QSO 355 Module 6 Discussion Example

Reviewed by Portia Lambrick, MBA

This QSO 355 Module 6 Discussion sample compares overtime and added staff as ways to add capacity to a schedule, including the effect of long weeks on productivity. SNHU QSO 355 (QSO-355) takes up schedule compression in Module 6 of its course on resource estimating and scheduling within the BS Operations Management. The case is Cedar Row Repertory Theater, an invented Milwaukee company whose winter schedule is 80 carpenter hours short. The post shows why the cheaper-looking option, Saturdays for the regular crew, may not deliver its hours, and why two extra carpenters for load-in week fit the shortfall better.

CourseQSO 355 Resource Estimating and Scheduling
ModuleModule 6
Paper typeundergraduate discussion post comparing overtime and added staff as ways to add capacity to a schedule, including productivity effects
LengthAbout 380 words, 3 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 355 Module 6

1

Module Six Discussion

Eighty Hours, Two Ways

Our winter schedule is 80 carpenter hours short: about 20 hours of Pirates of Penzance shop work by the end of week 11 and 60 hours in the load-in week, when the crew has 360 hours and the load-in needs 420. The deadline, first technical rehearsal on March 1, cannot move. Kelley and Walker (1959), in the paper that introduced the critical path method, gave each activity a normal duration and a faster, costlier crash duration and shortened schedules by buying time where it was cheapest. Our question is the same: where is the cheapest productive hour?

What this page is doingThe shortfall.
2

The obvious answer is overtime. Two Saturdays for five of our regular carpenters would cover 80 hours at time and a half, about $3,200. Our people know the shop and the set, need no orientation and can start tomorrow.

But overtime hours are not the same as regular hours. Thomas (1992), reviewing studies of scheduled overtime in construction, found that productivity declines when overtime is scheduled week after week, so each extra hour buys less work than a regular one. Hanna et al. (2005) measured the effect on electrical and mechanical projects and found that losses grew with both the number of hours per week and the number of consecutive weeks of overtime. Our crew will have worked full weeks since December, with Pirates using every hour from week 7, and the Saturdays would fall in the hardest stretch of the season.

There is a second problem: Saturdays in the shop do nothing for the 60 hours in load-in week, which happen on stage, all in one week.

What this page is doingThe cheaper-looking option.
3

Bringing in two carpenters from our over-hire list for load-in week runs about $2,900 at their day rate. Both have worked our stage, so orientation takes a morning. They add hands exactly where most of the shortfall sits, and they arrive fresh. Load-in also involves overhead work on battens and rigging, where fatigue is a safety issue, not only a productivity one.

What this page is doingThe over-hire option.
4

Over-hire two carpenters for load-in week, and hold one Saturday in reserve for the shop work only if it slips. One Saturday for five carpenters adds 40 hours, enough to cover the 20 with room to spare.

What this page is doingMy recommendation.
5

How long would your overtime last, and how many productive hours would it really buy?

What this page is doingFor classmates.
6

References

Hanna, A. S., Taylor, C. S., & Sullivan, K. T. (2005). Impact of extended overtime on construction labor productivity. Journal of Construction Engineering and Management, 131(6), 734-739. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:6(734)

Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference (pp. 160-173). Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318

Thomas, H. R. (1992). Effects of scheduled overtime on labor productivity. Journal of Construction Engineering and Management, 118(1), 60-76. https://doi.org/10.1061/(ASCE)0733-9364(1992)118:1(60)

What the QSO 355 Module 6 instructions ask for

The QSO 355 Module 6 discussion typically concerns ways to shorten a schedule or add capacity: overtime, additional staff or shifts, subcontracting and crashing activities on the critical path. Students are usually asked to recommend an option for a project and explain its costs and effects. Strong posts compare options on full cost rather than wage rates alone, consider the productivity loss from sustained overtime, the learning time and supervision new people need, where in the schedule the extra capacity is needed and safety, support the comparison with research and make a clear recommendation. Replies should ask a classmate how long their overtime would last or how quickly added people could become productive.

How this QSO 355 Module 6 discussion example is built

The post decides how Cedar Row Repertory Theater, a fictional Milwaukee company, should find 80 carpenter hours its winter schedule lacks: 20 in the shop and 60 in the load-in week. Two Saturdays for five regular carpenters cost about $3,200 and look cheaper. Thomas's work on scheduled overtime and Hanna, Taylor and Sullivan's study of extended overtime show productivity falls as long weeks continue, so the hours bought may not all arrive, and Saturdays in the shop do nothing for the load-in peak. Two over-hire carpenters for load-in week cost about $2,900 and add hands where the peak is. The post recommends over-hire for load-in and one Saturday only if the shop work slips.

Where the QSO 355 Module 6 rubric puts the points

The QSO 355 Module 6 thread is marked on a clear statement of the capacity problem, a comparison of options on full cost, attention to productivity, learning time, timing and safety, use of research on overtime and staffing, a reasoned recommendation and replies that help peers weigh their own options. Posts that do best explain where in the schedule the added capacity is needed and how long it must last. Marks fall when options are compared by hourly wage alone, productivity effects are ignored, added staff are assumed productive on day one or replies are simple agreement. Grammar and APA citations are part of the mark.

QSO 355 Module 6 help: the mistakes that cost points

Start by stating exactly how much capacity you lack, when and on which activities. Then list the options: overtime for current staff, temporary or added staff, a second shift, subcontracting or reducing scope. For each, estimate the full cost, including premiums, orientation and supervision, and ask how many productive hours it really buys. Long or repeated overtime lowers productivity, and new people take time to learn the work. Consider where the extra capacity is needed: hours added in the wrong week do not help. Note any safety concerns from fatigue. A common mistake is treating overtime hours as equal to regular hours; another is forgetting the time new people need before they are useful.

Get QSO 355 Module 6 written to your instructions

Paste the QSO 355 Module 6 prompt and describe the schedule you need to compress. A writer compares overtime, added staff and other options on cost, productivity, timing, learning time and safety, uses research on overtime effects, recommends a choice and asks QSO 355 classmates a question. Your first QSO 355 post is free and should arrive within two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 355 papers and related BS Operations Management samples

QSO 355 Module 6 questions, answered

Where can I find a free QSO 355 Module 6 Discussion sample?

This page holds the full QSO 355 Module 6 post: overtime or over-hire to cover an 80-hour shortfall at an invented theater's scenic shop.

Does overtime reduce productivity?

Studies of construction labor found that sustained scheduled overtime lowers productivity, and that losses grow as overtime continues for more weeks and longer days.

What is crashing a schedule?

Shortening the duration of critical path activities by adding resources, such as overtime or extra staff, at the lowest added cost per unit of time saved.

When is adding staff better than overtime?

When the extra work is concentrated in a short period, the new people can be productive quickly and the regular staff are already working long hours.

What is fast tracking?

Overlapping activities that the plan had placed one after another, which shortens the schedule but raises the risk of rework.