Free sample paper for QSO 355 Module 2
A Ship on a Turntable: Analogous, Parametric and Bottom-Up Labor Estimates for the Cedar Row Pirates of Penzance
[Student Name]
Southern New Hampshire University
QSO 355: Resource Estimating and Scheduling
Estimating Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
A Ship on a Turntable: Analogous, Parametric and Bottom-Up Labor Estimates for the Cedar Row Pirates of Penzance
Introduction
Cedar Row Repertory Theater's spring musical is The Pirates of Penzance, with first technical rehearsal on March 1. The scenic design calls for a two-deck pirate ship, 34 feet long, set on a 28-foot turntable that rotates the ship between the deck scenes and the shore scenes; two masts with rigging the actors climb; a rock unit with stairs for the shore; masking legs; and a painted backdrop. The shop has built many ships and rocks but has never built a turntable. This assignment estimates the carpentry hours for the set three ways, reconciles them into a planning figure and estimates welding and painting hours, with a basis of estimate.
Analogous Estimate
The most similar past build is the shop's last musical, two seasons ago, whose set included a two-level street, a bridge and a moving wagon. It took 2,750 carpenter hours, recorded on timesheets. The Pirates set is larger in platform area, about 1,450 square feet against 1,200, and has comparable wall area. It also has a mechanism, the turntable, that the earlier set lacked, while the earlier set had the wagon. Scaling by platform area alone gives about 3,300 hours. The analogy is useful but weak on the turntable, since the wagon was a much simpler mechanism.
Parametric Estimate
The shop's timesheets for the last four seasons give average rates of about 1.1 carpenter hours per square foot of platform, including framing, decking and facing, and 0.35 hours per square foot of wall or flat. Mechanisms and specialty pieces do not fit a per-square-foot rate, so they are estimated separately.
Parametric estimate of carpenter hours
| Item | Quantity | Rate | Hours |
|---|---|---|---|
| Platforms and decks | 1,450 sq ft | 1.1 per sq ft | 1,595 |
| Walls, flats and ship sides | 2,200 sq ft | 0.35 per sq ft | 770 |
| Turntable, allowance | 1 | 420 | |
| Masts, rigging and specialty pieces | 380 | ||
| Total | 3,165 |
The parametric estimate is the most data-driven for platforms and walls, but its allowances for the turntable and the masts are judgments rather than parameters.
Bottom-Up Estimate
The technical director and the lead carpenter broke the set into seven work packages and estimated each from shop drawings.
Bottom-up estimate of carpenter hours
| Work package | Hours |
|---|---|
| Turntable: frame, bearings, drive mount, deck | 460 |
| Ship hull, decks and stairs | 1,240 |
| Masts and rigging points | 410 |
| Rock unit and stairs | 380 |
| Railings and ladders | 290 |
| Masking legs and borders | 180 |
| Load-in and installation | 420 |
| Total | 3,380 |
The bottom-up estimate is the only one that includes load-in explicitly, which accounts for part of the difference from the other two; the analogous figure includes the earlier show's load-in, and the parametric rates include a share of it.
Reconciling the Three
The three estimates fall within 7 percent of each other, 3,165 to 3,380 hours, which gives confidence in the platform and wall work. Expert judgment is the estimating method used most in practice, and a review of the research found it no less accurate on average than formal models, though it improves when several independent estimates are combined and checked against past data (Jørgensen, 2004). That is the purpose of comparing the three methods here.
All three estimates, however, treat the turntable as a known quantity, and it is not. The bottom-up estimate of 460 hours assumes the bearings and drive arrive on time and fit the first time. A three-point estimate for the turntable package gives an optimistic 380 hours, a most likely 460 and a pessimistic 760 if the drive mount must be rebuilt, for a PERT expected value of (380 + 4 × 460 + 760) / 6, or about 497 hours. Replacing the turntable figure with that expected value raises the bottom-up total to about 3,420 hours.
The shop's own record, as discussed in Module 1, shows that builds with a mechanism new to the shop ran about 20 percent over their estimates last season, even after allowances. Flyvbjerg (2006) recommends adjusting estimates by the overruns seen in a reference class of similar projects rather than trusting the detail of the plan, which is the outside view Kahneman and Lovallo (1993) contrast with forecasts built only from the case at hand. Applying a smaller, 8 percent adjustment to the bottom-up total, since only the turntable is new and the rest of the set is familiar work, gives about 3,700 hours. That is the planning figure for carpentry. It is higher than any single method, which is the point: the methods agree with each other because they share the same blind spot.
Sensitivity of the Estimate
Two figures move the estimate most. If the platform rate proves to be 1.2 hours per square foot rather than 1.1, as it was on the two most complex sets of the last four seasons, the platform work rises by about 145 hours. If the turntable reaches its pessimistic case, the package grows by 300 hours over its most likely value. Both together would put carpentry near 4,150 hours, and the technical director will carry that figure as the high case into the winter schedule.
Welding and Painting
Welding covers the turntable's steel frame, the mast bases and the railings' steel posts. The bottom-up estimate is 340 welder hours, including a 60-hour allowance for the turntable frame's first fit. Painting covers the ship's hull and decks, the rock unit, the masking and the 30-by-50-foot backdrop. The charge scenic artist estimates 690 painter hours, of which 260 are for the backdrop, using the shop's rate of about 0.17 hours per square foot for a detailed drop of sky and coast.
Basis of Estimate
The estimate assumes final shop drawings by October 15, materials on site when each package starts, a turntable drive and bearings purchased rather than built and a crew of the shop's regular carpenters, whose productivity is reflected in the timesheets. It excludes properties, lighting, sound and costume work, fly system rigging done by the stage crew and the overtime premium if the schedule requires it. Hours are direct labor; supervision by the technical director is excluded. The estimate will be revised when final drawings are issued and again when the turntable frame is complete.
Conclusion
The planning estimate for the Pirates of Penzance set is about 3,700 carpenter hours, 340 welder hours and 690 painter hours. The three methods agree on the familiar work; the uplift reflects the turntable and the shop's history with new mechanisms.
References
Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5-15. https://doi.org/10.1177/875697280603700302
Jørgensen, M. (2004). A review of studies on expert estimation of software development effort. Journal of Systems and Software, 70(1-2), 37-60. https://doi.org/10.1016/S0164-1212(02)00156-5
Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17-31. https://doi.org/10.1287/mnsc.39.1.17
What the QSO 355 Module 2 instructions ask for
The QSO 355 Module 2 assignment usually asks students to estimate a project's resources or durations using more than one method. Expect to apply analogous estimating, based on a similar past project; parametric estimating, based on a statistical relationship such as hours per unit; and bottom-up estimating, built from a work breakdown structure; then compare the results, explain the differences and recommend a figure. Strong assignments show the data and arithmetic behind each method, adjust analogies for differences in size and complexity, use parameters drawn from records rather than guesses, give ranges where uncertainty is high and write a basis of estimate stating assumptions and exclusions. They also say which method deserves the most weight.
How this QSO 355 Module 2 estimating assignment example is built
The assignment estimates labor for the Pirates of Penzance set at Cedar Row Repertory Theater, a fictional Milwaukee company. An analogous estimate scales the shop's last musical, 2,750 carpenter hours, by about 20 percent for size and gets 3,300. A parametric estimate applies shop rates of 1.1 hours per square foot of platform and 0.35 per square foot of wall, plus allowances for the turntable and masts, and gets 3,165. A bottom-up estimate from a work breakdown structure gets 3,380. Because the turntable is new to the shop, a three-point range is added and the shop's record of overruns on new mechanisms is applied, giving 3,700 hours. Jørgensen on expert estimation and Flyvbjerg on reference classes support the reconciliation.
Where the QSO 355 Module 2 rubric puts the points
The QSO 355 estimating assignment is commonly graded on correct application of each method, data and arithmetic shown in full, sensible adjustment of analogies and parameters, a bottom-up estimate tied to a work breakdown structure, a reasoned reconciliation of the methods, treatment of uncertainty and a clear basis of estimate. The strongest assignments explain why the methods differ and which to trust for each part of the work. Credit drops when parameters are invented, analogies are used without adjustment, the bottom-up estimate omits work such as load-in, the recommended figure is an unexplained average or uncertainty is ignored. Tables, clear writing and APA citations complete the grade.
QSO 355 Module 2 help: the mistakes that cost points
Start by describing the work and its size in measurable units, such as square feet, pieces or lines of code. For an analogous estimate, choose the most similar past project and adjust for differences in size and complexity, saying how. For a parametric estimate, take rates from records, such as hours per square foot, and multiply. For a bottom-up estimate, break the work into a work breakdown structure and estimate each package. Then compare the three: if they agree, confidence rises; if they differ, find out why. Add a range for the parts you have never done, and write down your assumptions and exclusions. A common mistake is averaging the three without explanation; another is forgetting work outside the shop, such as installation.
Get QSO 355 Module 2 written to your instructions
Share the QSO 355 Module 2 instructions and describe the work you are estimating. A writer prepares analogous, parametric and bottom-up estimates with the data and arithmetic shown, adds ranges where the work is uncertain, reconciles the methods into one planning figure and writes the basis of estimate, citing estimating research. Your first QSO 355 estimate is free, done in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 355 papers and related BS Operations Management samples
- QSO 355 Module 1 Discussion: Why the Shop's Estimates Keep Running Short
- QSO 355 Module 3 Project One: A Resource-Loaded Schedule for the Fall Builds
- QSO 355 Module 4 Discussion: Three-Point Estimates for the Paint Deck
- QSO 355 Module 5 Resource Leveling Assignment: Two Builds, Nine Carpenters
- QSO 355 Module 6 Discussion: Overtime or Over-Hire?
- QSO 355 Module 7 Project Two: Schedule Risk and Crashing Before First Tech
- QSO 355 Module 8 Discussion: Telling the Artistic Director the Estimate Grew
- QSO 310 Module 7 Project Two: The Service Operations Improvement Plan
- QSO 325 Module 8 Discussion: Why Improvement Programs Fade
- MKT 205 Module 5 Milestone Two: The Marketing Mix Strategy
- MKT 400 Module 1 Discussion: What a Hockey Team's Name Is Worth
QSO 355 Module 2 questions, answered
Where can I find a free QSO 355 Module 2 Estimating Assignment sample?
The complete QSO 355 Module 2 assignment is on this page: analogous, parametric and bottom-up labor estimates for an invented theater's set.
What is analogous estimating?
Estimating a project from the actual cost or duration of a similar past project, adjusted for known differences in size and complexity.
What is parametric estimating?
Estimating from a statistical relationship between historical data and a project variable, such as labor hours per square foot or cost per unit.
What is bottom-up estimating?
Estimating each work package or activity in the work breakdown structure and adding the estimates up to the project total.
Which estimating method is most accurate?
Bottom-up estimates are usually most accurate when the scope is well defined, but comparing several methods and checking against past outcomes gives the most reliable figure.