QSO 355 Module 7 Project Two Example

Reviewed by Portia Lambrick, MBA

This QSO 355 Module 7 Project Two sample analyzes schedule risk with Monte Carlo simulation, measures the probability of meeting a deadline and chooses crashing options by cost and effect. SNHU QSO 355 (QSO-355) assigns this project in Module 7, near the close of its BS Operations Management course on estimating and scheduling. The project is the final 22 working days of the Pirates of Penzance build at Cedar Row Repertory Theater, an invented Milwaukee company. The single-number schedule shows two days to spare; the simulation shows a 41 percent chance of being ready. The paper explains the gap and buys the probability back for $12,600.

CourseQSO 355 Resource Estimating and Scheduling
ModuleModule 7
Paper typeundergraduate project analyzing schedule risk with Monte Carlo simulation, measuring the probability of meeting a deadline and choosing crashing options by cost and effect
LengthAbout 1,080 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 355 Module 7

1

Two Days of Slack and a 41 Percent Chance: Schedule Risk and Crashing for the Cedar Row Pirates Build

[Student Name]

Southern New Hampshire University

QSO 355: Resource Estimating and Scheduling

Project Two: Schedule Risk Analysis

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe durations, probabilities and costs for Cedar Row Repertory Theater in this QSO 355 project are invented.
2

Two Days of Slack and a 41 Percent Chance: Schedule Risk and Crashing for the Cedar Row Pirates Build

Introduction

On Friday, January 28, Cedar Row Repertory Theater's shop finished its Uncle Vanya load-in and turned the whole crew to The Pirates of Penzance. First technical rehearsal is Wednesday, March 1, and cannot move: the cast, orchestra and lighting designer are booked, and preview tickets are sold. From Monday, January 31, the shop has 22 working days. The set cannot load in before Monday, February 21, day 16, because Vanya occupies the stage until it closes the day before. This project asks how likely the shop is to be ready and what it would cost to raise that likelihood.

What this page is doingStates the deadline and the question.
3

The Remaining Network

Six activities remain. The ship hull and decks (A) must be finished and then painted (C). The masts and rigging (B) are built in parallel and fitted at load-in. The rock unit (D) is built in parallel and then painted along with the backdrop (E). Load-in (F) can start only when A and C, B, and D and E are all complete and the stage is free on day 16. With the most likely durations, the ship path takes 10 + 5 = 15 days, the rock path 7 + 8 = 15 days and the masts 8 days, so everything is ready at the end of day 15, load-in runs days 16 to 20 and the set is ready two days before first tech.

Three-point estimates in working days

ActivityOptimisticMost likelyPessimisticSource of the pessimistic case
A. Ship hull and decks81015Curved hull ribs need refitting
B. Masts and rigging6812Climbing points fail load test
C. Paint ship458Faux wood grain redone
D. Rock unit5710Foam carving slower than planned
E. Paint rock and backdrop6811Sky wash stripped and redone
F. Load-in457Turntable alignment on stage

The estimates came from the lead carpenter, the charge scenic artist and the technical director, each asked for the realistic problem behind the pessimistic value.

What this page is doingDescribes the work left.
4

Why a Single-Number Schedule Misleads

Malcolm et al. (1959), introducing PERT, calculated a project's expected time from the expected times of activities on the critical path. That method understates risk when several paths of similar length merge, because the next activity cannot start until the latest of them finishes, and a delay on any path delays the merge. Here two paths of exactly 15 days and a third of 8 merge before load-in. Williams (2003) argues that simulation is the practical way to capture such effects and that project managers should report distributions of outcomes rather than single dates. The analysis therefore uses Monte Carlo simulation.

What this page is doingExplains the merge effect.
5

Simulation Results

The simulation drew a duration for each activity from a triangular distribution on its three points, ran the network 20,000 times and recorded the day load-in finished.

Simulated finish of load-in, current plan

MeasureResult
Probability of finishing by day 2241%
Median finishDay 22.4
80th percentile finishDay 23.8
95th percentile finishDay 25.2
Ship path critical63% of runs
Rock path critical31% of runs
Masts critical0% of runs
No path critical, stage date governs6% of runs

The deterministic plan shows two days of slack, but the shop has only about a 41 percent chance of being ready on March 1. The median run finishes almost half a day late. The ship path drives the result most often, the rock path about a third of the time, and the masts never: their range ends well before the other paths. Missing first tech by a day would cost the paid technical rehearsal day, about $11,000 in musicians, crew and designers, and compress the remaining tech schedule.

What this page is doingReports the probability of meeting the deadline.
6

Crashing Options

Three options were costed. A second painting shift, two painters working evenings for two weeks, shortens both painting activities by about a quarter, at $5,400. Two over-hire carpenters on the hull for its first two weeks shorten activity A by about a fifth, at $7,200. An expanded load-in crew of four stagehands shortens load-in to a range of 3 to 5 days, at $6,000. Buying ready-made rigging for the masts, at $3,800, was rejected without simulation, because the masts are never critical.

Probability of finishing by day 22 under each option

OptionCostProbability80th percentile
Current plan$041%Day 23.8
Second painting shift$5,40077%Day 22.2
Hull over-hire$7,20068%Day 22.6
Expanded load-in crew$6,00072%Day 22.4
Painting shift and load-in crew$11,40094%Day 20.8
Painting shift and hull over-hire$12,60097%Day 21.1
All three$18,600Nearly 100%Day 19.5

The painting shift is the best single option, because it shortens both of the paths that are ever critical. No single option reaches 90 percent. The gains are not additive: the painting shift and the hull over-hire together reach 97 percent, more than either alone suggests, because the second removes the ship path's remaining tail once the first has shortened the rock path.

What this page is doingTests ways to raise the probability.
7

Recommendation

The shop should set a target of at least 95 percent, given the cost of losing a technical rehearsal day, and choose the painting shift and the hull over-hire for $12,600. That combination reaches about 97 percent, costs $1,200 more than the painting shift with the load-in crew, which falls short of the target at 94 percent, and is $6,000 cheaper than doing all three. The shop's remaining overtime and over-hire budget for the season is $14,000, so the plan fits, leaving $1,400.

Herroelen and Leus (2001) note that a buffer only protects a deadline if it is managed: watched, reported and consumed deliberately. The two days between the expected finish and first tech will be treated as a buffer of that kind. The technical director will report each Friday how much of it has been used and by which path.

What this page is doingChooses the plan.
8

Monitoring

The simulation will be rerun each Friday with updated ranges for the remaining work. If the probability falls below 90 percent before February 14, the expanded load-in crew, which can be booked on a week's notice, will be added. The rock unit's foam carving and the sky wash are the two events most likely to move the result and will be checked daily.

What this page is doingExplains how the risk will be tracked.
9

Conclusion

The single-number schedule for the Pirates build shows two days of slack; the simulation shows a 41 percent chance of being ready. The difference comes from two uncertain paths merging before load-in. A second painting shift and two hull carpenters, for $12,600, raise the chance to about 97 percent, within the season's budget.

What this page is doingSummarizes the analysis.
10

References

Herroelen, W., & Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management, 19(5), 559-577. https://doi.org/10.1016/S0272-6963(01)00054-7

Malcolm, D. G., Roseboom, J. H., Clark, C. E., & Fazar, W. (1959). Application of a technique for research and development program evaluation. Operations Research, 7(5), 646-669. https://doi.org/10.1287/opre.7.5.646

Williams, T. (2003). The contribution of mathematical modelling to the practice of project management. IMA Journal of Management Mathematics, 14(1), 3-30. https://doi.org/10.1093/imaman/14.1.3

What the QSO 355 Module 7 instructions ask for

QSO 355 Project Two commonly asks students to analyze the risk to a project's schedule and plan how to protect a deadline. Expect to identify uncertain activities, assign ranges or three-point estimates, analyze the schedule with PERT or Monte Carlo simulation, report the probability of meeting the deadline and the likely range of finish dates, identify which activities and paths drive the risk and evaluate options for compressing the schedule, such as crashing, fast tracking or added resources, by cost and effect. Strong projects explain why the deterministic schedule overstates the chance of success, show criticality rather than assuming one critical path, test options in combination and recommend the cheapest plan that reaches a stated target probability.

How this QSO 355 Module 7 project two example is built

The project analyzes the final 22 working days of the Pirates of Penzance build at Cedar Row Repertory Theater, a fictional Milwaukee company. The most likely durations have the set ready on day 15 and loaded in by day 20, two days before first tech. Three-point estimates on the ship hull, its painting, the masts, the rock unit, the rock and backdrop painting and load-in feed a 20,000-run Monte Carlo simulation, which gives only a 41 percent chance of meeting the date, because two uncertain paths merge before load-in. Three crashing options are tested alone and together. A second painting shift and two over-hire carpenters on the hull, together $12,600, raise the probability to about 97 percent.

Where the QSO 355 Module 7 rubric puts the points

Instructors grading QSO 355 Project Two look at sensible three-point estimates with stated sources, a correctly built simulation or PERT analysis, clear reporting of the probability of meeting the deadline and the distribution of finish dates, identification of the activities and paths driving risk, evaluation of compression options by cost and effect, including combinations, and a justified recommendation. Projects that score highest explain why the deterministic schedule is optimistic and set a target probability before choosing options. Credit drops when ranges are arbitrary, results are reported as a single date, merge effects are ignored, crashing is applied to non-critical work or options are chosen without comparing cost per gain. Tables, clarity and APA citations count too.

QSO 355 Module 7 help: the mistakes that cost points

Start with the schedule's network and the deadline. For each uncertain activity, ask the people doing it for optimistic, most likely and pessimistic durations and the event behind the pessimistic case. Run a simulation, many thousands of times, drawing a duration for each activity and recording the finish date; spreadsheets with add-ins or simple code can do this. Report the share of runs that meet the deadline, the median and the 80th and 95th percentile finishes and how often each path was critical. Then test options, alone and in combination, by rerunning the simulation with their effects and noting their costs. Choose the cheapest set that reaches your target. A common mistake is reporting only the most likely finish; another is crashing an activity that is rarely critical.

Get QSO 355 Module 7 written to your instructions

Upload the QSO 355 Project Two guidelines and your schedule. A writer sets three-point estimates for the risky activities, runs a Monte Carlo simulation, reports the probability of meeting the deadline with percentiles and criticality, tests crashing options alone and together on cost and effect and recommends a plan, with research behind the method. Your first QSO 355 project is free, delivered in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 355 papers and related BS Operations Management samples

QSO 355 Module 7 questions, answered

Where can I find a free QSO 355 Module 7 Project Two sample?

This page holds the complete QSO 355 Project Two: Monte Carlo schedule risk and crashing options for an invented theater set build.

What is Monte Carlo schedule analysis?

A simulation that runs the schedule thousands of times with durations drawn from each activity's range, producing a distribution of finish dates and the probability of meeting a deadline.

Why is the deterministic schedule optimistic?

Because when parallel paths merge, the later of them sets the start of the next activity, so uncertainty on any path delays the merge more often than it speeds it up.

What is a criticality index?

The percentage of simulation runs in which an activity or path was on the critical path, showing how often it drives the finish date.

How do you choose which activities to crash?

Crash activities that are often critical and offer the lowest cost per unit of time or probability gained, and test combinations, since gains are not additive.