Free sample paper for QSO 640 Module 3
Scope Statement and Work Breakdown Structure: Calder Rapids LED Streetlight Conversion
[Student Name]
Southern New Hampshire University
QSO 640: Project Management
Scope Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Scope Statement and Work Breakdown Structure: Calder Rapids LED Streetlight Conversion
Introduction
The charter for the Calder Rapids LED streetlight conversion gave the project a purpose, a budget of $12.6 million and a target of 78 weeks. Within two weeks of its approval, the project team had already heard several different assumptions about what the project includes. The parks department expected its pathway lights to be converted. A council member asked when the new lights would arrive on a street that has none. The lighting crew assumed that rusted poles would be replaced along the way. Each assumption, if accepted silently, would add cost and time the charter did not contemplate. This paper writes the scope statement, builds a deliverable-based work breakdown structure and sets out how scope changes will be handled.
Scope Statement
The project will produce eight deliverables.
Project deliverables and acceptance criteria
| Deliverable | Acceptance criterion |
|---|---|
| 1. Lighting inventory and GIS map | Every light recorded with location, type, owner, pole condition and circuit; 2% field sample matches records |
| 2. Lighting design standards | Standards by street type adopted by public works director; council committee briefed |
| 3. Utility purchase | Agreement signed; title and maintenance responsibility for 11,200 lights transferred |
| 4. Pilot | About 400 fixtures installed and evaluated; written evaluation accepted by sponsor |
| 5. Converted lights, by district | Each of nine districts: all lights LED, light levels meet standard on 10% sample of streets, every node reporting for 7 days |
| 6. Historic district lights | 1,100 post-top lights converted with fixture approved by Historic Preservation Commission; same light-level and reporting tests |
| 7. Central control system | System hosted by IT, alarms routed to lighting crew, monthly energy report produced |
| 8. Trained maintenance crew | All 9 crew members complete training; crew independently clears 20 test faults |
The acceptance criterion for converted districts deserves explanation. Atkinson (1999) argued that projects judged only on whether they finished on time and on budget can deliver results nobody wanted. Measuring light levels on a sample of streets and requiring a week of fault-free reporting tests whether the lights do their job, not just whether fixtures were hung.
Exclusions
The following are outside the project's scope. Poles will not be replaced, except where a pole fails the installer's structural check while a fixture is being changed; those poles will be reported to the street lighting crew's normal replacement program, which has its own budget. Lighting in parks, trails and city parking lots is excluded, though the standards produced by the project may later be used for them. New lights on streets that have none are excluded, since they require their own design and funding. Lights along state highways, which the Iowa DOT looks after, stay out, as does every privately owned fixture. Changes to the utility's electric rates are excluded, though the project will negotiate the purchase agreement.
Assumptions and Constraints
The scope assumes that the utility's records of its 11,200 lights are accurate to within 3 percent, that existing wiring can be reused for at least 95 percent of lights and that the Historic Preservation Commission will accept a fixture that resembles the current acorn globes. Constraints from the charter remain: the grant deadline, the bond's spending period and limits on work during rush hours and winter.
Work Breakdown Structure
The WBS is organized by deliverable at the second level and by district at the third level for the conversion work. An alternative organized by department, with branches for public works, IT and finance, was considered and rejected. Globerson (1994) showed that the way a WBS is structured changes how the people using it think about the project, and that a structure by function tends to hide how the pieces connect. Organizing by deliverable keeps attention on what the city receives, and organizing installation by district matches how the installer will work and how acceptance will be tested.
WBS summary, levels 1 to 3
| WBS code | Element |
|---|---|
| 1.0 | Calder Rapids LED Streetlight Conversion |
| 1.1 | Project management (charter, plans, reporting, steering group, closing) |
| 1.2 | Inventory and GIS map (field survey, data entry, verification) |
| 1.3 | Design standards (street classification, light levels, color temperature, fixture specification) |
| 1.4 | Utility purchase (valuation, negotiation, agreement, transfer of records) |
| 1.5 | Pilot (site selection, installation, measurement, resident survey, evaluation) |
| 1.6 | Procurement (fixture and node bid, installer bid, contracts) |
| 1.7 | Conversion of districts 1 to 9 (each: notice, installation, measurement, acceptance) |
| 1.8 | Historic district (commission review, fixture approval, installation, acceptance) |
| 1.9 | Control system (hosting, configuration, integration with work orders, commissioning) |
| 1.10 | Training and handover (curriculum, sessions, test faults, documentation) |
Each district branch under 1.7 decomposes into four work packages, and the other branches into three to eight packages, giving about 64 work packages in all. The packages are sized so that each takes between one and six weeks and has a single owner. Project management sits in its own branch so that its cost is visible rather than spread across the others.
WBS Dictionary
Sample WBS dictionary entries
| Field | 1.5.3 Pilot light-level measurement | 1.7.4.2 District 4 installation |
|---|---|---|
| Description | Measure light levels on pilot streets before and after conversion, at night, at points set by the design standard | Replace about 1,750 cobra-head fixtures in District 4 with specified LED fixtures and nodes |
| Owner | City traffic engineer | Installer's project manager |
| Duration and effort | 3 weeks; about 60 hours | 8 weeks; 2 crews |
| Acceptance | Report showing average and minimum levels on each pilot street against standard | All fixtures installed, nodes reporting, poles failing check reported |
| Dependencies | 1.5.2 Pilot installation complete | 1.6.2 Fixtures delivered; 1.7.4.1 Resident notice issued |
Scope Change Control
Two weeks after the scope statement was circulated in draft, the council member for Ward 2 asked the project to add 140 lights on streets in Ward 2 that have none. The request shows why a process is needed. In Calder Rapids each request arrives on a short public works form naming the streets or items affected, the reason and the requester. Within five working days the project manager prices the request, works out how many weeks it adds, notes new risks and checks which other deliverables it touches. Under the charter, the project manager may approve changes up to $50,000 or two weeks; anything bigger needs the steering group, and only the council can move the total budget or the finish date. The Ward 2 request, estimated at about $430,000 including poles and wiring, was declined as outside the project's scope and referred to the capital budget for next year, with a note that the new design standards would apply. Dvir et al. (2003) found that defining requirements and specifications was the planning activity most clearly associated with project success, and the scope statement gives the team a basis for saying no as well as yes.
Conclusion
The scope baseline for the Calder Rapids conversion consists of this scope statement, the work breakdown structure of about 64 work packages and the dictionary. It defines eight deliverables with testable acceptance criteria, excludes the work people were most likely to assume, organizes the project by what the city will receive and gives the team a process for change. The schedule and budget in later modules will be built from these work packages.
References
Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337-342. https://doi.org/10.1016/S0263-7863(98)00069-6
Dvir, D., Raz, T., & Shenhar, A. J. (2003). An empirical analysis of the relationship between project planning and project success. International Journal of Project Management, 21(2), 89-95. https://doi.org/10.1016/S0263-7863(02)00012-1
Globerson, S. (1994). Impact of various work-breakdown structures on project conceptualization. International Journal of Project Management, 12(3), 165-171. https://doi.org/10.1016/0263-7863(94)90032-9
What the QSO 640 Module 3 instructions ask for
The Module 3 assignment in QSO 640 generally asks students to define a project's scope and create a work breakdown structure. Expect to write a scope statement covering the project's deliverables, acceptance criteria, exclusions, assumptions and constraints, then decompose the work into a hierarchy of deliverables and work packages, often with a WBS dictionary describing selected packages. Strong papers state acceptance criteria that someone could test, list exclusions that address the real misunderstandings in the case, organize the WBS around deliverables rather than departments or phases alone, decompose to work packages small enough to estimate and assign, follow the rule that the lower levels add up to the whole and describe how scope changes will be requested, assessed and approved.
How this QSO 640 Module 3 scope assignment example is built
The assignment defines scope for the Calder Rapids LED streetlight conversion, a fictional Iowa city's $12.6 million project. Eight deliverables carry acceptance criteria, such as each district meeting the light-level standard on sampled streets and reporting to the control system for seven days without fault. Exclusions settle arguments over failed poles, park lighting and new lights residents want. A deliverable-based WBS runs four levels to about 64 work packages, organized by deliverable and district rather than department, with dictionary entries for two packages. A change control process is tested when a council member asks for 140 extra lights. Globerson, Dvir and colleagues and Atkinson are cited.
Where the QSO 640 Module 3 rubric puts the points
The QSO 640 scope rubric typically rewards deliverables described clearly, acceptance criteria that can be verified, exclusions that remove real ambiguity, stated assumptions and constraints, a WBS organized by deliverables with consistent decomposition, work packages small enough to estimate and assign, dictionary entries with owners and criteria and a change control process with clear approval levels. Papers stand out when the WBS shows the whole project and nothing extra. They lose points for WBS boxes that are departments or verbs, for missing exclusions, for acceptance criteria such as "to the city's satisfaction," for decomposing some branches far deeper than others or for no process for handling change requests. A legible WBS layout, APA references and clear prose finish the grade.
QSO 640 Module 3 help: the mistakes that cost points
Begin with the deliverables: the things the project hands over at the end. For each, write how you will know it is acceptable, in terms someone could test. Then list exclusions, especially items people have already assumed are included. Split each deliverable into its component outputs, and keep splitting until one person could own and estimate each piece, usually something taking between a few days and a few weeks. Check that every level adds up to the one above and that nothing is missing or doubled. Add a project management branch. Write dictionary entries for a couple of packages. Then explain how a change request will be handled. A common mistake is a WBS that copies the organization chart, which hides the actual work.
Get QSO 640 Module 3 written to your instructions
Share the QSO 640 Module 3 instructions and your project details. A writer prepares a scope statement with deliverables, acceptance criteria, exclusions, assumptions and constraints, builds a deliverable-based work breakdown structure to work-package level with dictionary entries and sets out change control, explaining the choices with project research. Your first QSO 640 assignment is free and typically delivered inside two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 640 papers and related MS Project Management samples
- QSO 640 Module 1 Discussion: Why the Conversion Is a Project
- QSO 640 Module 2 Project Charter Assignment: The Charter for 16,400 Lights
- QSO 640 Module 4 Discussion: Residents Who Found the Lights Too Blue
- QSO 640 Module 5 Schedule Assignment: The Network and Its Critical Path
- QSO 640 Module 6 Cost and Earned Value Assignment: The Budget and the Week 52 Check
- QSO 640 Module 7 Discussion: Fixtures That Failed After Installation
- QSO 640 Module 8 Risk Management Assignment: The Risk Register
- QSO 640 Module 9 Final Project: The Project Management Plan
- QSO 640 Module 10 Discussion: Closing the Project and Its Lessons
- ACC 620 Module 6 Milestone Two: Restricted Stock, Performance Shares and Diluted EPS
- OL 630 Module 7 Milestone Three: Financial Plan and Funding
- OL 751 Module 1 Discussion: A Seat at the Table or the Back Office?
- QSO 510 Module 7 Linear Programming Assignment: Assigning Coaches and Drivers
QSO 640 Module 3 questions, answered
Where can I find a free QSO 640 Module 3 scope and WBS sample?
This page carries the complete QSO 640 Module 3 assignment: a scope statement and work breakdown for an invented city's streetlight conversion.
What is a work breakdown structure?
A hierarchy that divides a project's total scope into deliverables and smaller work packages that can be estimated, scheduled, assigned and controlled.
What is a work package?
The lowest level of a WBS, a piece of work small enough to estimate, schedule and assign to one owner, with clear completion criteria.
What is the 100 percent rule?
The principle that a WBS includes all of the project's work and nothing more, with each level adding up exactly to the level above.
Why does a scope statement list exclusions?
Because stating what the project will not do prevents assumptions that lead to disputes, unplanned work and budget overruns.