Free sample paper for QSO 645 Module 9
Project Management Plan by Process Group: Halloran Science Center Dome Renewal
[Student Name]
Southern New Hampshire University
QSO 645: Project Management for PMP Certification
Final Project
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Project Management Plan by Process Group: Halloran Science Center Dome Renewal
Introduction
Halloran Science Center will replace its 1987 star projector, dome surface and seats, add accessible seating and produce new shows, for $4.8 million, during a seven-month closure ending with a September 8 reopening for school field trips. This plan is organized by the five process groups. Within each group, a table shows the key processes, the main inputs used, the tools and techniques applied and the outputs produced at Halloran, followed by a short explanation. The final sections work one change through integrated change control and describe closing.
Initiating
Initiating processes at Halloran
| Process | Main inputs | Tools and techniques | Outputs at Halloran |
|---|---|---|---|
| Develop project charter | Business case; benefits management plan; donor and grant agreements | Expert judgment from planetarium consultant; meetings with the board | Charter signed December 12 naming the executive director as sponsor |
| Identify stakeholders | Charter; donor list; school booking records | Stakeholder analysis; engagement assessment | Stakeholder register with ten groups |
The business case compared refurbishment, a hybrid optical and digital system and a fully digital system and recommended the hybrid, whose discounted income outruns the slice of savings Halloran itself puts in roughly fourfold. Badewi (2016) found that organizations combining sound project management with deliberate benefits management practices, such as naming benefit owners, reported more successful investments than those relying on project management alone, so the benefits register, with owners outside the project, was approved alongside the charter.
Planning
Key planning processes at Halloran
| Process | Main inputs | Tools and techniques | Outputs at Halloran |
|---|---|---|---|
| Collect requirements and define scope | Charter; stakeholder register | Focus groups, survey, interviews, observation, document analysis | Requirements traceability matrix, now 39 requirements; scope statement |
| Create WBS | Scope statement | Decomposition | WBS with seven deliverables and 52 work packages |
| Develop schedule | WBS; activity durations; vendor lead times | Critical path method; schedule compression | 30-week installation schedule with July 15 finish and reopening buffer |
| Determine budget | Cost estimates; contracts; risk register | Cost aggregation; reserve analysis | Cost baseline $4.42 million plus $380,000 contingency |
| Plan quality management | Requirements; vendor specifications | Cost of quality; test planning | Quality plan with metrics, factory and site acceptance tests |
| Plan communications and engagement | Stakeholder register; engagement assessment | Communication requirements analysis | Communication plan and engagement matrix |
| Plan risk management and responses | Scope, schedule and cost baselines | Risk workshop; probability and impact analysis | Risk register with owners and responses |
| Plan procurement | Scope baseline; make-or-buy analysis | Contract type selection; source selection criteria | Four procurement packages, each with its contract type |
The installation follows a predictive plan because contracts, inspections and the reopening date leave no room for discovery, while show production runs in two-week sprints with the education director as product owner. Boehm and Turner (2003) recommend letting a project's risks decide where plan-driven discipline and where agile flexibility belong, rather than choosing one for the whole effort; at Halloran, the frozen technical specification at week 6 is the agreed boundary between the two.
The schedule finishes installation by July 15, leaving seven weeks for testing, presenter training and rehearsals before September 8. The cost baseline is built from the four contracts and internal costs, with contingency sized from the risk register: dome panel delays, hidden conditions in the 1987 floor, integration problems between the optical and video systems and a shortfall in late donor pledges.
Executing
Key executing processes at Halloran
| Process | Main inputs | Tools and techniques | Outputs at Halloran |
|---|---|---|---|
| Direct and manage project work | Project management plan; approved changes | Weekly coordination meetings; work authorization | Installed dome, seats, projection and sound; work performance data |
| Manage quality | Quality plan; test results | Process audits by consultant | Audit reports; process improvements |
| Acquire and develop team | Resource plan | Training; co-location in site office | Presenters trained on portable system; integrated contractor team |
| Conduct procurements | Procurement documents; proposals | Weighted scoring by panel; negotiation | Four signed contracts |
| Manage communications and engagement | Communication plan; engagement matrix | Calls, meetings, tours, newsletters | School bookings retained; members renewed |
| Implement risk responses | Risk register | Agreed responses | Early dome panel order; floor survey before demolition |
Turner and Simister (2001) relate the choice of contract to how much is known about both the product and the way it will be produced. The four packages reflect that: a firm fixed price for the fully drawn dome surface, a fixed price with unit-price allowances for seating in a building whose floor conditions were unknown, a fixed-price-incentive-fee contract for the projection system whose integration effort was uncertain and capped time and materials for show co-production. The procurement for the sound package was also where professional responsibility was tested: a board member's family connection to one bidder was disclosed to the sponsor, the board member recused and all bids were scored on published criteria.
Monitoring and Controlling
Key monitoring and controlling processes at Halloran
| Process | Main inputs | Tools and techniques | Outputs at Halloran |
|---|---|---|---|
| Monitor and control project work | Work performance data; baselines | Earned value; buffer tracking | Monthly status reports to sponsor and board |
| Perform integrated change control | Change requests; plan | Impact analysis; change control board | Approved or rejected changes; updated baselines; change log |
| Validate scope | Verified deliverables; requirements matrix | Inspection; acceptance by sponsor | Accepted deliverables |
| Control quality | Quality metrics; deliverables | Measurements; viewing panel; test scripts | Test results; nonconformance reports |
| Monitor risks | Risk register; performance reports | Reviews at each status meeting | Updated register; triggered responses |
| Monitor stakeholder engagement | Engagement matrix; booking and renewal data | Engagement measures | Revised strategies |
Status is reported monthly using earned value for the installation and buffer consumption for the schedule; sprint progress for the show is reported through the backlog and the product owner's acceptance of scenes.
A Change Through Integrated Change Control
In April, the dome fabricator reported that a shortage of perforated aluminum sheet would delay delivery of the dome panels by three weeks, pushing dome installation, projector alignment and testing into August and leaving too little time before September 8. The project manager logged a change request and analyzed three options with the integrator and the general contractor.
Options for the dome panel delay
| Option | Effect on schedule | Cost | Risk |
|---|---|---|---|
| A: Accept the delay | Testing ends September 1; training cut to one week | none | High: little time to fix defects before reopening |
| B: Overtime and resequencing: install seats and sound before the dome, run dome crews six days a week | Recovers about two and a half weeks; testing ends July 30 | $38,000 | Moderate: crews working longer hours |
| C: Source sheet from a second mill at a premium | Recovers two weeks | $64,000 | Moderate: new supplier's material untested |
The project manager recommended Option B, which used part of the contingency reserve and stayed within the sponsor's approval authority, yet resequencing the baseline put it before the change control board anyway, where the sponsor, the planetarium manager and the board treasurer looked it over. It was approved on April 22. The schedule baseline, the cost forecast, the risk register and the communication plan were updated, and teachers and donors were told nothing had changed for them.
Closing
Closing processes at Halloran
| Process | Main inputs | Tools and techniques | Outputs at Halloran |
|---|---|---|---|
| Close project | Accepted deliverables; contracts; lessons log | Final review meeting; document archiving | Final report to board and county; transition to planetarium manager; lessons learned |
| Close procurements | Contracts; acceptance results | Procurement audit | Final payments; warranties; vendor evaluations |
Closing includes the transfer of the benefits register to its owners, whose yearly figures on visits, school groups, member households, rentals and teacher scores go to the treasurer's committee until the third anniversary of reopening.
Conclusion
Organized by process group, Halloran's plan shows the PMP framework at work on one project: a charter and stakeholder register from initiating, baselines and subsidiary plans from planning, a mix of fixed-plan installation and sprint-based show production in executing, monitoring that caught a supplier delay early enough to choose among options, and closing that hands both the planetarium and its benefits to the people who will keep them. The value of the framework lies less in its names than in the decisions it forces at the right time.
References
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778. https://doi.org/10.1016/j.ijproman.2015.05.005
Boehm, B., & Turner, R. (2003). Using risk to balance agile and plan-driven methods. Computer, 36(6), 57-66. https://doi.org/10.1109/MC.2003.1204376
Turner, J. R., & Simister, S. J. (2001). Project contract management and a theory of organization. International Journal of Project Management, 19(8), 457-464. https://doi.org/10.1016/S0263-7863(01)00051-5
What the QSO 645 Module 9 instructions ask for
The QSO 645 final project typically asks students to build a comprehensive project management plan that applies the process groups and knowledge areas to a project, demonstrating the inputs, tools and techniques and outputs of key processes. Expect to cover initiating, planning, executing, monitoring and controlling and closing, with the subsidiary plans and baselines planning produces and the way they are used afterward. Strong projects show that the student can do more than name processes: each key process is tied to a real document or decision, the baselines agree with each other, the approach suits the work, and at least one change or problem is traced through monitoring and control to a documented decision. Instructors also look for professional responsibility woven into the plan rather than appended.
How this QSO 645 Module 9 final project example is built
The project presents the plan for the dome renewal at Halloran Science Center, a fictional Omaha museum's $4.8 million planetarium project, organized by process group. Initiating covers the business case, charter and stakeholder register. Planning covers the requirements matrix, a 30-week installation schedule fixed to a September 8 reopening, a $4.42 million cost baseline with $380,000 of contingency and the subsidiary plans, including a hybrid approach for show production. Executing, monitoring and controlling and closing follow, each with a table of processes, inputs, tools and outputs. A three-week dome panel delay is worked through change control to an approved $38,000 overtime plan. Boehm and Turner, Badewi and Turner and Simister are cited.
Where the QSO 645 Module 9 rubric puts the points
Marks on the QSO 645 final project usually go to complete coverage of the process groups, accurate use of inputs, tools and techniques and outputs tied to real project documents, consistent baselines, subsidiary plans that fit the project, a sensible choice of approach, a change carried through integrated change control with options and a documented decision, attention to ethics and stakeholder engagement and research used to justify choices. Plans score well when a reader can see the framework working on one project. They lose points for listing processes without application, for baselines that disagree, for a change process that is described but never used or for treating closing as an afterthought. Tables, APA references and professional writing complete the grade.
QSO 645 Module 9 help: the mistakes that cost points
Organize your plan by the five process groups, and in each group pick the processes that matter most for your project. For each, name the main inputs you actually used, the tools or techniques you applied and the outputs you produced, using your own documents rather than generic terms. Make sure the scope, schedule and cost baselines agree. Show where you used a predictive approach and where an adaptive one. Then take one real change, describe the request, analyze its effect on scope, time, cost, quality and risk, give the options and record the decision and the updates it caused. Finish with closing. Final projects often list all forty-nine processes from memory; it is better to apply twenty well than to name every one.
Get QSO 645 Module 9 written to your instructions
Send the QSO 645 capstone brief, any instructor comments so far and the project you are planning. A writer organizes the plan by process group, shows the inputs, tools and outputs behind each key process, keeps scope, schedule, cost, quality, risk, procurement and communication consistent, works a change through integrated change control and supports the reasoning with project research. We write your first QSO 645 project free, in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 645 papers and related MS Project Management samples
- QSO 645 Module 1 Discussion: Five Process Groups in One Dome
- QSO 645 Module 2 Business Case Assignment: Repair, Replace or Go Fully Digital
- QSO 645 Module 3 Requirements Assignment: What Teachers and Visitors Asked For
- QSO 645 Module 4 Discussion: A Hybrid Approach for Show Production
- QSO 645 Module 5 Procurement Assignment: Four Packages, Four Contract Types
- QSO 645 Module 6 Quality Assignment: Acceptance Tests for an Image
- QSO 645 Module 7 Discussion: A Board Member's Relative Wants to Bid
- QSO 645 Module 8 Communications Assignment: Schools, Donors and Members
- QSO 645 Module 10 Discussion: Ready for Situational Questions
- OL 690 Module 9 Final Project: The Consulting Report
- ACC 645 Module 9 Milestone Three: Modifying the Auditor's Report
- QSO 640 Module 2 Project Charter Assignment: The Charter for 16,400 Lights
- OL 500 Module 9 Final Project: Case Study Analysis and Recommendations
QSO 645 Module 9 questions, answered
Where can I find a free QSO 645 Module 9 Final Project sample?
The full QSO 645 Module 9 final project is on this page: an invented museum's planetarium plan organized by process group, with a change request.
What are inputs, tools and techniques and outputs?
The way the PMP framework describes a process: the documents and information it uses, the methods applied and the documents or results it produces.
What is integrated change control?
The process of reviewing every change request, analyzing its effects across the project, approving or rejecting it and updating plans and baselines.
Why organize a project plan by process group?
It shows how the project moves from authorization through planning, execution and control to closing, mirroring the PMP framework.
Who approves changes in integrated change control?
A change control board or the sponsor, within authority levels set in the plan, with the project manager analyzing and recommending.