QSO 640 Module 2 Project Charter Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 640 Module 2 Project Charter Assignment sample writes a charter for a city works project, setting down why it exists, targets an outsider could verify, the outer edge of the work, dated milestones, the money and where it comes from, the assumptions most likely to fail, who holds a stake and how far the project manager may act alone, ready for the sponsor to sign. SNHU QSO 640 (QSO-640) asks MS Project Management students to charter a project in Module 2, the document that formally starts the work and names who answers for it. The project converts every streetlight in Calder Rapids, an invented Iowa city, to LED fixtures on a central control system. The charter turns a council resolution about saving energy into checkable objectives and usable authority.

CourseQSO 640 Project Management
ModuleModule 2
Paper typegraduate assignment drafting the charter that authorizes a public works project, from business case and checkable targets through funding, known risks and the limits of the project manager's decision rights
LengthAbout 1,160 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Project Management
UpdatedOctober 2026

Free sample paper for QSO 640 Module 2

1

Project Charter: Calder Rapids LED Streetlight Conversion

[Student Name]

Southern New Hampshire University

QSO 640: Project Management

Project Charter

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingCalder Rapids, its officials, budget and every figure in this QSO 640 charter are invented.
2

Project Charter: Calder Rapids LED Streetlight Conversion

Purpose and Business Case

Calder Rapids spends about $2.9 million a year to light its streets. About $2.2 million is energy and fixed charges paid to the electric utility, which owns 11,200 of the city's 16,400 streetlights and bills a flat monthly rate per pole, and about $0.7 million is maintenance of the 5,200 lights the city owns. Most fixtures are high-pressure sodium lamps installed between 1985 and 2005. LED fixtures use far less energy, last several times longer and, with a central control system, can report failures and be dimmed late at night. The City Council resolved in June to convert the entire system, expecting to cut lighting costs by about 60 percent, roughly $1.7 million a year, and to repay the project's bond from the savings within about eight years. This charter formally starts that project.

What this page is doingStates why the project exists.
3

Objectives

Project objectives

ObjectiveMeasureTarget
Convert the systemLights converted to LED and reporting to the control system16,400 of 16,400 within 78 weeks of charter approval
Stay within budgetTotal project cost$12.6 million or less, including reserves
Cut operating costEnergy and maintenance cost in the first full year after completionAt least 55% below the current $2.9 million
Improve reliabilityReported outages repaired90% within 48 hours, in the first year after completion
Keep residents' supportLighting complaints logged by the 311 centerBelow 1 per 1,000 lights a month after each district is converted

The objectives deliberately include results that appear after the project ends. Shenhar et al. (2001) found that some dimensions of success, such as the effect on customers and on the organization's business, only become visible months or years after a project closes, while efficiency can be judged at once. The operating cost and reliability measures will be reported by public works for one year after closing.

What this page is doingTurns the purpose into measures.
4

High-Level Scope

The project will purchase the 11,200 utility-owned streetlights and their poles, with the transfer of maintenance responsibility to the city; inventory and map every light in the city's geographic information system; set lighting design standards by street type; run a pilot of about 400 fixtures; procure fixtures and control nodes; contract an installer; convert all cobra-head lights on arterial, collector and residential streets; convert the 1,100 decorative post-top lights in the Riverside historic district with fixtures approved by the Historic Preservation Commission; commission the central control system; and train the city's lighting crew to operate and maintain the new system.

Outside the scope are pole replacement except where a pole fails inspection during installation, lighting in city parks and parking lots, traffic signals, state highway lighting maintained by the Iowa Department of Transportation and any private lighting.

What this page is doingDescribes what the project delivers.
5

Milestones

Major milestones

MilestoneTarget week
Charter approved0
Inventory and lighting standards complete18
Utility purchase agreement signed18
Pilot accepted by public works and council committee28
Installer contract awarded28
First production fixtures delivered44
City-owned and historic district lights converted60
All utility-acquired lights converted74
Control system commissioned and project closed78
What this page is doingGives dated outcomes.
6

Budget and Funding

The project budget is $12.6 million, funded by a $9.8 million general obligation bond, a $1.6 million rebate from the electric utility for efficient lighting and a $1.2 million grant from the state energy office. The budget includes about $2.1 million for the utility purchase, about $6.9 million for fixtures and control nodes, about $2.1 million for installation, $0.5 million for design, the pilot and project management and a contingency reserve of $1.0 million. The detailed cost baseline will be prepared in the planning phase.

What this page is doingSummarizes the money.
7

Assumptions and Constraints

The charter assumes that the utility will sell its lights at depreciated book value, estimated at $2.1 million; that fixture prices will not rise more than 5 percent before ordering; that the installer can convert about 24 lights per crew per day; and that the Historic Preservation Commission will approve a post-top fixture within eight weeks of submission. Kahneman and Lovallo (1993) observed that planners tend to forecast from the details of their own project, which breeds optimism, and recommended comparing plans against the record of similar projects. The installation rate and the 78-week duration were therefore checked against three other Midwestern cities' conversions, two of which ran over by several months.

Constraints include the bond's requirement that funds be spent within three years, the grant's requirement that work be complete by December of next year, a ban on installation work on arterials during the morning and evening rush and the winter months, when crews work fewer hours.

What this page is doingStates what could change the plan.
8

Stakeholders

The main stakeholders are the City Council, which approved the funding; the public works director, as sponsor; the street lighting crew, which will maintain the new system; the finance department, which manages the bond; information technology, which will host the control system; the electric utility; the installer; the Historic Preservation Commission; the police department, which cares about lighting levels at night; neighborhood associations; and residents. A stakeholder analysis and communication plan will be prepared in planning.

What this page is doingNames who has a stake.
9

Roles and Authority

Public works' director sponsors the project and chairs a steering group with the finance director and the city's chief information officer that meets monthly. The project manager, from public works, leads the project team, manages the schedule and budget, and may approve changes costing up to $50,000 each, or moving a milestone by up to two weeks, without steering group approval. Larger changes go to the steering group, and any change to total budget or to the completion date goes to the City Council. Dvir et al. (2003) found that the planning activities most clearly linked to project success were defining requirements and specifications, more than using planning tools, which is why this charter commits the team to finishing the lighting standards before fixtures are ordered.

What this page is doingMakes authority concrete.
10

Known Risks at Charter

Three risks are visible even before planning begins, and the charter names them so the steering group watches them from the first meeting. First, the utility purchase could stall. The utility has never sold lights to a city in Iowa, its valuation of the poles may differ from the city's, and until the agreement is signed the project cannot touch 68 percent of the lights. Second, fixture prices are exposed to import tariffs and to demand from other cities converting at the same time, and the budget holds only a 5 percent allowance for increases before ordering. Third, residents may react badly to the color or brightness of the new light, as they have in other cities, and a pilot that draws complaints could delay the fixture order. Each risk will be analyzed with an owner and a response in the risk register during planning, and the reserve set aside in this charter will be reviewed against that analysis.

What this page is doingFlags what could derail the project early.
11

Approval

By signing below, the sponsor releases the planning phase of the Calder Rapids conversion and allows the project manager to use the project budget within the limits stated above.

Sponsor: Director of Public Works, City of Calder Rapids

Project Manager: Public Works Project Manager

What this page is doingFormally authorizes the project.
12

References

Dvir, D., Raz, T., & Shenhar, A. J. (2003). An empirical analysis of the relationship between project planning and project success. International Journal of Project Management, 21(2), 89-95. https://doi.org/10.1016/S0263-7863(02)00012-1

Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17-31. https://doi.org/10.1287/mnsc.39.1.17

Shenhar, A. J., Dvir, D., Levy, O., & Maltz, A. C. (2001). Project success: A multidimensional strategic concept. Long Range Planning, 34(6), 699-725. https://doi.org/10.1016/S0024-6301(01)00097-8

What the QSO 640 Module 2 instructions ask for

The QSO 640 Module 2 assignment usually asks students to create a project charter for a case or their own project. Expect to include the project's purpose and business case, measurable objectives, a high-level description of scope and deliverables, major milestones, a summary budget, key assumptions and constraints, the main stakeholders, the sponsor and the authority given to the project manager. Strong charters write objectives that are specific and measurable rather than activities, separate what is included from what is not at a high level, give milestones as dated outcomes, state assumptions that could prove false and make the project manager's authority concrete. The charter should be short enough for a sponsor to read and sign, with a brief explanation of the reasoning where the instructions ask for it.

How this QSO 640 Module 2 project charter assignment example is built

The charter starts the LED streetlight conversion in Calder Rapids, a fictional Iowa city replacing 16,400 lights for $12.6 million. Its business case is cutting about $2.9 million a year in energy and maintenance costs by about 60 percent while making lights more reliable. Objectives are measurable: every light converted and on the control system within 78 weeks, spending within budget, outages answered within 48 hours and resident complaints below one per 1,000 lights a month. Scope includes buying 11,200 utility-owned lights and the historic district's 1,100 post-top lights. Milestones, funding, assumptions, constraints, stakeholders and a $50,000 change authority follow. Dvir and colleagues, Shenhar and colleagues and Kahneman and Lovallo inform it.

Where the QSO 640 Module 2 rubric puts the points

The QSO 640 charter rubric generally credits a clear purpose tied to the organization's goals, objectives carrying a number and a deadline, a high-level scope with exclusions, dated milestones, a budget with its sources, realistic assumptions and constraints, an identified sponsor and stakeholders and a defined level of authority for the project manager. Charters stand out when every objective could be checked by someone outside the project. They lose marks for objectives that describe tasks, for scope so broad it promises everything, for milestones with no dates, for missing assumptions or for authority stated only as "manages the project." Clean formatting, a brief rationale and APA references complete the grade.

QSO 640 Module 2 help: the mistakes that cost points

Write the charter for the sponsor, not for yourself. Start with why the project exists and what the organization gets from it, in a sentence or two with numbers. Turn that into three to five objectives someone could check at the end: what, how much and by when. Describe scope at a high level and list a few things that are clearly outside it. Give milestones as results with dates, such as "pilot accepted," not as activities. State the budget and where the money comes from. List assumptions that, if wrong, would change the plan. Name the sponsor and say exactly what the project manager may decide alone. Charters often read like a project plan in miniature; keep detail for later documents and make the charter something a busy executive can sign in ten minutes.

Get QSO 640 Module 2 written to your instructions

Share the QSO 640 Module 2 instructions and your project's details. A writer turns your situation into a signable charter: why the project exists, checkable targets, what sits inside and outside the boundary, dated milestones, money and its sources, the risky assumptions, who has a stake and exactly what the project manager may decide, with project research behind each choice. The first QSO 640 charter costs nothing and normally comes back inside two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 640 papers and related MS Project Management samples

QSO 640 Module 2 questions, answered

Where can I find a free QSO 640 Module 2 project charter sample?

This page has the full QSO 640 Module 2 charter for an invented city's streetlight conversion, with objectives, scope, milestones and authority.

What is a project charter?

A short document that formally authorizes a project, stating its purpose, objectives, high-level scope, milestones, budget, stakeholders and the project manager's authority.

What makes a good project objective?

It is specific, measurable and time-bound, describing a result that can be checked rather than an activity to be done.

Who signs the project charter?

The sponsor, the person or body with authority over the funding and the organization's commitment, often with the project manager.

Why list assumptions in a charter?

Because assumptions that prove false change the plan, and stating them early tells everyone what to watch.