Free sample paper for QSO 640 Module 10
Module Ten Discussion
Week 81, and Four Rules for the Next Project
We commissioned the last streetlight in Calder Rapids at week 81, one week inside the re-baselined finish of 82 and three weeks past the original commitment of 78. The final cost was about $12.55 million, within the $12.6 million budget only because the steering group deferred the control system's advanced reporting module. In the first three months, energy use for street lighting fell about 63 percent, beating the 55 percent objective, outages were repaired within 48 hours 93 percent of the time and complaints settled near 0.6 per 1,000 lights a month. The installer's punch list of 212 items is cleared, final payment has been released, warranties are with public works and the lighting crew passed its 20-fault test.
First, show residents the light before writing the standard; our pilot complaints cost three weeks. Second, put quality checks at the pole from the first day; the node failures cost money and trust. Third, report earned value from the first month, not after installation begins; finance's "below plan" comfort hid the slip. Fourth, ask for a grant extension the week the forecast slips, not when it becomes unavoidable.
Williams (2008) surveyed project managers and reviewed research on project learning and concluded that organizations often fail to carry lessons from one project to the next, partly because project teams are temporary and disband just as the lessons become clear. Schindler and Eppler (2003) reviewed methods for capturing project knowledge and noted that reviews held only at the end tend to produce documents nobody consults. So we did not write a lessons-learned report alone. Each lesson became a rule in the city's capital project manual: a resident preview for any project that changes what people see from their homes, a quality checklist at the point of work, earned value reporting from month one and a rule to notify any funder within two weeks of a forecast slip. The parks department's trail lighting project, which starts next spring, has adopted all four, and our traffic engineer will sit on its team.
I came into this project confident with schedules and nervous about people. The research suggests successful project managers need a different blend of intellectual, managerial and emotional strengths depending on the project (Müller & Turner, 2010). Mine shifted. I learned to lead installers, IT staff and a historic commission that did not report to me, mostly by listening first and deciding in public.
How does your organization make sure a lesson reaches someone who never worked on the project?
References
Müller, R., & Turner, R. (2010). Leadership competency profiles of successful project managers. International Journal of Project Management, 28(5), 437-448. https://doi.org/10.1016/j.ijproman.2009.09.003
Schindler, M., & Eppler, M. J. (2003). Harvesting project knowledge: A review of project learning methods and success factors. International Journal of Project Management, 21(3), 219-228. https://doi.org/10.1016/S0263-7863(02)00096-0
Williams, T. (2008). How do organizations learn lessons from projects: And do they? IEEE Transactions on Engineering Management, 55(2), 248-266. https://doi.org/10.1109/TEM.2007.912920
What the QSO 640 Module 10 instructions ask for
The final QSO 640 discussion usually asks students to reflect on project closing and on what they have learned about managing projects. Expect to describe how a project is formally closed, evaluate the project against its objectives, identify lessons learned and explain how they will be shared, often with a reflection on your own development as a project manager. Strong posts give an honest scorecard rather than a celebration, separate lessons about the project from lessons about the organization, and, most important, say how each lesson will reach the next project, since lessons recorded but never used change nothing. A personal reflection should name a specific skill and what built it. Replies should ask a classmate how their lessons will reach someone who never worked on the project.
How this QSO 640 Module 10 discussion example is built
The post reports that the LED streetlight conversion in Calder Rapids, a fictional Iowa city, finished at week 81 against a re-baselined 82, at about $12.55 million after deferring an advanced reporting module, with energy use down about 63 percent and complaints near 0.6 per 1,000 lights a month. The writer names four changes: show residents the light before setting the standard, check quality at the pole from day one, report earned value from the start and request a grant extension the week a forecast slips. Each becomes a rule in the city's capital project manual and a checklist for next spring's park lighting project. The writer reflects on leading without authority. Williams, Schindler and Eppler and Müller and Turner are cited.
Where the QSO 640 Module 10 rubric puts the points
Credit in the last QSO 640 thread typically goes to a clear account of how the project closed, an honest evaluation against the original objectives, specific lessons supported by events, a mechanism that carries each lesson to future projects, a reflection on the writer's development as a project manager and at least two studies of how projects learn. Admitting misses plainly, without excuses, lifts a post. They lose credit for a list of lessons with no plan to use them, a scorecard that only reports successes, generic lessons such as "communicate more" or a reflection with no specifics. Replies that test whether a classmate's lessons will survive staff turnover earn the strongest marks. APA citations and a concise post finish the grade.
QSO 640 Module 10 help: the mistakes that cost points
Start with the scorecard: each original objective, the target and the result, including the ones you missed. Then list three or four lessons, each tied to something that actually happened. For each, ask who needs to know it and how it will reach them: a checklist, a template, a training session, a rule in a manual, a person who joins the next project. Lessons written into a report and filed are rarely read. Then reflect on yourself: what can you do now as a project manager that you could not do before, and what taught you? Be specific. Posts often stop at "lessons learned" as a heading; the useful part is the path from the lesson to the next project's first meeting.
Get QSO 640 Module 10 written to your instructions
Paste the QSO 640 Module 10 prompt and describe a project you are closing or have closed. A writer judges the result against the original objectives, identifies what went well and what should change, turns each lesson into a specific practice the organization can adopt, reflects on your growth as a project manager and draws on project learning research, then a closing question. Your first QSO 640 post is free and generally arrives in two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 640 papers and related MS Project Management samples
- QSO 640 Module 1 Discussion: Why the Conversion Is a Project
- QSO 640 Module 2 Project Charter Assignment: The Charter for 16,400 Lights
- QSO 640 Module 3 Scope Assignment: What Is In, What Is Out and the Work Breakdown
- QSO 640 Module 4 Discussion: Residents Who Found the Lights Too Blue
- QSO 640 Module 5 Schedule Assignment: The Network and Its Critical Path
- QSO 640 Module 6 Cost and Earned Value Assignment: The Budget and the Week 52 Check
- QSO 640 Module 7 Discussion: Fixtures That Failed After Installation
- QSO 640 Module 8 Risk Management Assignment: The Risk Register
- QSO 640 Module 9 Final Project: The Project Management Plan
- QSO 511 Module 6 Predictive Model Assignment: Flagging Long Repairs at Drop-Off
- MKT 665 Module 8 Story Measurement Assignment: Measuring a Storytelling Campaign
- OL 500 Module 3 Discussion: Motivation Theories
- MKT 660 Module 7 Discussion: Cause-Related Marketing and Corporate Partnerships
QSO 640 Module 10 questions, answered
Where can I find a free QSO 640 Module 10 Discussion sample?
This page holds the full QSO 640 Module 10 post on closing a city's LED streetlight project and making its lessons stick.
What happens during project closing?
Deliverables are accepted, contracts and payments are completed, records are archived, resources are released, results are reported and lessons are captured.
Why are lessons learned often not used?
Because they are written at the end when the team is dispersing, stored where nobody looks and not built into the processes the next project follows.
How can an organization make lessons learned stick?
By turning them into checklists, templates, standards or training, and by involving people from past projects in the planning of new ones.
Should a closing post include personal reflection?
Usually yes; most prompts ask what you learned as a project manager, with specific skills and the experiences that built them.