| Course | QSO 355 Resource Estimating and Scheduling |
|---|---|
| Module | Module 1 |
| Paper type | undergraduate discussion post explaining why project estimates are biased and how outside data improves them |
| Length | About 380 words, 3 pages |
| Format | APA 7 student paper |
| School | Southern New Hampshire University |
| Program | BS Operations Management |
| Updated | October 2026 |
Free sample paper for QSO 355 Module 1
Module One Discussion
Four Builds Over, Two on Target
I am the assistant technical director at Cedar Row Repertory Theater, a nonprofit company in Milwaukee that produces six mainstage shows a season on one stage. Our shop has nine carpenters, two welders and three scenic painters, plus the technical director and me. Every set is a project with a fixed end: the first technical rehearsal, when the actors come onstage with the scenery, and it cannot move because tickets are already sold.
Last season four of our six builds used more labor than the technical director estimated: 12, 18, 24 and 31 percent more. The two that came in on target were box sets, rooms with walls and a door or two. The four that ran over each had something we had not built before: a raked deck, a moving staircase, a flown ceiling and a revolve. Each time, the estimate was made the same careful way, by listing every piece and the hours it should take, and each time the overrun was blamed on that show's particular troubles. Buehler et al. (1994) found the same habit in people predicting when they would finish their own work: they thought about the plan ahead and rarely drew on memories of earlier tasks, even when those memories showed their past predictions had been too hopeful.
Kahneman and Lovallo (1993) call this the inside view: forecasting from the details of the case in hand, which leads people to imagine the plan going as intended and to treat each overrun as a one-off. The outside view asks instead how long projects of this kind usually take. Flyvbjerg (2006) turned that idea into reference class forecasting: find a class of similar past projects, see how far their estimates were off and adjust the new estimate by that amount. For us, that would mean adding about 20 percent to any build with a mechanism we have not built before, because that is what the record shows.
The trouble is that we keep timesheets by show, not by type of scenery, so the record is thin. Starting this season, carpenters will log hours against categories such as platforms, walls, mechanisms and specialty pieces.
What records does your organization keep that could tell you how long the next project will really take?
References
Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the "planning fallacy": Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366-381. https://doi.org/10.1037/0022-3514.67.3.366
Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5-15. https://doi.org/10.1177/875697280603700302
Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17-31. https://doi.org/10.1287/mnsc.39.1.17
What the QSO 355 Module 1 instructions ask for
QSO 355 begins with introductions and the problem of estimating: how much work a project needs, how many people and how long. Students are usually asked to describe a project they know and discuss how its resources and durations were estimated and how accurate the estimates turned out to be. Strong posts give actual figures for estimates and results, identify the method used, explain the sources of error, including optimism, missing work and pressure to fit a budget, and suggest how estimates could be improved, drawing on research about estimating. Replies should ask a classmate what data their organization keeps from past projects or who sets the estimates they work to.
How this QSO 355 Module 1 discussion example is built
The post introduces the course's example, the scenic shop of Cedar Row Repertory Theater, a fictional nonprofit in Milwaukee whose crew of fifteen builds six sets a season. The technical director estimates each build by listing its pieces and the hours each should take. Last season four of six builds ran over, by 12 to 31 percent, and the two that did not were simple box sets. The post separates the inside view, a careful task list for each show, from the outside view, how long builds of the same kind actually took, using Kahneman and Lovallo on bold forecasts and Flyvbjerg on reference class forecasting, and proposes logging hours by type of scenery.
Where the QSO 355 Module 1 rubric puts the points
Marks in the first QSO 355 thread go to a specific example with real estimates and outcomes, an accurate description of how the estimates were made, a sound explanation of why they missed, use of estimating concepts such as optimism bias and the inside and outside views, a practical improvement, cited research applied to the case and replies that help classmates examine their own estimates. The strongest posts quantify the errors and look for a pattern across projects. Posts lose marks when they blame overruns on effort alone, give no numbers, describe estimating only in general terms or answer peers with a greeting. Grammar and APA citations count as well.
QSO 355 Module 1 help: the mistakes that cost points
Choose a project whose estimate and actual result you know, even roughly: a renovation, an event, a software release, a move. Write down how the estimate was made, who made it and what it assumed. Then compare it with what happened and ask whether the error was random or a pattern; most project estimates miss on the low side. Consider the inside view, the detailed plan for this project, against the outside view, how long similar projects took. Suggest one concrete improvement, such as keeping records of actual hours. A common mistake is treating an overrun as a failure of discipline rather than of estimating; another is offering no figures. Close by asking classmates what records their organizations keep.
Get QSO 355 Module 1 written to your instructions
Paste the QSO 355 Module 1 prompt and describe work you have estimated or watched others estimate. A writer explains how the estimates were made, why they missed, what the inside and outside views would each say and how past data could improve the next estimate, using estimating research, and asks QSO 355 classmates a question. Your first QSO 355 post is free, ready in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 355 papers and related BS Operations Management samples
- QSO 355 Module 2 Estimating Assignment: Three Ways to Estimate a Pirate Ship
- QSO 355 Module 3 Project One: A Resource-Loaded Schedule for the Fall Builds
- QSO 355 Module 4 Discussion: Three-Point Estimates for the Paint Deck
- QSO 355 Module 5 Resource Leveling Assignment: Two Builds, Nine Carpenters
- QSO 355 Module 6 Discussion: Overtime or Over-Hire?
- QSO 355 Module 7 Project Two: Schedule Risk and Crashing Before First Tech
- QSO 355 Module 8 Discussion: Telling the Artistic Director the Estimate Grew
- HRM 225 Module 2 Environmental Scan Assignment: Forces Reshaping Credit Union Work
- QSO 325 Module 6 Discussion: Mistake-Proofing the Hardware Kits
- HRM 310 Module 2 Labor Law Assignment: What the National Labor Relations Act Protects
- OL 326 Module 1 Discussion: Business and Society
QSO 355 Module 1 questions, answered
Where can I find a free QSO 355 Module 1 Discussion sample?
This page holds the full QSO 355 Module 1 post: why an invented theater scenic shop's labor estimates run short and how to fix them.
Why do project estimates run short?
Planners tend to focus on the specific plan, assume things go as intended and overlook delays and extra work, and pressure to fit budgets pushes estimates down further.
What is the inside view?
Estimating a project from its own details, tasks and plans, which tends to be optimistic because it imagines the project going as planned.
What is reference class forecasting?
Estimating a project by looking at the actual outcomes of a class of similar past projects and adjusting from that distribution, rather than building up from the plan alone.
What is a basis of estimate?
A record of how an estimate was made: the method, data, assumptions and exclusions, so that others can judge and update it.