Vanya First, Pirates After: Leveling Nine Carpenters Across Two Overlapping Builds at Cedar Row
[Student Name]
Southern New Hampshire University
QSO 355: Resource Estimating and Scheduling
Resource Leveling Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Vanya First, Pirates After: Leveling Nine Carpenters Across Two Overlapping Builds at Cedar Row
Introduction
Cedar Row Repertory Theater's shop must build two sets at once this winter. Uncle Vanya, a small-cast drama, loads in during week 6, after A Christmas Carol closes. The Pirates of Penzance, whose turntable and part of the ship were built in the fall with spare capacity, loads in during week 12, after Vanya closes on February 20, for first technical rehearsal on March 1. Both builds draw on the same nine carpenters. This assignment loads the carpenters across both builds for 12 weeks from Monday, December 6, finds the overloads, levels them with a priority rule and measures what remains.
Capacity and Demand
Nine carpenters working 40 hours give 360 hours a week. The shop closes for New Year's week, week 4, leaving 11 working weeks and 3,960 hours. Vanya needs 1,100 shop hours, which must be complete by the end of week 5, plus 240 hours of load-in in week 6. Pirates needs 2,280 more shop hours, its total of 3,700 less the 1,000 completed in the fall and the 420 hours of load-in in week 12, which must happen that week because Vanya occupies the stage until February 20.
Before any leveling, the totals show the problem's shape. Demand is 1,100 + 240 + 2,280 + 420, or 4,040 hours, against capacity of 3,960. The window is 80 hours short. No arrangement of the work inside the 12 weeks can remove that shortfall; leveling can only decide where it falls.
Unleveled Loading
If each build ran at its own natural pace, Vanya would spread its 1,100 hours over its four working weeks at 275 hours a week, and Pirates would spread 2,280 hours over its ten working weeks at 228.
Carpenter hours by week, unleveled
| Week | Vanya | Pirates | Total | Capacity |
|---|---|---|---|---|
| 1 to 3 | 275 | 228 | 503 | 360 |
| 4 | Shop closed | 0 | 0 | |
| 5 | 275 | 228 | 503 | 360 |
| 6 | 240 load-in | 228 | 468 | 360 |
| 7 to 11 | 228 | 228 | 360 | |
| 12 | 420 load-in | 420 | 360 |
The crew would be overloaded by 143 hours a week in weeks 1 to 3 and 5, by 108 hours in week 6 and by 60 hours in week 12, while 132 hours a week sat idle in weeks 7 to 11. The overloads total 740 hours and the idle time 660, a difference of exactly the 80-hour shortfall.
Choosing a Priority Rule
Davis and Patterson (1975) compared simple priority rules for allocating scarce resources in project schedules with optimal solutions and found that the minimum slack rule, giving resources first to the activity with the least float, was among the best performers, producing schedules close to optimal on most problems. Kolisch (1996) distinguishes serial schemes, which schedule one activity at a time, from parallel schemes, which move through time period by period and allocate the available resources at each step. A parallel scheme suits this problem, because the shop decides each Monday who works on which show. Optimization methods such as the genetic algorithm Hegazy (1999) applied to leveling can find better schedules on large networks, but a shop with two builds and one binding trade gains little from them.
Vanya has the least slack: its shop work must be finished by week 5, and it cannot borrow capacity from later weeks. Pirates has more room, because weeks 7 to 11 are lightly loaded. Under the minimum slack rule, Vanya receives its full 275 hours each week, and Pirates receives whatever remains.
Leveled Loading
Carpenter hours by week, leveled with minimum slack
| Week | Vanya | Pirates | Total |
|---|---|---|---|
| 1 to 3 | 275 | 85 | 360 |
| 4 | Shop closed | 0 | |
| 5 | 275 | 85 | 360 |
| 6 | 240 load-in | 120 | 360 |
| 7 to 11 | 360 | 360 | |
| 12 | 420 load-in | 420 |
Pirates now receives 85 hours a week in the four December and January weeks, about two carpenters, and 120 hours in week 6. From week 7 the whole crew moves to Pirates. By the end of week 11, Pirates has received 340 + 120 + 1,800, or 2,260 shop hours, 20 short of the 2,280 it needs. Its load-in in week 12 still needs 420 hours against 360 available. The leveled schedule therefore leaves the expected shortfall, 20 shop hours and 60 load-in hours, both on Pirates, both at the end.
What the Rule Changes
The rule protects Vanya completely. Its build has no overload and finishes on time even if Pirates runs late. The cost is that Pirates now has no slack: it uses every carpenter hour in weeks 7 to 11, and any problem on the ship, which Module 2 identified as the riskiest work of the season, comes out of an already empty margin. The alternative rule, giving Pirates priority because it is larger, would push the shortfall onto Vanya, whose load-in date cannot move and whose opening is a week after it. That would put an earlier, fixed deadline at risk to protect a later one, which is the opposite of the logic of minimum slack.
Checking the Other Trades
Painters and welders were checked the same way. Vanya's 300 painter hours and the 690 remaining on Pirates total 990 against 1,320 available in the 11 working weeks, and the welders' remaining 220 hours on Pirates fit easily inside their 880. Neither trade is overloaded in any week once painting is scheduled to follow the carpentry it depends on, so the carpenters are the only constraint that binds this winter.
Options for the Shortfall
Because the shortfall exists in total, it can only be closed by adding capacity or reducing work. Three options are available. Overtime for regular carpenters, about two Saturdays for five carpenters, would cost about $3,200 at time and a half. Over-hiring two carpenters from the theater's list for the load-in week would cost about $2,900 and would also ease the load-in peak. Reducing work, for example by replacing the built rock stairs with a stock unit from storage, would save about 60 hours but needs the scenic designer's approval. The choice between overtime and over-hire is the subject of the next discussion.
Conclusion
Leveling with the minimum slack rule removes every overload on Vanya and confines the problem to 80 hours on Pirates at the end of the window. It also shows plainly that the problem cannot be solved by rearranging the work: the shop needs 80 more hours, or 80 fewer hours of work, before first technical rehearsal.
References
Davis, E. W., & Patterson, J. H. (1975). A comparison of heuristic and optimum solutions in resource-constrained project scheduling. Management Science, 21(8), 944-955. https://doi.org/10.1287/mnsc.21.8.944
Hegazy, T. (1999). Optimization of resource allocation and leveling using genetic algorithms. Journal of Construction Engineering and Management, 125(3), 167-175. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(167)
Kolisch, R. (1996). Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research, 90(2), 320-333. https://doi.org/10.1016/0377-2217(95)00357-6
What the QSO 355 Module 5 instructions ask for
The QSO 355 Module 5 assignment generally asks students to resolve resource conflicts in a schedule. Expect to load a resource across activities or projects, identify periods where demand exceeds availability, apply a leveling method, such as delaying activities with float or allocating scarce resources by a priority rule, and report the effect on the schedule and finish dates. Strong assignments state capacity accurately, including holidays, choose and justify a priority rule, show the loading before and after leveling, check whether total demand exceeds total capacity, which leveling cannot fix, and explain the remaining options when deadlines cannot move. They also show how the leveled schedule changes the risk on each project.
How this QSO 355 Module 5 resource leveling assignment example is built
The assignment levels the nine carpenters at Cedar Row Repertory Theater, a fictional Milwaukee company, across two winter builds over 12 weeks from December 6, with the shop closed in week 4. Uncle Vanya needs 1,100 shop hours before its week 6 load-in; The Pirates of Penzance needs 2,280 shop hours plus a 420-hour load-in in week 12. Built at their natural pace, the two overload the crew by up to 143 hours a week in six weeks while 132 hours sit idle in five others. A minimum slack rule gives Vanya its carpenters first. Total demand of 4,040 hours exceeds capacity of 3,960, so 80 hours remain. Davis and Patterson on priority rules and Kolisch on scheduling schemes support the method.
Where the QSO 355 Module 5 rubric puts the points
The QSO 355 leveling assignment is commonly scored on accurate resource loading, realistic capacity, a justified priority rule applied consistently, clear before-and-after loading, a check of total demand against total capacity, a correct statement of what leveling can and cannot achieve and sensible options for any shortfall. The strongest assignments explain why the chosen rule fits the projects' deadlines and show how leveling changes each project's risk. Credit drops when holidays are ignored, the rule is not stated, the leveled schedule still contains overloads, the overall shortfall goes unnoticed or options are listed without costs. Tables, clarity and APA citations complete the rubric.
QSO 355 Module 5 help: the mistakes that cost points
Start by listing the resource's capacity for every period, taking out holidays and other commitments. Then load each activity's demand period by period and mark every overload. Before leveling, add up total demand and total capacity over the window: if demand is larger, leveling alone cannot solve the problem, and you will need overtime, more people or less work. Choose a priority rule, such as giving resources first to the activity with the least slack, and apply it period by period. Show the result in a table and check that no period is still overloaded. A common mistake is moving work into periods that are already full; another is leveling one project without noticing the other loses its float.
Get QSO 355 Module 5 written to your instructions
Share the QSO 355 Module 5 instructions and your schedule or scenario. A writer loads the resource period by period, shows where demand exceeds capacity, applies a stated priority rule to level it, compares the leveled and original schedules, calculates any shortfall leveling cannot remove and explains the options, citing scheduling research. Your first QSO 355 leveling paper is free, sent within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 355 papers and related BS Operations Management samples
- QSO 355 Module 1 Discussion: Why the Shop's Estimates Keep Running Short
- QSO 355 Module 2 Estimating Assignment: Three Ways to Estimate a Pirate Ship
- QSO 355 Module 3 Project One: A Resource-Loaded Schedule for the Fall Builds
- QSO 355 Module 4 Discussion: Three-Point Estimates for the Paint Deck
- QSO 355 Module 6 Discussion: Overtime or Over-Hire?
- QSO 355 Module 7 Project Two: Schedule Risk and Crashing Before First Tech
- QSO 355 Module 8 Discussion: Telling the Artistic Director the Estimate Grew
- ACC 425 Module 4 Project One: An Interview Outline for a Corroborative Witness
- HRM 360 Module 4 Discussion: Ethics of Employee Data
- HRM 400 Module 2 Change Models Assignment: Lewin, Kotter or ADKAR for the Ownership Transition
- OL 322 Module 2 Change Readiness Assignment: Assessing Readiness for Change
QSO 355 Module 5 questions, answered
Where can I find a free QSO 355 Module 5 Resource Leveling Assignment sample?
The complete QSO 355 Module 5 assignment is on this page: nine carpenters leveled across two overlapping builds at an invented theater.
What is a priority rule in resource leveling?
A rule deciding which activity receives scarce resources first when demand exceeds capacity, such as least slack, earliest due date or shortest duration.
What is the minimum slack rule?
A priority rule that gives resources first to the activity with the least float, so the work closest to delaying a deadline is protected.
Can resource leveling always meet the deadline?
No. If total demand within the window exceeds total capacity, leveling can only move the shortage; meeting the deadline then requires more capacity or less work.
What is a parallel scheduling scheme?
A method that moves through the schedule period by period and, at each step, assigns available resources to eligible activities in priority order.