QSO 640 Module 5 Schedule Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 640 Module 5 Schedule Assignment sample builds a network schedule from work-package dependencies, calculates early and late dates, float and the critical path, and chooses crashing and fast-tracking options that meet a deadline at the least cost and risk. SNHU QSO 640 (QSO-640) covers project time in Module 5 of its MS Project Management core course. The project is the LED streetlight conversion in Calder Rapids, an invented Iowa city that promised its council a 78-week finish. The first network says 84 weeks. The paper finds which activities drive that date, prices three ways to recover the difference and protects the result with a buffer rather than padding.

CourseQSO 640 Project Management
ModuleModule 5
Paper typegraduate assignment building a network schedule from work-package dependencies, calculating early and late dates, float and the critical path, and choosing crashing and fast-tracking options to meet a deadline at the least cost and risk
LengthAbout 1,230 words, 7 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Project Management
UpdatedOctober 2026

Free sample paper for QSO 640 Module 5

1

Eighty-Four Weeks Against a Promise of Seventy-Eight: Scheduling the Calder Rapids Conversion

[Student Name]

Southern New Hampshire University

QSO 640: Project Management

Schedule Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe activities, durations, costs and schedule for Calder Rapids in this QSO 640 assignment are invented.
2

Eighty-Four Weeks Against a Promise of Seventy-Eight: Scheduling the Calder Rapids Conversion

Introduction

Calder Rapids promised its council a converted lighting system within 78 weeks of the charter, a date the state energy grant depends on. That figure came from the council resolution and from other cities' experience, not from a schedule. This paper builds the schedule from the work breakdown structure prepared in Module 3, finds the critical path, compares ways to shorten it and recommends a baseline schedule protected by a buffer.

What this page is doingStates the scheduling problem.
3

Activities and Dependencies

For the summary schedule, the 64 work packages are grouped into twelve activities. Durations were estimated by the package owners, and the installation rate of 24 lights per crew per day was checked against the installer's records from two other cities.

Summary activities, durations and predecessors

CodeActivityWeeksPredecessors
ACouncil approval of funding and contracts4none
BUtility purchase agreement14A
CInventory and GIS mapping8A
DDesign standards6C
EPilot installation and evaluation10D
FInstaller bid and award10D
GFixture and node order and delivery16E
HConvert 4,100 city-owned lights14F, G
IConvert 11,200 utility-acquired lights30B, F, G
JHistoric district: commission review8D
KHistoric district: convert 1,100 lights12F, G, J
LControl system commissioning6H, I, K
MTraining, handover and closing4L

Fixtures are ordered after the pilot because the pilot decides the color and output of the fixtures; Module 4 showed why that dependency is real.

What this page is doingSets out the network.
4

Forward and Backward Pass

Kelley (1961) set out the mathematical basis of critical-path planning, in which each activity's earliest start is the latest of its predecessors' earliest finishes and each latest finish is the earliest of its successors' latest starts, working back from the project's end. Applying the forward pass: A finishes at week 4; B at 18; C at 12; D at 18; E at 28; F at 28; G at 44; J at 26. H, which needs F and G, runs from 44 to 58. I, which needs B, F and G, runs from 44 to 74. K, which needs F, G and J, runs from 44 to 56. L waits for H, I and K and runs from 74 to 80, and M from 80 to 84.

Early and late dates and float, in weeks

CodeES weekEF weekLS weekLF weekFloat, weeks
A04040
B418304426
C4124120
D121812180
E182818280
F1828344416
G284428440
H4458607416
I447444740
J1826546236
K4456627418
L748074800
M808480840

Activities A, C, D, E, G, I, L and M form the critical path; together they take 84 weeks, six more than the council was promised. The finding surprised the team. Most attention had gone to the utility purchase, which everyone expected to be slow, yet it has 26 weeks of float; the pilot and the fixture lead time drive the date.

What this page is doingCalculates the dates.
5

What Float Means for Management

Float tells the team where it can absorb trouble. The utility negotiation can slip by up to 26 weeks without delaying completion, so the project manager should not concede on price to speed it up. The historic district's commission review has 36 weeks of float, enough to allow a second round if the first fixture is rejected. The installer award has 16, which allows a rebid if prices come in high. Float is shared along a path, however: if H uses its float, the slack available to later activities on that path shrinks.

What this page is doingInterprets noncritical activities.
6

Options for Shortening

Compression options on the critical path

OptionActivityWeeks savedAdded costCost per weekAdded risk
Third installation crewI6about $165,000$27,500Low; crew available from installer's other contract
Air freight for first fixture lotG2about $60,000$30,000Low; only first 30% of fixtures
Order residential fixtures at week 25, before pilot closesE to G overlap3smallunder $5,000Moderate; order placed with about 70% of pilot data

Adding a crew to activity I saves six weeks at the lowest cost per week among the crashing options and carries little risk, because the installer has a third crew finishing another city's work. Air freight for the first lot is slightly more expensive per week and saves less. The overlap is a form of fast-tracking: the residential fixture order would be placed three weeks before the pilot evaluation is formally accepted, once the color and dimming results are clear but before the final survey report. Its cost is low, but if the final evaluation changed the specification, part of the order would need to be modified.

After crashing I to 24 weeks, the paths must be rechecked. I would run from 44 to 68, so L could start at 68. H finishes at 58 and K at 56, so neither becomes critical. With the overlap, G starts at 25 and ends at 41, I runs 41 to 65, L 65 to 71 and M 71 to 75.

What this page is doingCompares compression choices.
7

Recommendation

The recommended schedule adds the third crew and the fixture order overlap, giving a planned finish at week 75 for about $170,000. Air freight is held as a contingency option. The three weeks between the planned finish and the 78-week commitment stay in one pool at the end of the Calder Rapids schedule, under the project manager's control, instead of being handed out task by task. Herroelen and Leus (2005) review how scheduling approaches handle uncertainty and note that a schedule built from single-point estimates will almost certainly be wrong in detail, so the question is how to protect it. Steyn (2001) walks through the logic of critical chain scheduling: strip the hidden cushions out of each task estimate and hold the time in one shared reserve at the tail, since a cushion handed to a single task tends to get spent whether it is needed or not. Consumption of the buffer will be reported monthly to the steering group: if more than half is used before the installation phase is half complete, the air freight option will be triggered.

What this page is doingChooses the compression and a buffer.
8

Risks to the Schedule

The fixture lead time depends on the manufacturer's production slot and on import timing for some components, which the risk register in Module 8 will address. Winter reduces installation hours; the schedule assumes installation of utility lights runs from late winter through summer, so a slip of more than two months in the fixture order would push installation into the next winter and cost far more than the buffer. The overlap of the pilot and the fixture order also depends on the pilot's results being clear by week 25.

What this page is doingNames what could still move the date.
9

Conclusion

The network schedule shows that the Calder Rapids conversion would take 84 weeks as planned, driven by the pilot and fixture lead time rather than by the utility purchase most people worried about. Adding a third installation crew and placing the residential fixture order three weeks early bring the planned finish to week 75 at modest cost, and a three-week buffer at the end protects the 78-week commitment better than padding every task. This becomes the schedule baseline against which progress will be measured.

What this page is doingSummarizes the baseline.
10

References

Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289-306. https://doi.org/10.1016/j.ejor.2004.04.002

Kelley, J. E., Jr. (1961). Critical-path planning and scheduling: Mathematical basis. Operations Research, 9(3), 296-320. https://doi.org/10.1287/opre.9.3.296

Steyn, H. (2001). An investigation into the fundamentals of critical chain project scheduling. International Journal of Project Management, 19(6), 363-369. https://doi.org/10.1016/S0263-7863(00)00026-0

What the QSO 640 Module 5 instructions ask for

For Module 5, QSO 640 supplies or asks for an activity list and wants a working schedule built from it, identify the critical path and analyze ways to shorten the project. Expect to define activities and their dependencies, estimate durations, draw a network diagram, calculate early and late start and finish times and float, identify the critical path and evaluate crashing, which adds resources at a cost, and fast-tracking, which overlaps activities at a risk. Strong papers show the calculations clearly enough to check, explain what the float on noncritical activities means for managing them, compare compression options by cost per week saved and by the risk each adds, notice when shortening one path makes another critical and say how the schedule will be protected against the uncertainty in every estimate.

How this QSO 640 Module 5 schedule assignment example is built

The assignment schedules the LED streetlight conversion in Calder Rapids, a fictional Iowa city replacing 16,400 lights. Twelve summary activities and their dependencies give a forward and backward pass of 84 weeks against the charter's 78. The critical path runs through inventory, design standards, the pilot, the fixture order and installing the 11,200 lights bought from the utility; the utility purchase has 26 weeks of float. Three options are priced: a third crew saving six weeks for about $165,000, air freight saving two weeks for about $60,000 and ordering residential fixtures three weeks before the pilot closes. The recommendation gives a week-75 finish with a three-week buffer. Kelley, Herroelen and Leus and Steyn are cited.

Where the QSO 640 Module 5 rubric puts the points

Marks on the QSO 640 schedule assignment usually go to correct dependencies, accurate forward and backward pass calculations, correctly identified float and critical path, a clear network diagram or table, compression options compared on cost per week and on risk, attention to paths that become critical after compression, a recommendation that meets the deadline with a sensible protection against uncertainty and research that supports the reasoning. Papers stand out when the numbers lead to a choice the reader would not have guessed. They lose points for arithmetic errors, for treating every activity as critical, for crashing activities that are not on the critical path or for meeting the deadline with no margin at all. Tables, APA citations and clear explanation complete the grade.

QSO 640 Module 5 help: the mistakes that cost points

List the activities, how long each takes and what each must wait for. Draw the network, then work forward to find each activity's earliest start and finish and backward from the end to find the latest. Float is the difference; zero float marks the critical path. Check your arithmetic twice. If the project is too long, look only at critical activities for savings. For each option, work out the cost per week saved and what new risk it adds. Shorten in the cheapest steps and recheck the paths after each step, since another path may become critical. Finally, protect the finish with a buffer rather than adding a little to every task. Papers often crash the first activities they see, even ones with weeks of float, which spends money and saves nothing.

Get QSO 640 Module 5 written to your instructions

Share the QSO 640 Module 5 instructions and your activity list. A writer sets dependencies and durations, draws the network, runs the forward and backward passes, reports float and the critical path, compares crashing and fast-tracking options by cost and risk, recommends a schedule with a buffer and explains each step with scheduling research. The opening QSO 640 assignment is written for free, often inside two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 640 papers and related MS Project Management samples

QSO 640 Module 5 questions, answered

Where can I find a free QSO 640 Module 5 schedule sample?

This page holds the full QSO 640 Module 5 assignment: the network, critical path and compression choices for an invented city's streetlight project.

What is the critical path in project management?

The chain of linked tasks with no slack at all; because it runs longest end to end, it fixes the earliest date the whole project can finish.

What is float in a project schedule?

Spare time: how many weeks a task may slide before the end date moves, worked out as late start minus early start.

How do crashing and fast-tracking each shorten a schedule?

Crashing adds resources to critical activities at extra cost; fast-tracking overlaps activities that would normally run in sequence, adding risk.

Why put a buffer at the end of a schedule?

A shared buffer protects the finish date against overruns on any critical activity more efficiently than adding padding to each task.