QSO 355 Module 3 Project One Example

Reviewed by Portia Lambrick, MBA

This QSO 355 Module 3 Project One sample builds a resource-loaded schedule across several activities, finds the overloads in the resource histogram and resolves them with float. SNHU QSO 355 (QSO-355) asks for this schedule in Module 3 of its course on resource estimating and scheduling, part of the BS Operations Management. The project is the fall season's three set builds at Cedar Row Repertory Theater, an invented Milwaukee company with one shop and a fixed crew. Scheduling everything early overloads the carpenters four times, at up to 514 hours against 360. Delaying two builds within their float removes every overload and leaves room to start the spring turntable early.

CourseQSO 355 Resource Estimating and Scheduling
ModuleModule 3
Paper typeundergraduate project building a resource-loaded schedule across several activities, finding overloads in the histogram and resolving them with float
LengthAbout 1,050 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 355 Module 3

1

Five Hundred Fourteen Hours in a 360-Hour Week: A Resource-Loaded Schedule for the Cedar Row Fall Builds

[Student Name]

Southern New Hampshire University

QSO 355: Resource Estimating and Scheduling

Project One: Resource-Loaded Schedule

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe builds, hours and dates for Cedar Row Repertory Theater in this QSO 355 project are fictional.
2

Five Hundred Fourteen Hours in a 360-Hour Week: A Resource-Loaded Schedule for the Cedar Row Fall Builds

Introduction

Cedar Row Repertory Theater opens its season with three productions on its one stage: Twelfth Night, The Importance of Being Earnest and the annual A Christmas Carol, whose set is refurbished each year. The scenic shop builds all three with the same crew of nine carpenters, three scenic painters and two welders, each working 40 hours a week. This project builds a schedule for the three fall builds from Monday, July 5 (week 1), to the Christmas Carol load-in in week 21, loads each activity with labor, finds where demand exceeds capacity and levels the schedule.

What this page is doingStates the scope of the schedule.
3

Fixed Dates and Activities

Each show's load-in, when the set moves from the shop to the stage, can only happen after the previous show closes, and each first technical rehearsal is fixed by the season's ticketed dates. Twelfth Night loads in during week 9 and opens in week 11. Earnest loads in during week 15, after Twelfth Night closes on Sunday, October 10. A Christmas Carol loads in during week 21, after Earnest closes on November 21. Each build has four activities in sequence: carpentry, painting overlapping the second half of carpentry, welding where needed and load-in.

Labor estimates by build

BuildCarpenter hoursPainter hoursWelder hoursLoad-in carpenter hours
Twelfth Night1,900520180300
The Importance of Being Earnest1,50061060300
A Christmas Carol refurbishment65024040260

The estimates come from the shop's timesheet rates and bottom-up estimates from the shop drawings, prepared as in Module 2.

What this page is doingSets the constraints.
4

Early Start Schedule

Kelley and Walker (1959), who introduced the critical path method, showed how earliest and latest start times give each activity a measure of slack, the time it can move without delaying the project. Applied here, Twelfth Night has one week of slack: its carpentry could run weeks 1 to 7, and load-in is in week 9. Earnest's drawings are ready by week 6, so its carpentry could start then and finish in week 12, leaving two weeks before its week 15 load-in. A Christmas Carol's refurbishment could run weeks 13 to 17, three weeks before its week 21 load-in.

Carpenter hours by week, early start

WeeksActivitiesHours per weekCapacity
1 to 5Twelfth Night carpentry271360
6 to 7Twelfth Night and Earnest carpentry486360
8Earnest carpentry214360
9Twelfth Night load-in and Earnest carpentry514360
10 to 12Earnest carpentry214360
13 to 14Christmas Carol carpentry130360
15Earnest load-in and Christmas Carol carpentry430360
16 to 17Christmas Carol carpentry130360
18 to 20None0360
21Christmas Carol load-in260360

The early start schedule overloads the carpenters in weeks 6, 7, 9 and 15, by 70 to 154 hours, and leaves them idle in weeks 18 to 20. Meeting it would mean about 476 hours of overtime or over-hire in four weeks, costing about $19,000, while the shop sits empty later. Those overtime weeks would also be the busiest of the fall, and Thomas (1992) found that scheduled overtime loses productivity the longer it runs, so the hours bought would not all turn into work. The painters and welders are not overloaded in the early schedule: painting peaks at about 104 hours a week in weeks 4 to 8 and welding at 60 hours in weeks 1 to 3.

What this page is doingSchedules everything as early as possible.
5

Leveling

Hegazy (1999) describes resource leveling as a search for start times, within the activities' float, that reduce peaks and fluctuations in resource demand without delaying the project, and notes that simple heuristics, such as moving activities with the most float first, often give good results on small schedules. The leveled schedule here applies that heuristic in three moves.

First, Twelfth Night's carpentry uses its one week of float and is stretched from seven weeks to eight, running weeks 1 to 8 at about 238 hours a week. It still finishes before load-in. Second, Earnest, with two weeks of float, is both delayed and compressed: its carpentry starts in week 10 instead of week 6 and runs five weeks at 300 hours a week, with more carpenters assigned to it, finishing in week 14 just before its load-in. Third, A Christmas Carol, also with three weeks of float, starts in week 16 and runs at 130 hours a week to week 20. Painting is moved with each build: Twelfth Night in weeks 3 to 8, Earnest in weeks 10 to 15 at about 102 hours a week, partly on stage during load-in, and A Christmas Carol in weeks 17 to 20.

Carpenter hours by week, leveled

WeeksActivitiesHours per weekSpare capacity
1 to 8Twelfth Night carpentry238122
9Twelfth Night load-in30060
10 to 14Earnest carpentry30060
15Earnest load-in30060
16 to 20Christmas Carol carpentry130230
21Christmas Carol load-in260100

The leveled schedule has no overloads for any trade. Carpenter demand peaks at 300 hours a week, and no load-in date or rehearsal moves. The total, 4,910 carpenter hours, is unchanged; only its timing is different.

What this page is doingUses float to remove the overloads.
6

Risks of the Leveled Schedule

Leveling has a cost: Earnest and A Christmas Carol now have no float left. Any delay in their drawings or materials will fall directly on load-in. To manage that, the technical director will confirm Earnest's final drawings by week 8 and order its materials in week 8, and the props and paint departments will be told that the builds now start later. The shop also keeps 60 hours a week in reserve during the Earnest build, enough to absorb a delay of about one week.

What this page is doingExplains what leveling gives up.
7

Spare Capacity

The leveled schedule leaves about 1,150 carpenter hours spare in weeks 16 to 20. The spring Pirates of Penzance set includes a turntable the shop has never built. Starting the turntable frame in week 16 would use part of that capacity and gives the riskiest work package of the season extra time, which the estimate in Module 2 showed it needs.

What this page is doingShows what the leveled schedule makes possible.
8

Conclusion

Scheduling the fall builds as early as possible overloads the carpenters in four weeks and leaves them idle in three. Using the float in all three builds removes every overload without overtime or a change to any date, and frees capacity to start the spring turntable early.

What this page is doingSummarizes the schedule.
9

References

Hegazy, T. (1999). Optimization of resource allocation and leveling using genetic algorithms. Journal of Construction Engineering and Management, 125(3), 167-175. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(167)

Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference (pp. 160-173). Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318

Thomas, H. R. (1992). Effects of scheduled overtime on labor productivity. Journal of Construction Engineering and Management, 118(1), 60-76. https://doi.org/10.1061/(ASCE)0733-9364(1992)118:1(60)

What the QSO 355 Module 3 instructions ask for

QSO 355 Project One usually asks students to build a resource-loaded schedule for a project. Expect to define activities with durations and dependencies, calculate the critical path and float, assign resources to each activity, produce resource histograms by period, compare them with available capacity, identify overloads and resolve them by resource leveling or smoothing, and explain the effect on the schedule. Strong projects state resource capacity realistically, including holidays and other commitments, show the histogram before and after leveling, use float before extending the finish date, explain which activities moved and why and note what spare capacity the leveled schedule leaves. Clear tables or described charts matter, since graders must follow the loading period by period.

How this QSO 355 Module 3 project one example is built

The project schedules the fall builds at Cedar Row Repertory Theater, a fictional Milwaukee company: Twelfth Night, The Importance of Being Earnest and a refurbished A Christmas Carol, over 21 weeks from July 5. Capacity is 360 carpenter hours a week, 120 painter hours and 80 welder hours. With every build scheduled as early as possible, carpenters are overloaded in weeks 6, 7, 9 and 15, peaking at 514 hours. Because each show's load-in is fixed by the previous show's closing, every build has some float. Using it, and compressing Earnest onto more carpenters, brings the peak to 300 hours. Kelley and Walker on the critical path method and Hegazy on resource leveling inform the method.

Where the QSO 355 Module 3 rubric puts the points

Instructors grading QSO 355 Project One look at correct activities, durations, dependencies and float, resources assigned to each activity, accurate histograms compared with realistic capacity, overloads identified and resolved with a sound leveling approach, the effect on the schedule explained and clear presentation. Projects that score highest use float before moving fixed dates, check every resource type rather than only the busiest and note what spare capacity remains. Credit drops when capacity is unrealistic, histograms are missing or wrong, leveling pushes critical activities without saying so, or the project treats all resources as unlimited. Tables, clarity and APA citations count too.

QSO 355 Module 3 help: the mistakes that cost points

Start with the activities, durations and dependencies, and calculate early and late dates so you know each activity's float. Then assign resources, such as hours of each trade per week, and add them up period by period to make a histogram for each resource. Draw the capacity line and mark every period above it. To level, move or stretch activities that have float first, since that costs nothing in finish date; only if overloads remain should you extend the schedule, add people or approve overtime. Show the histogram before and after. A common mistake is leveling one resource and creating an overload in another; another is ignoring other demands on the same people, such as maintenance or rentals.

Get QSO 355 Module 3 written to your instructions

Upload the QSO 355 Project One guidelines and your project data. A writer builds the schedule with durations, dependencies and float, loads each activity with resources, draws the histogram against capacity, finds the overloads and levels them using float or resource limits, then explains what changed and what spare capacity remains. Your first QSO 355 project is free, completed in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 355 papers and related BS Operations Management samples

QSO 355 Module 3 questions, answered

Where can I find a free QSO 355 Module 3 Project One sample?

This page holds the complete QSO 355 Project One: a resource-loaded, leveled schedule for an invented theater's three fall set builds.

What is a resource-loaded schedule?

A schedule in which each activity is assigned the resources it needs, so that demand for each resource can be totaled by period and compared with what is available.

What is a resource histogram?

A bar chart showing the quantity of a resource required in each period of the schedule, usually drawn against a line showing the resource's availability.

What is resource leveling?

Adjusting start and finish dates to keep resource demand within available limits, which may lengthen the project if float is not enough.

How does leveling differ from smoothing?

Smoothing adjusts activities only within their float so the finish date does not change; leveling may extend the finish date to respect resource limits.