the changes it approves.

What this page is doingChooses an estimate at completion.
5

Forecasting the Opening Date

Earned schedule puts the project 0.85 months behind, and a forecast based on the time-based index would put completion at about 17.5 months, mid-June, three weeks after the planned opening. Vandevoorde and Vanhoucke (2006) found that earned schedule gives more reliable duration forecasts than the classic schedule indexes, especially later in a project, so this forecast should be taken seriously.

The critical path gives the more specific answer. About five weeks of shell work remain. If it stops on December 1 and resumes in March, the shells finish about April 5, piping tests take two weeks, plaster cannot finish before about May 10, filling and chemical startup take two weeks and the health inspection follows: the opening would slip to about June 10.

What this page is doingUses the critical path and earned schedule.
6

Recovery Options

Recovery options for the pool shells

OptionWhat it doesCostOpeningMain risk
A. Heated enclosuresFinish shells in December under enclosures and blankets$185,000May 27, on scheduleExtreme cold stops work for days
B. Wait for springResume shells in MarchNo added construction costAbout June 10Lost early-season revenue of about $140,000
C. Split the poolsFinish the leisure pool and lazy river shells in December with lighter protection; competition pool in March$70,000Partial opening May 27; competition pool about June 10Swim team season delayed; two startups

Option B costs nothing in construction but would forfeit about two weeks of the season, including Memorial Day weekend, when the district expects about $140,000 in admissions and season pass sales and has promised pass holders an opening date. The construction manager would owe liquidated damages of $2,000 a day for late substantial completion, about $58,000, but that would not cover the district's loss or its reputation. Option C protects part of the opening for less money but delays the competition pool, which the local swim team needs for its season. Option A is the only one that keeps the full opening.

What this page is doingCompares three ways to protect the opening.
7

Who Pays

The delay arose from rejected shop drawings, the construction manager's responsibility, so the construction manager would carry the full cost of Option A under a strict reading of the contract and would face liquidated damages if it did nothing. The construction manager has argued that July's rain, which no one controls, contributed about a week. After negotiation, the parties agreed to share Option A's $185,000 at 60 percent for the construction manager and 40 percent, $74,000, for the district, with the construction manager waiving any weather claim. The district's share buys certainty about the opening and avoids a dispute.

What this page is doingAllocates the recovery cost.
8

Change Control

Change requests at month ten

ChangeCostDecisionBaseline effect
CO-02 District share of winter protection$74,000Approve; executive directorPools account budget rises by $74,000
CO-03 Pool lift required by health department review$38,000Approve; project managerPools account budget rises by $38,000
CO-04 Shade structures requested by two board members$96,000Defer; board to decide in springNone now

Each approved change raises the pools account's budget for the added scope, not to cover existing variances, so the cost variance on the original work remains visible. The construction budget at completion becomes $12.152 million, and the forecast, applying the current CPI to the revised budget, about $12.79 million. The shade structures are deferred because they are not needed to open and can be added after the season.

What this page is doingProcesses pending changes.
9

Reserves

Touran (2003) frames contingency as a probability of being sufficient rather than a fixed sum, which makes it useful to ask, at each stage, what remains against the risks still ahead. Owner contingency has now funded the rock removal, $140,000, the winter protection share, $74,000, and the pool lift, $38,000, for $252,000 of the $700,000. The remaining $448,000 must cover any design errors still undiscovered and spring weather risk to plaster, which together have an expected cost of about $150,000. The board's $500,000 management reserve is untouched.

What this page is doingReports what is left.
10

Recommendation

The board should approve Option A, the shared cost of heated enclosures, and change orders CO-02 and CO-03, and defer CO-04. The district should require the construction manager to report shell progress weekly in December, with earned schedule and critical path updates, and should treat the forecast cost of about $12.79 million as above the revised guaranteed maximum price, so that any further overrun is the construction manager's. If extreme cold stops work for more than ten days, the fallback is Option C for the competition pool only.

What this page is doingStates the decision for the board.
11

References

Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009

Touran, A. (2003). Probabilistic model for cost contingency. Journal of Construction Engineering and Management, 129(3), 280-284. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:3(280)

Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), 289-302. https://doi.org/10.1016/j.ijproman.2005.10.004

What the QSO 420 Module 7 instructions ask for

QSO 420 Project Two usually asks students to analyze a project's performance at a status date, forecast its outcome and recommend corrective action. Expect to calculate earned value measures and, in many versions, earned schedule; produce several estimates at completion and choose one with reasons; calculate the to-complete performance index; forecast the completion date; identify and evaluate corrective actions or recovery options; process change requests through change control and update the baseline appropriately; and report to sponsors with recommendations. Strong projects tie each forecast method to the causes found in variance analysis, test whether the budget can still be met, compare options on cost, schedule and risk, show who bears which costs under the contract and keep the baseline honest.

How this QSO 420 Module 7 project two example is built

The project reports on the Sauk Bend Park District's aquatic center, a fictional Illinois project, at month ten. With the rock change order approved, the budget is $12.04 million; planned value of $7.715 million, earned value of $7.01 million and actual cost of $7.38 million give an SPI of 0.91 and a CPI of 0.95, and earned schedule puts the project 0.85 months behind. Estimates at completion range from $12.41 million to $13.21 million; $12.68 million is chosen because the remaining overruns reflect continuing performance. A to-complete index of 1.08 shows the budget cannot be met. Heated enclosures costing $185,000, shared with the construction manager, are recommended to finish the shells and keep the opening. Lipke and colleagues, Vandevoorde and Vanhoucke and Touran support the analysis.

Where the QSO 420 Module 7 rubric puts the points

Instructors grading QSO 420 Project Two look at correct earned value and earned schedule calculations, several estimates at completion with a justified choice, a correctly interpreted to-complete index, a completion forecast tied to the critical path, recovery options compared on cost, time and risk, changes processed through change control with baseline updates and a clear report with recommendations. Projects that score highest connect the chosen forecast to the causes of variance and show who pays for each option. Credit drops when one forecast formula is applied without reasoning, completion is forecast from SPI alone, recovery options lack costs, changes bypass control or the baseline is adjusted to absorb variances. Tables, clarity and APA citations count too.

QSO 420 Module 7 help: the mistakes that cost points

Start with the numbers at the status date: planned value, earned value and actual cost, then variances, indexes and earned schedule. Calculate several estimates at completion, such as budget divided by CPI, actual cost plus remaining budget and a version that also reflects schedule pressure, and choose the one whose assumption matches the causes you found. Calculate the to-complete index to see whether the remaining work can meet the budget. Forecast the finish from the critical path, using earned schedule as a check. List recovery options, price each, estimate its effect on the date and its risks and say who pays under the contract. Run each change request through change control and update the baseline only for approved scope changes. A common mistake is choosing a forecast because it looks best; another is quietly moving budget to cover overruns.

Get QSO 420 Module 7 written to your instructions

Upload the QSO 420 Project Two guidelines and your status data. A writer calculates current performance, earned schedule and several estimates at completion, chooses the one that fits the causes, computes the to-complete index, compares recovery options on cost, time and risk, runs pending changes through change control and writes the report for the sponsor, citing research. Your first QSO 420 project is free, completed within roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 420 papers and related BS Operations Management samples

QSO 420 Module 7 questions, answered

Where can I find a free QSO 420 Module 7 Project Two sample?

This page holds the complete QSO 420 Project Two: forecast, recovery options and change control for an invented park district's aquatic center.

Which estimate at completion should be used?

The one whose assumption fits the causes of variance: budget divided by CPI if performance will continue, actual cost plus remaining budget if the variance was one-time, and a CPI times SPI version if schedule pressure will raise costs.

What is the to-complete performance index?

The cost efficiency the remaining work must achieve to finish within a target, calculated as remaining work divided by remaining funds; values well above 1.0 mean the target is unrealistic.

What is corrective action in project control?

A deliberate change in how the remaining work is performed, such as adding crews or resequencing, to bring future performance back in line with the plan.

When should a baseline be updated?

Only for approved changes in scope or plan funded through change control, never to remove variances caused by performance.