QSO 420 Module 3 Project One Example

Reviewed by Portia Lambrick, MBA

This QSO 420 Module 3 Project One sample builds an integrated performance measurement baseline with the schedule, control accounts, earned value measurement methods, variance thresholds and change control. SNHU QSO 420 (QSO-420) asks for this baseline in Module 3 of its cost and schedule control course in the BS Operations Management, once budgets are in place. The project is the Sauk Bend Park District's outdoor aquatic center, an invented Illinois project with a winter concrete shutdown and a fixed Memorial Day opening. The project maps the critical path, loads each control account, chooses how progress will be measured for each kind of work and sets the rules that will trigger an explanation.

CourseQSO 420 Integrated Cost and Schedule Control
ModuleModule 3
Paper typeundergraduate project building an integrated performance measurement baseline with schedule, control accounts, earned value measurement methods, thresholds and change control
LengthAbout 1,040 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 420 Module 3

1

One Baseline for Money and Time: The Performance Measurement Baseline for the Sauk Bend Aquatic Center

[Student Name]

Southern New Hampshire University

QSO 420: Integrated Cost and Schedule Control

Project One: Integrated Baseline

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe schedule, control accounts and methods for the Sauk Bend Park District in this QSO 420 project are fictional.
2

One Baseline for Money and Time: The Performance Measurement Baseline for the Sauk Bend Aquatic Center

Introduction

The budgeting assignment divided the Sauk Bend aquatic center's $11.9 million construction budget into six control accounts and spread it over 16 months. That budget becomes a performance measurement baseline only when it is tied to the schedule and to rules for measuring the work done. This project sets out the schedule and its critical path, links the control accounts to it, chooses an earned value measurement method for each kind of work, sets the variance thresholds and describes how the baseline will be reviewed and changed.

What this page is doingStates what the baseline must do.
3

Schedule and Critical Path

Construction runs from February 1, 2027, to substantial completion on May 12, 2028, with opening on Saturday, May 27, 2028. The critical path runs through the pools: site work and excavation from February to June 2027, pool shells and underground piping from May to November, piping pressure tests in December, plaster in April 2028 once nights stay above about 50 degrees, then two weeks of filling and chemical startup and the health department's inspection in mid-May.

Two features make the schedule unusual. First, concrete for the pool shells cannot be placed outdoors from December to February without heated enclosures, so shell work left over when December arrives waits until March. Second, plaster depends on weather, not on the contract, and cannot be started earlier to recover time. The bathhouse and electrical work run in parallel and have about six weeks of float, and the slides, which arrive in February 2028, have about four weeks.

The practical meaning is that the pool shells must be complete by November 30, 2027. Every other date can absorb some delay; that one cannot without costly winter protection.

What this page is doingIdentifies what drives the opening date.
4

Linking Budget and Schedule

Control accounts loaded onto the schedule

Control accountBudgetMonths of workCritical
1. Site work and utilities$1,650,0001 to 5Yes, through excavation
2. Pools and mechanical$4,200,0004 to 10, then 14 to 15Yes
3. Slides and features$1,850,0005 to 7, then 13 to 15No, about four weeks of float
4. Bathhouse$2,400,0004 to 15No, about six weeks of float
5. Electrical and lighting$900,0006 to 14Partly, pool equipment power
6. Landscaping, paving and fencing$900,00014 to 16No

Each control account's budget is spread over the activities that perform its work, so that the planned value in any month is the budget of the work scheduled for that month. The cumulative planned value is $5.10 million at the end of August 2027, month seven, and $7.575 million at the end of November, month ten, when the pool shells must be complete.

What this page is doingLoads the control accounts.
5

Earned Value Measurement Methods

Anbari (2003) notes that earned value is only as reliable as the way progress is measured, and Kim et al. (2003), studying organizations that had adopted earned value, linked how well it was accepted and used to whether users understood it and trusted the data behind it. The methods below were chosen so that progress is credited for objective evidence of work, never for money spent.

Measurement method by control account

Control accountMethodEvidence
Site work and utilitiesPhysical unitsCubic yards excavated, feet of pipe installed and tested
Pools and mechanicalWeighted milestonesExcavation 10%, rebar 20%, shotcrete shell 30%, piping and test 20%, plaster 10%, startup 10%
Slides and featuresWeighted milestonesShop drawings approved 10%, fabrication 40% at delivery, erection 40%, testing 10%
BathhousePercent complete by schedule of valuesLine items on the construction manager's pay application, verified on site
Electrical and lightingPercent complete by schedule of valuesSame, with inspection sign-offs
Landscaping, paving and fencingPhysical unitsSquare yards paved, feet of fence, plantings installed

The slide supplier's deposit, paid in month five, is an actual cost but earns no value by itself; value is earned only when shop drawings are approved. Weighted milestones for the pools mean that a pool earns its 30 percent for the shell only when the shell is complete and accepted, not as concrete is poured, which prevents optimistic partial credit on the critical path. Percent complete is used only where the schedule of values gives an objective basis that the district's inspector verifies each month.

What this page is doingChooses how progress is credited.
6

Variance Thresholds

A control account manager must submit a variance analysis report when the cumulative cost variance exceeds 10 percent of the earned value or $100,000, or when the cumulative schedule variance exceeds 10 percent of the planned value or $150,000. Any variance on the pools account, which carries the critical path, requires a report at 5 percent. Each report states the cause, the effect on the opening date and the final cost, the corrective action and who will take it.

Kwak and Anbari (2012) describe how government agencies that use earned value rely on such thresholds to focus management attention on the few accounts that need it, rather than reviewing every number every month.

What this page is doingSets the rules for explanation.
7

Baseline Review

Before construction begins, the district's project manager, the construction manager's project executive and each control account manager will hold a baseline review to confirm that every activity in the schedule belongs to one control account, that budgets add up to the guaranteed maximum price, that measurement methods are understood the same way by both parties and that the planned value curve matches the schedule. The review will also confirm that the construction manager's contingency is held outside the control account budgets.

What this page is doingConfirms the baseline before use.
8

Change Control

The baseline may change only for approved changes in scope or for owner contingency or reserve released through the approval rules set in the budget. Each change order states the control accounts affected, the budget moved and the schedule effect, and the baseline is updated the month it is approved. Variances may not be cleared by moving budget between accounts or by re-planning work already performed. A log of every baseline change will be reported to the park board each quarter.

What this page is doingProtects the baseline.
9

Conclusion

The aquatic center now has one baseline for money and time: a critical path that runs through the pools and a November deadline for the shells, six control accounts loaded onto the schedule, measurement methods that credit only verified work, thresholds that call for explanations early and rules that keep the baseline from being rewritten to hide problems.

What this page is doingSummarizes the baseline.
10

References

Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403

Kim, E., Wells, W. G., Jr., & Duffey, M. R. (2003). A model for effective implementation of Earned Value Management methodology. International Journal of Project Management, 21(5), 375-382. https://doi.org/10.1016/S0263-7863(02)00049-2

Kwak, Y. H., & Anbari, F. T. (2012). History, practices, and future of earned value management in government: Perspectives from NASA. Project Management Journal, 43(1), 77-90. https://doi.org/10.1002/pmj.20272

What the QSO 420 Module 3 instructions ask for

QSO 420 Project One usually asks students to build an integrated cost and schedule baseline for a project. Expect to develop or summarize the schedule and critical path, define control accounts and work packages, assign budgets and time-phase them, choose methods for measuring earned value, set variance thresholds for reporting, describe how the baseline will be reviewed and approved and set rules for changing it. Strong projects show how the schedule and budget are linked through the same work, choose measurement methods that match the nature of each kind of work, avoid methods that reward spending rather than progress, set thresholds that trigger analysis before problems grow and explain how changes are approved so that the baseline stays meaningful.

How this QSO 420 Module 3 project one example is built

The project builds the baseline for the Sauk Bend Park District's aquatic center, a fictional Illinois project. The critical path runs from excavation through pool shells, piping pressure tests, plaster, fill and chemical startup and the health department inspection to a Memorial Day opening, with the December to February concrete shutdown as a hard window. The six control accounts are loaded onto the schedule. Measurement methods range from installed quantities for site work and weighted milestones for the pools to percent complete by schedule of values for the bathhouse. Thresholds of 10 percent or $100,000 for cost and $150,000 for schedule trigger variance reports. Kim, Wells and Duffey, Anbari and Kwak and Anbari inform the design.

Where the QSO 420 Module 3 rubric puts the points

Instructors grading QSO 420 Project One look at a schedule with a correctly identified critical path and constraints, control accounts linked to the schedule, a correctly time-phased budget, earned value measurement methods suited to each kind of work, sensible variance thresholds, a baseline review and clear change control rules. Projects that score highest explain why each measurement method resists manipulation and how the baseline protects the fixed date. Credit drops when progress is measured by spending, percent complete is an estimate with no basis, thresholds are missing or arbitrary, schedule constraints are ignored or the baseline can be changed without approval. Tables, clarity and APA citations count too.

QSO 420 Module 3 help: the mistakes that cost points

Start with the schedule: identify the critical path and any hard windows, such as seasons or fixed dates. Link each control account's budget to the activities that perform its work, so cost and time share one baseline. Then choose how progress will be measured for each kind of work: physical quantities where work is countable, weighted milestones where it moves through clear stages, percent complete only where there is an objective basis such as a schedule of values, zero or 100 percent for short items. Set thresholds in both percent and dollars that require a variance explanation. Describe how the baseline will be reviewed before use and how it can be changed. A common mistake is measuring progress by money spent; another is letting the baseline be revised to absorb variances.

Get QSO 420 Module 3 written to your instructions

Upload the QSO 420 Project One guidelines and your project. A writer builds the integrated baseline: critical path and key constraints, control accounts loaded onto the schedule, an earned value measurement method for each kind of work, variance thresholds, a baseline review and change control rules, citing research on earned value implementation. Your first QSO 420 project is free, ready in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 420 papers and related BS Operations Management samples

QSO 420 Module 3 questions, answered

Where can I find a free QSO 420 Module 3 Project One sample?

This page holds the complete QSO 420 Project One: an integrated baseline for an invented park district's aquatic center.

What is a performance measurement baseline?

The approved, integrated scope, schedule and budget against which project performance is measured, excluding management reserve.

What are earned value measurement methods?

Rules for crediting earned value as work progresses, such as physical units complete, weighted milestones, percent complete, fixed formulas like 0/100 or 50/50 and level of effort.

What is a variance threshold?

A limit on cost or schedule variance, often in both percent and dollars, beyond which a control account manager must explain the cause and corrective action.

Why control changes to the baseline?

Because a baseline revised to absorb variances no longer measures performance, so changes must be authorized, documented and limited to real changes in scope or plan.